First Notice | | 9/22/2013 | 9/30/2013 | | DONE |
|
|
|
Project was started in 2008 by owner and new owner continued project in 2013. Unable to verify final values due to age in project and different owner/GC's.
|
Permanent Occupancy | | | 9/12/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 9/11/2013 | 9/11/2013 | 9/11/2013 | P | PASS |
Jim Storey
|
|
|
Please call at least 10 mins prior to inspection Phone #: ###-####
|
FIRE-Final Inspection | 8/16/2013 | 8/16/2013 | 8/16/2013 | P | PASS |
Forrest France
|
|
|
Previous correction items completed. Life safety finaled.
|
BLD-Final | 8/16/2013 | 8/16/2013 | 8/16/2013 | P | FAIL |
Jim Storey
|
|
|
truss bracing v webs and 2ft 2 in oc bottom chord.
|
BLD-Final | 8/14/2013 | 8/14/2013 | 8/14/2013 | P | NR |
Jim Storey
|
|
|
Debbie-Please call at least 30 mins prior to inspection so she can provide access--and verify no mechanical is required Phone #: ###-#### need truss engineering/ p&z and fire sign off
|
FIRE-Final Inspection | 7/16/2013 | 7/17/2013 | 7/17/2013 | A | FAIL |
Troy Cobbley
|
|
|
The unobstructed road width through the gate is not 20' as required. See review note #2 (note B). Drawing sheet C1.0 shows a 22' Drive Aisle. Provide fire dept access signage as per review note #3.
|
BLD-Aging Inspection | 7/2/2013 | 7/2/2013 | 7/2/2013 | | NR |
Jim Storey
|
|
|
no requist verify c/n
|
Zoning Approval | 6/28/2013 | 6/28/2013 | 6/28/2013 | | PASS |
Josh Wilson
|
|
|
|
PubWorks Occupancy Approval | 6/3/2013 | 6/3/2013 | 6/3/2013 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Conference | 4/1/2013 | 4/1/2013 | 4/2/2013 | P | DEFR |
Jim Storey
|
|
|
|
BLD-Conference | 4/1/2013 | 4/2/2013 | 4/2/2013 | A | PASS |
Jim Storey
|
|
|
call when on way to meet//Debbie Phone #: ###-#### need truss eningeering/ reviewed signoffs needed/ door hardware
|
BLD-Framing/Rough-in | 3/29/2013 | 3/29/2013 | 3/29/2013 | P | PART |
Tom Arcoraci
|
|
|
Debbie-PLease call at least 30 mins prior to inspection Phone #: ###-#### needs plans bath rooms appear ok will call for conf with j storey
|
BLD-Aging Inspection | 1/10/2013 | 1/10/2013 | 1/10/2013 | | NR |
Jim Storey
|
|
|
|
Route to Impact Fee Review | 9/19/2012 | 9/24/2012 | 1/10/2013 | | PASS |
Cindy M. Gould
|
|
|
|
OVERRIDE | | | 1/9/2013 | | |
|
|
|
|
Zoning Approval Temp | 1/9/2013 | 1/9/2013 | 1/9/2013 | | PASS |
Josh Wilson
|
|
|
180-day occupancy. Bond is in place for paving to be completed.
|
Plan assigned to (JCM) | 8/24/2012 | 8/24/2012 | 1/9/2013 | | PASS |
John Menard
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/9/2013 | | DONE |
Tisha Gallop
|
|
|
Plan mod issued to new owner Cripe PRoperties
|
(F) Reprint permit | | | 1/9/2013 | | DONE |
Tisha Gallop
|
|
|
|
Meeting | | | 1/9/2013 | | DONE |
Tisha Gallop
|
|
|
property has changed owners from Roger Anderson to Cripe Properties LLC (Deborah Cripe - contact). New owner Cripe has provided new application and signed GC form to be their own GC. Will provide new RP prior to site work beginning when weather permits. To receive occupancy owner has bonded for pavement site work (Bnd13-00002).
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/9/2013 | | DONE |
John Menard
|
|
|
New owner submitted application to issue plan modification for this project. JCM
|
Print Occupancy Form | | | 1/9/2013 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 1/9/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Design Review | 11/27/2012 | | 11/28/2012 | | PASS |
Josh Wilson
|
|
|
OK per DRH12-00286
|
Routing - PLAN CHECK | 11/28/2012 | | 11/28/2012 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 9/24/2012 | | 11/27/2012 | | |
John Menard
|
|
|
|
Plan resubmittals received | | | 10/10/2012 | | DONE |
Tisha Gallop
|
|
|
received two copies of Interior Lighting Compliance Certificate and plan sheet A4.0; inserted by permit tech and taken back to John Menard.
|
Routing - FIRE | 9/19/2012 | | 9/24/2012 | | PASS |
Scott Arellano
|
|
|
Attached modified comment to plans.
|
Plan Reviewer's activity | | | 9/19/2012 | | DONE |
John Menard
|
|
|
Asked Brian Murphy if he needed to review plans for any required drainage revisions. He indicated that because of the location of the addition, he would not need to review the plan modification. JCM
|
Plan resubmittals requested | | | 9/19/2012 | | DONE |
John Menard
|
|
|
E-mailed the engineer requesting additional information and revisions. JCM
|
Routing - PLAN CHECK | 9/7/2012 | | 9/19/2012 | | FAIL |
John Menard
|
|
|
|
Plan resubmittals received | | | 9/14/2012 | | DONE |
Tisha Gallop
|
|
|
received additional sheets for plan modification review; received two copies of plan sheets A1.0, A2.0, A3.0; taken to John Menard
|
Routing - PLANNING | 9/5/2012 | | 9/7/2012 | | FAIL |
Matthew A Halitsky
|
|
|
DR Modification required.
|
Routing - PLAN CHECK | 8/24/2012 | | 9/5/2012 | | FAIL |
John Menard
|
|
|
|
Plan resubmittals requested | | | 9/5/2012 | | DONE |
John Menard
|
|
|
E-mailed the applicant requesting two complete sets of as-built building plans. JCM
|
Plan Modification Accepted | | | 8/24/2012 | | DONE |
Christina Prado
|
|
|
Plan modification accepted to show the details for the 1000 sq. ft. larger built out than the plans originally called for. Sheets affected are S2.0, C1.0 & C2.0. Received three sets of above listed sheets as well as three sets of structural calcs and storm water calcs. Gave plans and Calcs to John Menard for review.
|
BLD-Framing/Rough-in | 6/14/2012 | 6/15/2012 | 6/15/2012 | P | PART |
Jim Storey
|
|
|
200 pm aptm. w/chris person ###-#### need truss engineering
|
BLD-Aging Inspection | 5/10/2012 | 5/10/2012 | 5/10/2012 | | FAIL |
Jim Storey
|
|
|
stil need framing insp. interior plm exp.
|
BLD-Aging Inspection | 2/9/2012 | 2/9/2012 | 2/10/2012 | | PART |
Jim Storey
|
|
|
stil need framing insp. interior
|
BLD-Aging Inspection | 11/10/2011 | 11/10/2011 | 11/10/2011 | | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 8/11/2011 | 8/11/2011 | 8/11/2011 | P | PASS |
Jim Storey
|
|
|
called owner work is still in progress. cost is out of pocket and working to get to a point to be able to call for insp.
|
BLD-Aging Inspection | 8/10/2011 | 8/10/2011 | 8/11/2011 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 3/9/2011 | 3/9/2011 | 3/11/2011 | | PASS |
Jim Storey
|
|
|
|
BLD-Other | 12/27/2010 | 12/27/2010 | 12/27/2010 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 12/27/2010 | 12/27/2010 | 12/27/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 10/25/2010 | 10/25/2010 | 10/25/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 8/23/2010 | 8/23/2010 | 8/23/2010 | | PASS |
Jim Storey
|
|
|
work slow but progressing.
|
BLD-Aging Inspection | 6/21/2010 | 6/21/2010 | 6/21/2010 | | PASS |
Jim Storey
|
|
|
work slow but progressing.
|
BLD-Aging Inspection | 4/20/2010 | 4/20/2010 | 4/21/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Conference | 4/21/2010 | 4/21/2010 | 4/21/2010 | A | PASS |
Jim Storey
|
|
|
called owner work is still in progress. cost is out of pocket and working to get to a point to be able to call for insp.
|
BLD-Aging Inspection | 2/18/2010 | 2/18/2010 | 2/18/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 12/14/2009 | 12/14/2009 | 12/14/2009 | | PASS |
Jim Storey
|
|
|
meet with owner on site work is still in progress.
|
BLD-Conference | 12/14/2009 | 12/14/2009 | 12/14/2009 | P | PASS |
Jim Storey
|
|
|
meet with owner on site work is still in progress.
|
BLD-Conference | 12/14/2009 | 12/14/2009 | 12/14/2009 | P | CANC |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 10/12/2009 | 10/12/2009 | 10/12/2009 | | PASS |
Jim Storey
|
|
|
talked to roger and work will begin agian next week.
|
BLD-Aging Inspection | 8/10/2009 | 8/10/2009 | 8/10/2009 | | PASS |
Jim Storey
|
|
|
slow if any progress no access.
|
BLD-Aging Inspection | 6/8/2009 | 6/8/2009 | 6/8/2009 | | PART |
Jim Storey
|
|
|
slow if any progress no access.
|
BLD-Aging Inspection | 4/1/2009 | 4/1/2009 | 4/1/2009 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Aging Inspection | 1/28/2009 | 1/28/2009 | 1/28/2009 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Concrete | 6/25/2008 | 6/26/2008 | 6/26/2008 | P | PASS |
Jim Storey
|
|
|
Roger Phone #: ###-####
|
BLD-Footing | 6/18/2008 | 6/19/2008 | 6/19/2008 | A | PASS |
Jim Storey
|
|
|
Roger Phone #: ###-#### ft ok rebar ok
|
(F) Reprint permit | | | 5/19/2008 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/16/2008 | | DONE |
|
|
|
|
OVERRIDE | | | 5/8/2008 | | |
|
|
|
|
Print Occupancy Form | | | 5/8/2008 | | DONE |
|
|
|
|
Telephone call | | | 5/8/2008 | | DONE |
|
|
|
t/c w roger anderson at ###-#### - permit ready and fees given - also need ACHD receipt
|
Permit Ready to Issue | | | 5/8/2008 | | DONE |
|
|
|
|
Routing PW Solid Waste | 5/7/2008 | | 5/8/2008 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - PLAN CHECK | 5/7/2008 | | 5/7/2008 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/7/2008 | | DONE |
John Menard
|
|
|
|
Routing - PLAN CHECK | 5/6/2008 | | 5/7/2008 | | |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 5/7/2008 | | 5/7/2008 | | PASS |
Beverly Hall
|
|
|
|
Plan assigned to (JCM) | 2/5/2008 | | 5/7/2008 | | PASS |
John Menard
|
|
|
5/7/2008 15:39:48 JCM - activity updated through activity BLDA022 from case BLD08-00207.
|
Routing - PUBLIC WORKS | 4/30/2008 | | 5/6/2008 | | FAIL |
Louise Waldorf
|
|
|
|
Routing PW Solid Waste | 5/6/2008 | | 5/6/2008 | | FAIL |
Peter J. McCullough
|
|
|
Trash enclosure is not correct size; must be minimum 12' X 12'. Also location is not accessible for collection. Contact Peter McCullough, ###-####.
|
Plan resubmittals received | | | 5/6/2008 | | |
|
|
|
Received two copes of sheets C1.0 & C2.0; inserted by LEG and taken back to John Menard
|
Plan resubmittals received | | | 5/5/2008 | | |
|
|
|
Received transmittal, calcs, five copies of sheet C2.0; inserted by LEG and taken back to Brian Murphy
|
Routing PW Drainage | 5/5/2008 | | 5/5/2008 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 4/17/2008 | | 4/30/2008 | | |
|
|
|
|
Plan resubmittals received | | | 4/17/2008 | | |
|
|
|
Received 1 cover transmittal, 2 copies of storm water calcs, 5 copies of sheets C1 & C2 and inserted into plans and taken to John Menard desk 4-17-08 @ 4:10pm BAS
|
Routing - PLUMBING | 4/15/2008 | | 4/17/2008 | | PASS |
Bill VanDegrift
|
|
|
added drinking fountain. vent on the pump chamber will be required. per plans and 2003 upc
|
Routing - PLAN CHECK | 4/9/2008 | | 4/15/2008 | | |
John Menard
|
|
|
|
Routing PW Drainage | 4/9/2008 | | 4/9/2008 | | FAIL |
Brian Murphy
|
|
|
roof drainage contact Brian Murphy ###-####
|
Routing - PUBLIC WORKS | 3/28/2008 | | 4/9/2008 | | FAIL |
Louise Waldorf
|
|
|
|
Plan Reviewer's activity | | | 3/28/2008 | | PASS |
John Menard
|
|
|
Reviewed and approved structural and nonstructural revisions with redlined notes and attached comment list. JCM
|
Routing - PLAN CHECK | 3/12/2008 | | 3/28/2008 | | PASS |
John Menard
|
|
|
|
Plan resubmittals received | | | 3/26/2008 | | |
|
|
|
Received revised cover sheet of application, two copies of sheets A-1, P-1, P-2, E-1, E-2; inserted by owner and taken back to John Menard
|
Plan resubmittals received | | | 3/26/2008 | | |
|
|
|
Received two transmittal, letter of response to plan reivew, letter of response to storm water comments, letter to request storm water variance, five copies of sheet C2.0, and two copies of sheets A1.0, A2.0, S2.0, S4.0; inserted by arch. rep. and taken back to John Menard
|
Plan resubmittals received | | | 3/14/2008 | | |
|
|
|
Received 1 cover transmittal, 3 copies of structural calculations, 3 copies pf sheets S1.0, S2.0, S3.0 and inserted into plans then taken back to John Menard's desk///3-14-08 @ 4:05pm BAS
|
1st review completed | | | 3/12/2008 | | FAIL |
|
|
|
Failed PW, Structural, Planning, Plan Check
|
Routing - FIRE | 3/11/2008 | | 3/12/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - PLAN CHECK | 2/26/2008 | | 3/11/2008 | | FAIL |
John Menard
|
|
|
John Menard
|
Plan resubmittals requested | | | 3/11/2008 | | DONE |
John Menard
|
|
|
Mailed the applicant a copy of the plan review requesting revisions. JCM
|
Plan resubmittals requested | | | 3/10/2008 | | DONE |
John Menard
|
|
|
Faxed the engineer a copy of the structural review comment list requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 2/8/2008 | | 2/28/2008 | | FAIL |
John Menard
|
|
|
Called Action Courier for pick up 2-8-08 @ 8:25am BAS
|
Routing - PLUMBING | 2/25/2008 | | 2/26/2008 | | PASS |
Bill VanDegrift
|
|
|
vent pump chamber. provisions should be made at this time for the T.I. required drinking fountain.
|
Routing - PLANNING | 2/26/2008 | | 2/26/2008 | | PASS |
Matthew A Halitsky
|
|
|
DRH07-00428-Matt Halitsky
Routed to Plan Check 2/26/2008.
|
Routing - Erosion and Sediment | 2/20/2008 | | 2/25/2008 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions.
|
Routing PW Street Lights | 2/19/2008 | | 2/20/2008 | | PASS |
Bill Colson
|
|
|
|
Routing - PUBLIC WORKS | 2/8/2008 | | 2/20/2008 | | FAIL |
Louise Waldorf
|
|
|
|
Routing PW Sewer Design | 2/11/2008 | | 2/19/2008 | | PASS |
Jim Pardy
|
|
|
|
Routing PW Drainage | 2/8/2008 | | 2/11/2008 | | FAIL |
Brian Murphy
|
|
|
roof draians, swale width,3 detail sheet copies, basalt variance. BRIAN MURPHY ###-####
|
Plan routing begun/NEW & ADDTN | | | 2/8/2008 | | |
|
|
|
|
Routing PW Sewer Rating | 2/8/2008 | | 2/8/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PLANNING Land Div | 2/8/2008 | | 2/8/2008 | | PASS |
Todd Tucker
|
|
|
Parcel is a platted lot in a subdivision.
|
Plans ACCEPTED BY PLAN TECH | | | 2/8/2008 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/5/2008 | | DONE |
|
|
|
|
Application received | | | 2/5/2008 | | |
|
|
|
|
Pending Assignment by MYS | 2/5/2008 | | 2/5/2008 | | DONE |
John Menard
|
|
|
2/5/2008 15:07:48 JCM - activity updated through activity BLDA166 from case BLD08-00207.
|