BLD-Final | 11/12/2008 | 11/13/2008 | 11/13/2008 | A | PASS |
Tony Young
|
|
|
Kathy Phone #: ###-#### Note: documents are in the garage if not code call kathy
|
DOC - Permit Finaled | 11/13/2008 | 11/13/2008 | 11/13/2008 | P | PASS |
Tony Young
|
|
|
signed paperwork
|
PubWorks Subgrade Approval | 10/23/2008 | 10/23/2008 | 10/23/2008 | | DONE |
Terry Records
|
|
|
Footing subgrade approved by the geotechnical engineer
|
Routing Walk-In (BLD) | 9/23/2008 | 9/23/2008 | 9/23/2008 | P | PASS |
Perry Paine
|
|
|
final inspection questions
|
Case Summary (BLD) | | | 9/23/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 9/23/2008 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/23/2008 | | |
|
|
|
|
BLD-Final | 8/22/2008 | 8/25/2008 | 8/25/2008 | A | NR |
Tony Young
|
|
|
Kathy Phone #: ###-#### need all engineering per scope of work
|
BLD-Conference | 4/7/2008 | 4/7/2008 | 4/7/2008 | P | PEND |
Tony Young
|
|
|
Tony please call me regarding this permit. Thanks Rita ###-#### placed a SWO on job for permit fees owed per office
|
Override - Parcel Holds | | | 4/7/2008 | | |
|
|
|
|
BLD-Energy code compliance | 4/3/2008 | 4/4/2008 | 4/4/2008 | A | PASS |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 4/2/2008 | 4/3/2008 | 4/3/2008 | P | PASS |
Tony Young
|
|
|
JUSTIN Phone #: ###-####
|
BLD-Framing/Rough-in | 4/2/2008 | 4/2/2008 | 4/2/2008 | P | NR |
Jim Sly
|
|
|
justin Phone #: ###-#### Need Plumb and Mech rough-ins approved.
|
BLD-Framing/Rough-in | 3/31/2008 | 4/1/2008 | 4/1/2008 | A | FAIL |
Tony Young
|
|
|
justin Phone #: ###-#### c/n posted,, need a mech permit and r/in,, need elec. and plumbing r/in also,, on site conf.. will need struct. eng. letter for work done w/out permits or inspections
|
Issue PAID IN FULL permit | | | 3/21/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/20/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2008 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/20/2008 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 3/17/2008 | 3/17/2008 | 3/17/2008 | P | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 3/17/2008 | 3/17/2008 | 3/17/2008 | P | DONE |
Perry Paine
|
|
|
3/17/2008 15:04:43 PEP - activity updated through activity BLDI258 from case BLD08-00211.
|
Routing Walk-In (Erosion) | 3/17/2008 | 3/17/2008 | 3/17/2008 | P | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC08-00180
|
Case Summary (BLD) | | | 3/17/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 3/17/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 3/17/2008 | | |
|
|
|
|
BLD-Conference | 3/4/2008 | 3/4/2008 | 3/4/2008 | P | FAIL |
Tony Young
|
|
|
per tony young - doing work without a permit need to double fee,, concrete has been poured,, framed, sided, etc.. will need a letter of ok as built from structural engineer on ftgs and soils
|
(F) Reprint permit | | | 2/19/2008 | | |
|
|
|
|
Routing Walk-In (Zoning) | 2/6/2008 | 2/6/2008 | 2/6/2008 | A | PASS |
Lucinda Grames
|
|
|
|
Routing Walk-In (BLD) | 2/6/2008 | 2/6/2008 | 2/6/2008 | A | FAIL |
Perry Paine
|
|
|
|
Routing Walk-In (Zoning) | 2/5/2008 | 2/5/2008 | 2/6/2008 | P | DONE |
Lucinda Grames
|
|
|
2/6/2008 09:06:58 LIG - activity updated through activity BLDI254 from case BLD08-00211.
|
Application received | | | 2/5/2008 | | |
|
|
|
|
Routing - PLAN CHECK | 3/17/2008 | | | | |
|
|
|
PEP
|