Information based on query as of Thursday, July 25, 2024.
Permit Information
Permit NumberBLD08-00234
StatusFinaled
Name KREIZENBECK CONSTRUCTORS
Site Address 1122 N LIBERTY RD
Project NameApollo College
Customer Number 
ePlanReviewNo
Description
Apollo College (Classroom and Administration Building) - To construct a new 23,550 square foot, two story, wood framed classroom and administration building and related site improvements. First Floor: 12,000 square feet, Second Floor: 11,550 square feet. This building is fully fire sprinkled. The sprinklers are used for area increase. All construction per the approved plans and attached comment list. JCM//Plan modification submitted 6-13-08 to relocate a new seepage bed further south, the existing catch basin location will direct storm via pipe to the new basin approved per Brian Murphy 6-19-08 BAS
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 7/22/20097/22/2009 DONE
This permit finaled on the web by Brandon Byington
First Notice 5/29/20097/22/2009 DONE
First Notice 5/29/20097/22/2009 DONE
Zoning Approval5/29/20095/29/20095/29/2009 DONE
DetailsJoshua Johnson
All Design Review and Current Planning Conditions met
Permanent Occupancy  5/29/2009 DONE
DetailsTisha Gallop
BLD-Final5/26/20095/28/20095/28/2009APASS
DetailsTom Arcoraci
Jan Phone #: ###-#### ok for perm occ
BLD-Aging Inspection5/20/20095/20/20095/20/2009 DEFR
DetailsTom Arcoraci
zoning issue
BLD-Conference3/18/20093/18/20093/18/2009APASS
DetailsTom Arcoraci
on temp
BLD-Aging Inspection3/18/20093/18/20093/18/2009 PASS
DetailsTom Arcoraci
Temporary Occupancy UNPAID FEE  2/5/2009  
The remaining improvements must be complete for permanent occupancy to be granted.

ANT and JRJ
Temporary Occupancy UNPAID FEE  2/5/2009 DONE
Zoning Approval Temp1/26/20091/26/20091/26/2009 PASS
DetailsAndrea Tuning
The applicant has posted abond for the remaining improvements. The applicant has been granted temporary occupancy for 90 days. The remaining improvements must be complete for permanent occupancy to be granted.

ANT and JRJ
BLD-Final1/15/20091/16/20091/16/2009APART
DetailsTom Arcoraci
jan Note: late morning please Phone #: ###-#### pending zoning sign off
FIRE-Final Inspection1/15/20091/16/20091/16/2009APASS
DetailsTroy Cobbley
Life safety passed
Zoning Approval1/16/20091/16/20091/15/2009 FAIL
DetailsAndrea Tuning
The applicant has requested occupancy of the new building but has not removed the protable classrooms, installed the new parking area adjacent to Liberty Street, has not restriped the parkking located behind the original building and has not installed the required planters and improvments throughout the entire site. As such, the applicant has been given two options. 1 - The applicant may complete of the improvements and then schedule a new inspection or 2 - The applicant may obtain a temporary parking agreement that is offsite AND must bond for the remaining improvments. ANT 1-15-09
FIRE-Final Inspection1/13/20091/14/20091/14/2009AFAIL
DetailsTroy Cobbley
Need the project related fire alarm permit finaled. Need approved hardware installed on the pocket doors, approved hardware on the south exit door and the east exit door. Need the exit discharge light repaired at the main north exit. Curbing needs painted for fire dept access. One additional fire extinguisher is needed in the second floor corridor.
BLD-Conference1/8/20091/8/20091/8/2009PPASS
DetailsTom Arcoraci
BLD-Conference1/8/20091/8/20091/8/2009APASS
DetailsTom Arcoraci
BLD-Wall cover11/20/200811/21/200811/21/2008PCANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 11/20/2008 at 12:58:03 PM. Contact: ###-####. grid ok
BLD-Wall cover10/31/200811/3/200811/3/2008APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 10/31/2008 at 1:17:29 PM. Contact: ###-####.
BLD-Energy code compliance10/7/200810/7/200810/7/2008PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/7/2008 at 10:49:30 AM. Contact: ###-####.ok to cover ext walls
BLD-Energy code compliance9/19/20089/19/20089/19/2008APASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/19/2008 at 7:10:14 AM. Contact: ###-####.
BLD-Wall cover9/16/20089/17/20089/17/2008PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 9/16/2008 at 5:30:10 PM. Contact: ###-####. Verified vapor barrier at 2nd floor ceiling, north half. ok to cover.
BLD-Wall cover9/16/20089/17/20089/17/2008APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/16/2008 at 1:57:41 PM. Contact: ###-####.
Interior and exterior nailing for shear (at stair towers) ..... and both stair tower walls OK ......OK to insulate, rock and stucco.
BLD-Energy code compliance9/12/20089/15/20089/15/2008APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/12/2008 at 12:46:28 PM. Contact: ###-####. 2-3 b-c attic blowen full.
BLD-Framing/Rough-in9/4/20089/4/20089/4/2008PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 9/4/2008 at 7:49:25 AM. Contact: ###-####. Nailing and straps for roof diaphragm between grids 1-4 and C-D.
BLD-Wall cover9/2/20089/3/20089/3/2008PDONE
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/2/2008 at 10:54:35 AM. Contact: ###-####.
BLD-Wall cover9/2/20089/2/20089/2/2008PPART
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/2/2008 at 7:50:48 AM. Contact: ###-####.
(2) Interior shear walls.... Lobby rm 151 and near West stair tower..... OK
BLD-Other8/28/20088/29/20088/29/2008APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/28/2008 at 1:47:12 PM. Contact: ###-####. Inspected nailing for roof diaphragm and verified required straps between gris 1-7 and a-b
BLD-Wall cover8/25/20088/26/20088/26/2008PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 8/25/2008 at 4:53:18 PM. Contact: ###-####.
Roof framing OK
BLD-Framing/Rough-in8/26/20088/26/20088/26/2008PPART
DetailsJim Sly
Scheduled by ###-####
OK to totally fill roof joist bays in leiu of installing sprinklers.....roof framing ok
BLD-Energy code compliance8/26/20088/26/20088/26/2008APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 8/26/2008 at 6:46:22 AM. Contact: ###-####.
1st floor select Ext. walls
BLD-Framing/Rough-in8/21/20088/22/20088/22/2008PPART
DetailsJim Sly
Scheduled by a contractor via Hello! on 8/21/2008 at 5:14:27 PM. Contact: ###-####.
!st floor appears OK........Needs firestop on a few through electrical box penitrations at 1hr walls.
BLD-Conference7/31/20088/1/20088/1/2008PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 7/31/2008 at 3:34:26 PM. Contact: ###-####.
BLD-Conference7/30/20087/31/20087/31/2008PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 7/30/2008 at 3:27:30 PM. Contact: ###-####.
BLD-Conference7/29/20087/30/20087/30/2008PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 7/29/2008 at 2:15:35 PM. Contact: ###-####. easr side is afull fill of insulation in ceiling
BLD-Framing/Rough-in7/24/20087/25/20087/25/2008PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 7/24/2008 at 8:19:04 AM. Contact: ###-####. lid ok pending other inspections
CHANGE STATUS TO (ISS)  6/20/2008  
previously issued- plan mod
(F) Reprint permit  6/20/2008  
OVERRIDE  6/19/2008  
Print Occupancy Form  6/19/2008 DONE
Telephone call  6/19/2008 DONE
DetailsBarbara Stitt
Called Eric Packer and left voice message that plan mod is ready and fees due///6-19-08 @ 10:52am BAS
Permit Ready to Issue  6/19/2008 DONE
DetailsBarbara Stitt
Plan assigned to (JCM)6/13/20086/13/20086/18/2008 PASS
DetailsJohn Menard
6/18/2008 16:18:37 JCM - activity updated through activity BLDA022 from case BLD08-00234.
Routing - PLUMBING6/17/2008 6/18/2008 PASS
DetailsBill VanDegrift
no plumbing
Routing - PLAN CHECK6/18/2008 6/18/2008 PASS
DetailsJohn Menard
Plan modification to relocate a parking lot drainage field location.
PLANS/APPL TAKEN TO FRONT DESK  6/18/2008 DONE
Routing - PUBLIC WORKS6/16/2008 6/17/2008 PASS
DetailsBeverly Hall
Routing PW Drainage6/16/2008 6/17/2008 PASS
DetailsBrian Murphy
Plan Modification Accepted  6/13/2008  
DetailsJohn Menard
plan modification excepted for Bld08-00234 for the redesign to construct a new seepage bed to relocate & replace an existing parking lot seepage bed. the existing seepage bed over laps the building foundation & will require to be moved. a new bed will be constructed further south. the exising catch basin location will direct storn via pipe to the new basin on sheets C2 of C4 (paving & landscaping no affected)routed to John Menard.
BLD-Foundation5/29/20085/30/20085/30/2008APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 5/29/2008 at 3:10:32 PM. Contact: ###-####.
BLD-Footing5/23/20085/27/20085/27/2008APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 5/23/2008 at 12:38:23 PM. Contact: ###-####. spec insp on site
(F) Reprint permit  5/7/2008  
Issue PAID IN FULL permit  5/6/2008 DONE
Routing - PUBLIC WORKS4/28/2008 4/28/2008 PASS
DetailsLouise Waldorf
Original sign off was on 2-27-08.
Print Occupancy Form  4/25/2008 DONE
Telephone call  4/25/2008 DONE
left vm for zack lester at ###-#### - permit ready and fees given - also need gc name, rce#, rp name and ACHD receipt
Permit Ready to Issue  4/25/2008 DONE
Plan assigned to (JCM)2/11/2008 4/24/2008 PASS
DetailsJohn Menard
4/24/2008 13:52:56 JCM - activity updated through activity BLDA022 from case BLD08-00234.
Routing - PLANNING3/4/2008 4/24/2008 FAIL
DetailsAndrea Tuning
The applicant has not submitted revised drawings to DR or CU staff addressing the conditions of approval. The applicant was also required to provide a shared parking agreement. This document has not been submitted at this time. ANT ###-#### 3-4-08.

drh07-00551 Andrea Tuning & cup07-00163 for Josh Wilson
Routing - PLANNING4/23/2008 4/24/2008 PASS
DetailsJoshua Johnson
Approved per DRH07-00551 4-24-08 ANT.
Approoved per CUP07-00163. 4-24-08 JRJ

Routed to John Menard
Routing - PLAN CHECK4/24/2008 4/24/2008 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  4/24/2008 DONE
DetailsJohn Menard
Plan Reviewer's activity  4/23/2008 PASS
DetailsJohn Menard
Reviewed and approved revised plans with red lined notes and attached comment list. JCM
Routing - PLAN CHECK4/11/2008 4/23/2008 PASS
DetailsJohn Menard
Plan resubmittals received  4/18/2008  
Received 1 cover transmittal, 1 copy of response dated 4-16-08 from CTA, 1 copy of 2006 Envelope Compliance, 1 copy of cover transmittal from CTA dated 4-15-08, , 1 copy of plan review comments, 2 sets of sheets EC101, F101, sheet C1 of C4, sheet C2 of C4, sheet C3 of C4, sheet C4 of C4, L303, A001, A002, A003, A004, A006, A102, A401, A403, A501, A502, A701, A801, A802, A804, A901, A902, inserted into plans and taken back to John Menards desk///4-18-08 @ 10:00am BAS
1st review completed  4/11/2008 FAIL
Failed PW, Structural, Plumbing, Planning, Plan Check
Routing - FIRE4/7/2008 4/11/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
Routing - PLAN CHECK3/4/2008 4/7/2008 FAIL
DetailsJohn Menard
John Menard
Plan Reviewer's activity  4/7/2008 PASS
DetailsJohn Menard
Reviewed and approved structural calculation revisions. JCM
Plan resubmittals requested  4/7/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing - PLUMBING4/7/2008 4/7/2008 PASS
DetailsBill VanDegrift
per resubmitted plans dated 3/11/08 and 2003 upc
Plan resubmittals received  3/26/2008  
Received 1 cover transmittal, and 3 copies of sheets L301, L302, L303, L401, L402, L403 and inserted by CTA runner and taken back to John Menard's desk 3-26-08 @ 4:10pm BAS
Plan resubmittals received  3/21/2008  
Received 1 cover transmittal, 4 copies of sheets c1 of c4, c2 of c4, c3 of c4, c4 or c4, A0001, A0002, A0003, A00004, F102 and inserted by CTA and taken to John Menard///3-21-08 @ 4:34pm BAS
Plan resubmittals received  3/11/2008  
Received transmittal, three copies of sheets P300, P302, and two copies of three page plumbing details; inserted by arch. rep. and taken back to John Menard
Routing - PLUMBING2/28/2008 3/4/2008 FAIL
DetailsBill VanDegrift
each dental chair with water will require it's own reduced pressure backflow preventor located over a floor sink. provide a new detail. notes 3&4 page P302- pipe intake for the air compressor and the exhaust for the vacuum pump to the exterior, terminate per NFPA 99C. additional cross connection protection may be required.
Routing - Erosion and Sediment2/27/2008 2/28/2008 PASS
DetailsSteven Webb
ESC plan approved with attached conditions. Refer to ESC08-00234.
Routing PW Solid Waste2/26/2008 2/27/2008 PASS
DetailsPeter J. McCullough
Routing - PUBLIC WORKS2/22/2008 2/27/2008 PASS
DetailsBeverly Hall
per Brian Murphy route to public works
Routing PW Street Lights  2/26/2008 PASS
DetailsBill Colson
Routing PW Sewer Rating2/26/2008 2/26/2008 PASS
DetailsLouise Waldorf
Routing PW Drainage2/25/2008 2/25/2008 PASS
DetailsBrian Murphy
Plan resubmittals requested  2/22/2008 DONE
DetailsJohn Menard
Faxed the architect a copy of the structural review requesting revisions. JCM
Plan resubmittals received  2/22/2008  
received "5" sheets each of Cz of C4 --plans re-routed to public works
Routing Off Site - STRUCTURAL2/11/2008 2/22/2008 FAIL
DetailsJohn Menard
called action couries at ###-#### for pickup - Received comment list from the consulting structural engineer requesting revisions. JCM
Routing PW Drainage2/12/2008 2/21/2008 FAIL
DetailsBrian Murphy
Need 20% drainrock on swale bottom.BRIAN MURPHY ###-####
(F) Reprint permit  2/12/2008  
Routing - PUBLIC WORKS2/12/2008 2/12/2008 PASS
DetailsDave Abo
Routing - PLANNING Land Div2/12/2008 2/12/2008 PASS
DetailsDave Abo
Legal parcel existed prior to October 30, 1965. (Combined parcel comprised of parts of 4 original lots)
Plans ACCEPTED BY PLAN TECH  2/11/2008  
Application received  2/11/2008  
Pending Assignment by MYS2/11/2008 2/11/2008 DONE
DetailsJohn Menard
2/11/2008 13:48:35 JCM - activity updated through activity BLDA166 from case BLD08-00234.
Recd Pcfee & Taken To Pln CK  2/11/2008  
Plan routing begun/NEW & ADDTN  2/11/2008  
PubWorks Occupancy Approval1/15/20091/15/2009   
Signed final occupancy 01/13/09