Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD08-00212
StatusFinaled
Name PRISTINE POOLS AND SPAS
Site Address 11200 W KING ST
Project NameAMBLESIDE SUB - POOL
Customer Number 
ePlanReviewNo
Description
(AMBLESIDE - POOL) To construct a 48' x 20', approximate total of 920 square feet, in ground gunite swimming pool with related 400,000 BTU pool heater, filtering and operation equipment. Pool, deck & equipment shall be bonded per the NEC. Clubhouse, detached pool equipment storage shed, fencing around the pool, and accessible restrooms are permitted under BLD07-02596. Installation shall comply with Section 3109 IBC. Accessibility of recreational facilities is responsibility of contractor, design professional & owners per current ADA requirements. NOTE: All storage and handling of chemicals shall be per the Fire Code. ~SRZ~
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD11/7/200811/7/200811/10/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice9/16/20089/16/200811/7/2008 DONE
DetailsJim Sly
BLD-Final9/15/20089/16/20089/16/2008APASS
DetailsJim Sly
anne Phone #: ###-####
DOC - Permit Finaled9/16/20089/16/20089/16/2008PPASS
DetailsJim Sly
BLD-Final8/26/20088/27/20088/27/2008ANR
DetailsJim Sly
Anne Phone #: ###-####
Need Electr final
BLD-Framing/Rough-in3/19/20083/20/20083/20/2008PPASS
DetailsJim Sly
Rebar
Contact = Becky Phone #: ###-#### Internet Inspection Request from: Becky Leavitt
Pool rebar OK
Permit Ready to Issue  3/3/2008 DONE
Issue PAID IN FULL permit  3/3/2008 DONE
Inspection Record Card- Bld  2/28/2008 DONE
1st review completed  2/27/2008 PASS
Routing - PLAN CHECK2/27/2008 2/27/2008 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  2/27/2008 DONE
Plan assigned to (SRZ)2/15/2008 2/27/2008 PASS
DetailsSam Zahorka
2/27/2008 15:54:45 SRZ - activity updated through activity BLDA022 from case BLD08-00212.
Routing - PLAN CHECK2/21/2008 2/27/2008 PEND
DetailsSam Zahorka
others to pass
Routing - FIRE2/27/2008 2/27/2008 PASS
DetailsScott Arellano
No seperate review comments attached. Plans approved with red line comments regarding limitations of pool chemicals storage.
Routing - PLANNING2/20/2008 2/21/2008 PASS
DetailsAndrea Tuning
Approved per DRH07-00045
Routing - Erosion and Sediment2/19/2008 2/20/2008 PASS
DetailsJames Rogers
See attahed ESC conditions under ESC08-00075
Routing - PLUMBING2/20/2008 2/20/2008 PASS
DetailsBill VanDegrift
plumbing approved with bld07-02596.
Routing - PUBLIC WORKS2/15/2008 2/19/2008 PASS
DetailsBeverly Hall
Routing PW Sewer Rating2/15/2008 2/15/2008 PASS
DetailsLouise Waldorf
Pending Assignment by MYS2/8/2008 2/15/2008 DONE
DetailsMarlene Southard
2/15/2008 11:36:28 MYS - activity updated through activity BLDA160 from case BLD08-00212.
Plans ACCEPTED BY PLAN TECH  2/8/2008  
Recd Pcfee & Taken To Pln CK  2/8/2008 DONE
Application received  2/5/2008