Permit Information
Permit NumberBLD08-00130
StatusFinaled
Name THE CHRISTENSEN CORPORATION
Site Address 950 W BANNOCK ST Unit: 1050
Project NameClearwater Advisors Expansion
Customer Number 
ePlanReviewNo
Description
(Clearwater Advisors Expansion) Add open office, offices, Conferance room,new restroom. Ext 1hr corridor and install 3 20 min doors. This(10,922 square feet) office tenant space on the 10th story of a high-rise building. Work is to include interior Nordwall demountable nonbearing partitions, interior doors, sidelights, millwork, and finishes. The access floor system and the suspended ceilings were installed under permit BLD05-02939. The shell and core, including the core restrooms, were constructed under permit BLD04-02348. The work is required to comply with the approved drawings, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  11/6/2015 DONE
Third Notice BLD9/22/20089/22/20089/30/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD8/11/20088/11/20089/22/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 7/16/20088/11/2008 DONE
BLD-Final7/15/20087/16/20087/16/2008APASS
DetailsDave Hannah
tucker Phone #: ###-#### ok for perm occ
Permanent Occupancy UNPAID FEE  7/16/2008 DONE
DetailsTisha Gallop
FIRE-Final Inspection6/19/20086/19/20086/20/2008PPASS
DetailsForrest France
Fire life safety inspection completed satisfactory, inspection passed.
BLD-Final6/19/20086/20/20086/20/2008APART
DetailsDave Hannah
tucker Phone #: ###-#### ok for temp occ needs to fix ada restroom and change swing on lobby doors
BLD-Conference4/14/20084/15/20084/15/2008APASS
DetailsDave Hannah
tucker Phone #: ###-####
BLD-Framing/Rough-in4/11/20084/11/20084/11/2008PPART
DetailsDave Hannah
mario Phone #: ###-####
BLD-Other3/24/20083/25/20083/25/2008APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 3/24/2008 at 8:59:34 PM. Contact: ###-####. ceiling grid needs clips or spreader bars around new area
BLD-Framing/Rough-in2/27/20082/27/20082/27/2008PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 2/27/2008 at 8:57:08 AM. Contact: ###-####. cooidor ext on north side ok to cover
BLD-Framing/Rough-in2/19/20082/19/20082/19/2008PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 2/19/2008 at 8:46:23 AM. Contact: ###-####.south side restroom and corridor wall ok to cover
Telephone call  2/8/2008 DONE
left vm for tucker anderson at ###-#### - permit ready and fees given
Permit Ready to Issue  2/8/2008 DONE
Issue PAID IN FULL permit  2/8/2008  
Routing - PLAN CHECK2/7/2008 2/7/2008 PASS
DetailsDave Hannah
PLANS/APPL TAKEN TO FRONT DESK  2/7/2008  
PLANS/APPL TAKEN TO FRONT DESK  2/7/2008 DONE
Print Occupancy Form  2/7/2008 DONE
Print Occupancy Form  2/7/2008  
Case Summary (BLD)  2/7/2008  
1st review completed  2/7/2008 DONE
Routing - PUBLIC WORKS2/5/2008 2/6/2008 PASS
DetailsBeverly Hall
Routing PW Sewer Rating2/6/2008 2/6/2008 PASS
DetailsLouise Waldorf
Routing - PLAN CHECK2/5/2008 2/5/2008 PEND
DetailsDave Hannah
ok after public works returns
Plans ACCEPTED BY PLAN TECH  1/25/2008  
Recd Pcfee & Taken To Pln CK  1/24/2008  
Application received  1/24/2008  
Pending Assignment by MYS1/24/2008    
Routing - PLAN CHECK2/7/2008   PASS