Third Notice BLD | 9/22/2008 | 9/22/2008 | 11/21/2008 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 8/11/2008 | 8/11/2008 | 9/22/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/10/2008 | 8/11/2008 | | DONE |
|
|
|
|
BLD-Final | 6/10/2008 | 6/10/2008 | 6/10/2008 | P | PASS |
Mike Jordan
|
|
|
ed Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 6/10/2008 | 6/10/2008 | 6/10/2008 | P | PASS |
Troy Cobbley
|
|
|
fire life safety passed
|
Permanent Occupancy | | | 6/10/2008 | | DONE |
|
|
|
|
FIRE-Final Inspection | 6/5/2008 | 6/6/2008 | 6/6/2008 | P | FAIL |
Troy Cobbley
|
|
|
Overbooked and the project related fire alarm permit is not ready.
|
BLD-Framing/Rough-in | 4/8/2008 | 4/9/2008 | 4/9/2008 | A | PASS |
Mike Jordan
|
|
|
randy Phone #: ###-####. interior wood framed walls ok. Also went over other requirements for E occ with contractor and all red lined items. Also noted to contraxctor that shell and core not finaled.
|
Issue PAID IN FULL permit | | | 3/27/2008 | | DONE |
|
|
|
|
Routing - FIRE | 3/17/2008 | | 3/18/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - PLAN CHECK | 3/18/2008 | | 3/18/2008 | | PASS |
Dan Stuart
|
|
|
To permit desk to issue
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/18/2008 | | PASS |
|
|
|
|
Print Occupancy Form | | | 3/18/2008 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 3/18/2008 | | DONE |
|
|
|
|
Telephone call | | | 3/18/2008 | | DONE |
|
|
|
Randy was called permit ready and fee given ///dld
|
Plan assigned to (DRS) | 2/6/2008 | | 3/18/2008 | | PASS |
Dan Stuart
|
|
|
3/18/2008 09:51:48 DRS - activity updated through activity BLDA022 from case BLD08-00125.
|
Plan resubmittals received | | | 3/17/2008 | | DONE |
|
|
|
Received 1 project letter,and 2 copies of sheets A2.0,A9.0 taken to Dan S.
|
Routing - PLAN CHECK | 3/13/2008 | | 3/17/2008 | | PEND |
Dan Stuart
|
|
|
Resubmittals of 3/17/08 inserted into plans. No further submittals required. Routing to fire code analyst for review.
|
Plan resubmittals requested | | | 3/13/2008 | | DONE |
|
|
|
Remaining code items needing to be addressed e-mailed to architect, i.e. clearance at door to accessible restrooms & drinking fountain floor clearance removed by actions for corrections to drinking fountain & drinking fountain requirement for high and low fountains not provided and indicated on plans.
|
Routing - PLAN CHECK | 2/22/2008 | | 3/13/2008 | | FAIL |
Dan Stuart
|
|
|
Resubmittals of 3/6/08 were incomplete. Two items remain to be corrected to provide code compliance due to changes made to plans with resubmittals or corrections not shown on plans in resubmittals. Plan review items needing correction e-mailed to architect with copy to Randy Callies.
|
Plan resubmittals received | | | 3/7/2008 | | |
|
|
|
received project letter from the architects office (2) pages & "2" sheets each of AO.O, A2.O, A9.O, & E2.O--plans taken to Dan Stuart
|
1st review completed | | | 2/22/2008 | | FAIL |
|
|
|
Failed Plan Check, Fire
|
Routing - FIRE | 2/20/2008 | | 2/22/2008 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
Plan resubmittals requested | | | 2/20/2008 | | DONE |
|
|
|
Copy of plan review corrections e-mailed to architect.
|
Routing - PLAN CHECK | 2/7/2008 | | 2/20/2008 | | FAIL |
Dan Stuart
|
|
|
Plan review corrections e-mailed to architect, Mark Sanders. Routing plans to fire code analyst for review.
|
Plan resubmittals received | | | 2/19/2008 | | |
|
|
|
Received 1 cover letter, 1 monthly menu, 1 drawing and taken to Dan Stuart to talk to///2-19-08 @ 10:45 BAS
|
Plan resubmittals received | | | 2/19/2008 | | |
|
|
|
received transmittal and three copies of sheet A2.0; taken to Dan Stuart
|
Routing - PLANNING | 2/6/2008 | | 2/7/2008 | | PASS |
Sue Hansen
|
|
|
CUP07-00227
|
Routing - PUBLIC WORKS | 2/6/2008 | | 2/6/2008 | | PASS |
Beverly Hall
|
|
|
|
Pending Assignment by MYS | 1/23/2008 | | 2/6/2008 | | DONE |
Marlene Southard
|
|
|
2/6/2008 12:07:47 MYS - activity updated through activity BLDA168 from case BLD08-00125.
|
Routing Off Site - C.D.H | 2/4/2008 | | 2/6/2008 | | PASS |
Barbara Stitt
|
|
|
Plans given to Mark Sanders to get Central District Health stamp and signature//Plans returned from Mark Sanders with Central District Health stamp and signature///2-6-08 @ 9:45am BAS
|
Routing PW Sewer Rating | 2/6/2008 | | 2/6/2008 | | PASS |
Louise Waldorf
|
|
|
|
Application received | | | 1/23/2008 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/23/2008 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/23/2008 | | |
|
|
|
|