BLD-Final | 1/9/2012 | 1/9/2012 | 1/9/2012 | P | PASS |
Tony Young
|
|
|
DAN Phone #: ###-####
|
DOC - Permit Finaled | | | 1/9/2012 | | DONE |
|
|
|
|
FIRE-Final Inspection | 1/3/2012 | 1/3/2012 | 1/3/2012 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Energy code compliance | 11/15/2011 | 11/16/2011 | 11/16/2011 | P | PART |
Tony Young
|
|
|
Dan Phone #: ###-####,,, two small corrections,, then ok to cover
|
BLD-Energy code compliance | 11/15/2011 | 11/15/2011 | 11/15/2011 | P | PART |
Tony Young
|
|
|
Dan Phone #: ###-####,,, seal pack ok,, frame ok,,, needs trades passed
|
BLD-Aging Inspection | 11/9/2011 | 11/9/2011 | 11/15/2011 | | PEND |
Tony Young
|
|
|
|
FIRE-Conference | 11/9/2011 | 11/9/2011 | 11/9/2011 | P | DONE |
Troy Cobbley
|
|
|
Inspection was actually for an underground supply flush for the future fire sprinkler system. The flush passed.
|
CHANGE STATUS TO (ISS) | | | 11/8/2011 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (SRZ) | 10/31/2011 | 10/31/2011 | 11/3/2011 | | PASS |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 11/3/2011 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 11/3/2011 | | 11/3/2011 | | PASS |
Sam Zahorka
|
|
|
Plan modification approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2011 | | DONE |
Sam Zahorka
|
|
|
|
Inspection Record Card- Bld | | | 11/3/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/3/2011 | | DONE |
|
|
|
|
Telephone call | | | 11/3/2011 | | DONE |
|
|
|
11-3-11 called David permit ready for pick up and fee given ///dld
|
CHANGE STATUS TO (REV) | | | 10/31/2011 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 10/31/2011 | | |
|
|
|
10-31-11 plan modifiation accepted for BLD08-00226 to make 2 offices page affected is the floor plan.
|
Plan Reviewer's activity | | | 10/24/2011 | | DONE |
Sam Zahorka
|
|
|
Received updated floor plan. attached to case and delivered to records department.
|
Plan resubmittals received | | | 10/21/2011 | | |
|
|
|
Received 2 copies of revised floor plan and taken to Sam Zahorka
|
BLD-Aging Inspection | 8/10/2011 | 8/10/2011 | 8/12/2011 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 3/28/2011 | 3/28/2011 | 3/29/2011 | | PEND |
Tony Young
|
|
|
|
BLD-Wall cover | 1/20/2011 | 1/24/2011 | 1/24/2011 | P | PART |
Jim Sly
|
|
|
Dan Phone #: ###-#### Common rated walls only.....OK
|
BLD-Framing/Rough-in | 1/5/2011 | 1/5/2011 | 1/5/2011 | P | NR |
Jim Storey
|
|
|
dan - partial cover Phone #: ###-####
|
BLD-Aging Inspection | 12/27/2010 | 12/27/2010 | 1/3/2011 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 10/26/2010 | 10/26/2010 | 11/1/2010 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 8/23/2010 | 8/23/2010 | 8/24/2010 | | PASS |
Tony Young
|
|
|
|
BLD - Request for Extension | 6/21/2010 | 6/22/2010 | 6/22/2010 | A | PASS |
Tony Young
|
|
|
Dave- call prior to going Phone #: ###-####
|
BLD-Aging Inspection | 6/16/2010 | 6/16/2010 | 6/21/2010 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/14/2010 | 4/14/2010 | 4/19/2010 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 2/4/2010 | 2/9/2010 | 2/9/2010 | A | PASS |
Tony Young
|
|
|
ok to keep active
|
BLD-Framing/Rough-in | 5/22/2009 | 5/22/2009 | 5/22/2009 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Jessica Noland conf only
|
PubWorks Occupancy Approval | 5/22/2009 | 5/22/2009 | 5/22/2009 | | PASS |
Brian Murphy
|
|
|
ok for perm occupancy per BGM
|
BLD-Wall cover | 3/24/2009 | 3/25/2009 | 3/25/2009 | A | PART |
Mike Jordan
|
|
|
need ok to cover exterior (siding) Phone #: ###-#### Internet Inspection Request from: Jessica Noland. exterior shear nailing ok.
|
BLD-Framing/Rough-in | 2/10/2009 | 2/11/2009 | 2/11/2009 | A | PART |
Tony Young
|
|
|
ben - ###-#### - party wall ok
|
Override - Parcel Holds | | | 2/10/2009 | | |
|
|
|
|
Override - Parcel Holds | | | 2/10/2009 | | |
|
|
|
|
Elevation Cert Rec'd-Final | | | 1/27/2009 | | DONE |
|
|
|
Received Elevation Certificate documenting compliance with Floodplain Ordinance. Okay to schedule framing inspection. Jim Wyllie / ###-####
|
BLD-Concrete | 10/9/2008 | 10/10/2008 | 10/10/2008 | A | PASS |
Tony Young
|
|
|
rebar inspection pouring concrete AM Phone #: ###-#### Internet Inspection Request from: Jessica Noland stem walls ok
|
BLD-Concrete | 9/26/2008 | 9/29/2008 | 9/29/2008 | P | PASS |
Tony Young
|
|
|
rebar inspection Phone #: ###-#### Internet Inspection Request from: Jessica Noland footings ok,, corners surveyed in
|
Override - Parcel Holds | | | 8/11/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 8/11/2008 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/11/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/8/2008 | | DONE |
|
|
|
left vm for curtis crystal at ###-#### - permit ready and fees given
|
Override - Parcel Holds | | | 8/8/2008 | | |
|
|
|
|
Override - Parcel Holds | | | 8/8/2008 | | |
|
|
|
|
Permit Ready to Issue | | | 8/8/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/4/2008 | | 8/7/2008 | | PASS |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 8/7/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2008 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 8/7/2008 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 4/24/2008 | | 8/7/2008 | | PASS |
Sam Zahorka
|
|
|
8/7/2008 09:15:53 SRZ - activity updated through activity BLDA022 from case BLD08-00226.
|
Routing - FIRE | 7/31/2008 | 7/31/2008 | 8/4/2008 | | PASS |
Scott Arellano
|
|
|
See IFC fire plan review note attached.
|
1st review completed | | | 8/4/2008 | | FAIL |
|
|
|
Public works, PW flood plain and plan check.
|
Plan resubmittals received | | | 8/4/2008 | | |
Sam Zahorka
|
|
|
Received transmittal, response letter and two copies of sheets A0.0, A0.1, A1.0, A1.1, A3.0, A3.1, A3.2, A5.0, A5.1, A5.2, A6.0, A6.1, A7.0, A7.2, A8.0, A8.1, A9.0, A10.0, S0.1, S4.01, S5.01, E2.1M; inserted by arch. rep. and taken back to Sam Zahorka
|
Route to Impact Fee Review | 7/31/2008 | 8/5/2008 | 7/31/2008 | | PASS |
Cindy M. Gould
|
|
|
Impact fees applied by LEG
|
Routing - PLAN CHECK | 7/15/2008 | | 7/31/2008 | | FAIL |
Sam Zahorka
|
|
|
Emailed correction to the Architect.
|
Case Summary (BLD) | | | 7/31/2008 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/15/2008 | | |
|
|
|
Received 6 copies of sheet A6.1 and inserted into plans by Modus Architects///7/15/08 @ 11:48am BAS
|
Routing - PUBLIC WORKS | 7/15/2008 | | 7/15/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing PW Flood Plain | 7/15/2008 | | 7/15/2008 | | PASS |
Jim Wyllie
|
|
|
|
Routing PW Flood Plain | 7/8/2008 | | 7/8/2008 | | FAIL |
Jim Wyllie
|
|
|
Show flood vents on building elevation. Jim Wyllie (###-####)
|
Routing PW Flood Plain | 6/19/2008 | | 6/23/2008 | | FAIL |
Jim Wyllie
|
|
|
Elevation Certificate shows attached garage below Base Flood Elevation without flood vents. Elevation Certificate needs to be modified to show placement of flood vents as per FEMA Technical Bulletin 1-93. Jim Wyllie / ###-####
|
Routing - PUBLIC WORKS | 6/19/2008 | | 6/23/2008 | | FAIL |
Louise Waldorf
|
|
|
Plans are so large that they are in office with Carl & Ben waiting re-submittals.
|
Routing - PLANNING | 6/19/2008 | | 6/19/2008 | | PASS |
Matthew A Halitsky
|
|
|
Routed to Public Works.
|
Plan resubmittals received | | | 6/12/2008 | | |
|
|
|
Received 6 copies of sheet A6.0 and A6.1 and taken to Matt Halitsky 6-12-08 @ 11:44am BAS
|
Plan resubmittals received | | | 6/9/2008 | | |
Tisha Gallop
|
|
|
Received two copies of sheet LS1.0; taken to Matt H. to insert into plans
|
Pending Assignment by SRZ | 2/8/2008 | | 4/24/2008 | | DONE |
Marlene Southard
|
|
|
4/24/2008 11:14:27 MYS - activity updated through activity BLDA160 from case BLD08-00226.
|
Routing - PLANNING | 2/9/2008 | | 2/14/2008 | | FAIL |
Matthew A Halitsky
|
|
|
Drh07-00466 Matt Halitsky; Cup07-00121 Susan Riggs
Conditions of DR approval not met. Email sent 2/13/2008.
Plans in my office.
|
Routing - Addressing | 2/8/2008 | | 2/8/2008 | | PASS |
Chris Pichardo
|
|
|
|
Application received | | | 2/8/2008 | | |
|
|
|
|