Case Summary (BLD) | | | 11/6/2015 | | DONE |
|
|
|
|
Third Notice BLD | 9/22/2008 | 9/22/2008 | 9/30/2008 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 8/11/2008 | 8/11/2008 | 9/22/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 7/16/2008 | 8/11/2008 | | DONE |
|
|
|
|
BLD-Final | 7/15/2008 | 7/16/2008 | 7/16/2008 | A | PASS |
Dave Hannah
|
|
|
tucker Phone #: ###-#### ok for perm occ
|
Permanent Occupancy UNPAID FEE | | | 7/16/2008 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 6/19/2008 | 6/19/2008 | 6/20/2008 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory, inspection passed.
|
BLD-Final | 6/19/2008 | 6/20/2008 | 6/20/2008 | A | PART |
Dave Hannah
|
|
|
tucker Phone #: ###-#### ok for temp occ needs to fix ada restroom and change swing on lobby doors
|
BLD-Conference | 4/14/2008 | 4/15/2008 | 4/15/2008 | A | PASS |
Dave Hannah
|
|
|
tucker Phone #: ###-####
|
BLD-Framing/Rough-in | 4/11/2008 | 4/11/2008 | 4/11/2008 | P | PART |
Dave Hannah
|
|
|
mario Phone #: ###-####
|
BLD-Other | 3/24/2008 | 3/25/2008 | 3/25/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/24/2008 at 8:59:34 PM. Contact: ###-####. ceiling grid needs clips or spreader bars around new area
|
BLD-Framing/Rough-in | 2/27/2008 | 2/27/2008 | 2/27/2008 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/27/2008 at 8:57:08 AM. Contact: ###-####. cooidor ext on north side ok to cover
|
BLD-Framing/Rough-in | 2/19/2008 | 2/19/2008 | 2/19/2008 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/19/2008 at 8:46:23 AM. Contact: ###-####.south side restroom and corridor wall ok to cover
|
Telephone call | | | 2/8/2008 | | DONE |
|
|
|
left vm for tucker anderson at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 2/8/2008 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/8/2008 | | |
|
|
|
|
Routing - PLAN CHECK | 2/7/2008 | | 2/7/2008 | | PASS |
Dave Hannah
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/7/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/7/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 2/7/2008 | | |
|
|
|
|
1st review completed | | | 2/7/2008 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 2/5/2008 | | 2/6/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 2/6/2008 | | 2/6/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PLAN CHECK | 2/5/2008 | | 2/5/2008 | | PEND |
Dave Hannah
|
|
|
ok after public works returns
|
Plans ACCEPTED BY PLAN TECH | | | 1/25/2008 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/24/2008 | | |
|
|
|
|
Application received | | | 1/24/2008 | | |
|
|
|
|
Pending Assignment by MYS | 1/24/2008 | | | | |
|
|
|
|
Routing - PLAN CHECK | 2/7/2008 | | | | PASS |
|
|
|
|