Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD08-00103
StatusFinaled
Name R & O CONSTRUCTION
Site Address 10500 W OVERLAND RD
Project NameFIVE MILE PLAZA
Customer Number 
ePlanReviewNo
Description
(ALBERTSONS STORE #0160)(FIVE MILE PLAZA) A phased remodel to an existing 51,100 sq. ft. grocery store building located at the west end of an existing shopping center per approved plans. Work to include some interior demolition work, some new interior walls and doors, updating some product fixtures/equipment, new suspended aisle markers, [concrete slab work over new trenches for plumbing, electrical, or refridration,] new interior finish and decor elements, some new suspended ceiling work, some new suspended walls/soffits, exterior site work, patch and repair existing asphalt, new exterior paint, minor fire sprinkler and alarm work, mechanical work, plumbing work, and electrical work. NOTE: This building was constructed in Ada County in 1978 and annexed into Boise City on 12/30/99. NOTE: This building is fully fire sprinklered for area increase. A letter of completion is required to final this permit.Reference MIS08-00027 for completion of upgrade agreement bld04-02214**TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD3/3/20093/3/20093/6/2009 DONE
DetailsAlexandra L. DeYoung
Second Notice has not been responded to.
Second Notice BLD1/29/20091/29/20093/3/2009 DONE
DetailsJim Toombs
First Notice has not been responded to.
First Notice1/15/20091/15/20091/29/2009 DONE
DetailsMike Jordan
BLD-Final1/14/20091/15/20091/15/2009PPASS
DetailsMike Jordan
chad Phone #: ###-####
DOC - Permit Finaled1/15/20091/15/20091/15/2009PPASS
DetailsMike Jordan
Letter of compliance was issued.
BLD-Final1/9/20091/12/20091/14/2009ANR
DetailsMike Jordan
Zoning Approval1/9/20091/9/20091/12/2009 DONE
DetailsJosh Wilson
BLD-Final1/9/20091/9/20091/9/2009PFAIL
DetailsMike Jordan
chadd Phone #: ###-#### Note: please call 1/2 hr prior to inspection . Needs zoning final and to resolve the exp. mech. permit issue. Also needs to get fire final on racking permit done prior to this permit being finaled. Needs to provide smoke index and flame spread data for foam insul in new walk in cooler.
FIRE-Final Inspection1/8/20091/9/20091/9/2009APASS
DetailsTroy Cobbley
Life safety passed.
FIRE-Final Inspection1/6/20091/7/20091/7/2009AFAIL
DetailsTroy Cobbley
Need the project related fire alarm permit finaled. Also need the exit discharge lights installed at both main exits and the exit sign, corridor emergency light and exit discharge light repaired at/in the north exit corridor at the meat department. The west exterior exit door out of the flower service area needs the large metal bar/deadbolt/padlock removed.
FIRE-Final Inspection12/30/200812/31/200812/30/2008ACANC
DetailsTroy Cobbley
chad Phone #: ###-#### Inspection cancelled from web by: Patricia Smith
FIRE-Final Inspection8/11/20088/12/20088/12/2008APART
DetailsTroy Cobbley
The Pizza area is ok to occupy. Todays inspection was for this area only.
BLD-Final8/10/20088/11/20088/11/2008ANR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/10/2008 at 10:20:22 PM.
BLD-Framing/Rough-in7/8/20087/8/20087/8/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 7/8/2008 at 2:04:31 AM. screws removed from top track of soffitt at seafood area and supported from structure. ok to cover.
BLD-Framing/Rough-in7/7/20087/7/20087/7/2008PFAIL
DetailsMike Jordan
Soffitt at seafood area. needs to support top track from structure.
Case Summary (BLD)  6/18/2008 DONE
BLD-Framing/Rough-in6/11/20086/11/20086/11/2008PPASS
DetailsMike Jordan
r & o Phone #: ###-####. Interior framed steel stud walls for coinstar machine and cigarrette sales.
BLD-Framing/Rough-in6/5/20086/5/20086/5/2008PPASS
DetailsMike Jordan
Charlie Phone #: ###-####furout walls in new pizzaria and soffitt at pharmacy.
BLD-Framing/Rough-in6/4/20086/5/20086/5/2008ANR
DetailsMike Jordan
bob\\this is for a soffit inspection Phone #: ###-####. no one on jobsite, trailer locked. Noted to bob on phone that he would have to reschedule for this afternoon or when someone would be here.
BLD-Framing/Rough-in5/12/20085/13/20085/13/2008APART
DetailsJim Storey
dan Phone #: ###-#### angled wall and two sides of box next to delli ok to cover noted area on aproved plan. need to verify what is to be done on the other permits listed per the up-grade agreement. not clear on the plan that I could identify at this time. contractor to contact arch.
BLD-Framing/Rough-in5/12/20085/12/20085/12/2008PCANC
DetailsMike Jordan
dan Phone #: ###-####
Issue PAID IN FULL permit  4/22/2008 DONE
Inspection Record Card- Bld  4/9/2008 DONE
Telephone call  4/9/2008 DONE
left vm for jeffrey king at ###-#### - permit ready and fees given - also need rce# and rp name
Permit Ready to Issue  4/9/2008 DONE
Plan assigned to (TLW)2/4/2008 4/8/2008 PASS
DetailsTim L. Woodard
4/8/2008 15:51:57 TLW - activity updated through activity BLDA022 from case BLD08-00103.
Routing - PLAN CHECK4/3/2008 4/8/2008 PASS
DetailsTim L. Woodard
Plans approved with redlines.
PLANS/APPL TAKEN TO FRONT DESK  4/8/2008 DONE
Routing - FIRE3/28/2008 4/3/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  4/3/2008 PASS
Routing - PLAN CHECK3/28/2008 3/28/2008 PASS
DetailsTim L. Woodard
Per approved plans, redlines, and Plans review report.
Routing - PLAN CHECK2/8/2008 2/18/2008 FAIL
DetailsTim L. Woodard
Previous Remodel not finaled
1st review completed  2/18/2008 DONE
Previous BLD04-02214 not finaled. MIS permit pulled to access completeness. MIS08-00027. Will not proceed with this BLD until old BLD is Finaled.
Routing - PLANNING2/7/2008 2/8/2008 PASS
DetailsJosh Wilson
Routing - PLUMBING2/6/2008 2/7/2008 PASS
DetailsBill VanDegrift
cross connection survey will be conducted prior to final. indirect big dipper into s.s. connected floor sink. per plans and 2003 upc.
Routing PW Environmental2/5/2008 2/6/2008 PASS
DetailsWalt Baumgartner
substitution by CTA Engineering noted. Installing Big Dipper 15gpm electro mechanical in pizza area. New cutsheet attached to both sets of plans by WAB.
Routing - PUBLIC WORKS2/4/2008 2/6/2008 PASS
DetailsBeverly Hall
Routing - Erosion and Sediment2/6/2008 2/6/2008 PASS
DetailsSteven Webb
Need rp prior to issuance of permit. Plan waiver approved with attached conditions. Refer to ESC08-00035.
Routing PW Sewer Rating2/5/2008 2/5/2008 PASS
DetailsLouise Waldorf
Pending Assignment by MYS1/17/2008 2/4/2008 DONE
DetailsMarlene Southard
2/4/2008 14:06:08 MYS - activity updated through activity BLDA185 from case BLD08-00103.
Plans ACCEPTED BY PLAN TECH  1/17/2008  
Recd Pcfee & Taken To Pln CK  1/17/2008 DONE
Application received  1/16/2008