First Notice | | 1/30/2008 | 3/7/2008 | | DONE |
|
|
|
|
First Notice | | 1/30/2008 | 3/7/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/30/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/30/2008 | | |
|
|
|
|
BLD-Final | 1/24/2008 | 1/25/2008 | 1/25/2008 | A | PASS |
Mike Jordan
|
|
|
Cornel ###-#### or cell ###-####
|
FIRE-Final Inspection | 1/24/2008 | 1/25/2008 | 1/25/2008 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 1/11/2008 | 1/15/2008 | 1/15/2008 | A | FAIL |
Mike Jordan
|
|
|
fire inspection also scheduled//Cornel Larson ###-####, cell # ###-#### will be here from 9am - 12:30. Provide door hardware on exit doors to meet exiting requirements and remove or cover exit signs on doors with no hardware.
|
FIRE-Final Inspection | 1/11/2008 | 1/15/2008 | 1/15/2008 | A | FAIL |
Troy Cobbley
|
|
|
Tag the fire extinguishers, provide hardware on the required exit doors, cover the "exit" text on the doors that are not going to be used for exits and repair the trouble signals on the fire alarm panel. Also repair the fire dept access signs at the property entrances.
|
Issue PAID IN FULL permit | | | 1/11/2008 | | DONE |
|
|
|
|
Application received | | | 1/9/2008 | | |
|
|
|
|
Plan assigned to (R_H) | 1/9/2008 | | 1/9/2008 | | DONE |
Ron Hill
|
|
|
|
Routing - PLAN CHECK | 1/9/2008 | | 1/9/2008 | | PASS |
Ron Hill
|
|
|
|
Routing - PLAN CHECK | 1/9/2008 | | 1/9/2008 | | PASS |
Ron Hill
|
|
|
|
Case Summary (BLD) | | | 1/9/2008 | | DONE |
|
|
|
|
1st review completed | | | 1/9/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/9/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/9/2008 | | DONE |
|
|
|
|
Telephone call | | | 1/9/2008 | | |
|
|
|
tlk to moe kupaei ###-#### that permi and fees are ready to be picked up
|
Permit Ready to Issue | | | 1/9/2008 | | |
|
|
|
|