Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD08-00281
StatusFinaled
Name THE RUSSELL CORPORATION
Site Address 9196 W EMERALD ST Unit: 135
Project NamePINNACLE SQUARE
Customer Number 
ePlanReviewNo
Description
*(BUSINESS IQ LLC)* - (PINNACLE SQUARE - STE 135) To construct a 2,018 sq.ft. office tenant in an existing shell building (BLD07-02611) per approved plans. This office building allowed in M-1D zone under CUP99-00166. Work to include construction of two accessible restrooms, installation of a suspended ceiling system, construction of interior partitions, and interior finishes in compliance with Ch. 8 of the 2006 IBC. PARTIAL PERMIT ISSUED 3/10/2008. This building is fully fire sprinklered for area increase, any alterations or modifications to the sprinkler system shall be per NFPA #13 as regulated by the fire department.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD8/11/20088/11/20089/4/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 6/3/20088/11/2008 DONE
Case Summary (BLD)  6/17/2008 DONE
BLD-Final6/2/20086/3/20086/3/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 6/2/2008 at 2:14:10 PM. Contact: ###-####. Vertical grab bars installed at correct height. tempered glazing installed. ok for perm occ.
Permanent Occupancy  6/3/2008 DONE
DetailsCathy Weisshaupt
BLD-Final5/21/20085/22/20085/22/2008PPART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 5/21/2008 at 2:56:07 PM. Contact: ###-####. ok for temp occ. Needs to mount vertical grab bar at correct height. Install remaining safty glazing.
FIRE-Final Inspection5/21/20085/22/20085/22/2008APASS
DetailsTroy Cobbley
Life safety passed
Temporary Occupancy5/22/20088/20/20085/22/2008 DONE
DetailsCathy Weisshaupt
BLD-Other5/13/20085/14/20085/14/2008PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 5/13/2008 at 4:25:55 PM. Contact: ###-####.
BLD-Other5/14/20085/14/20085/14/2008APASS
DetailsMike Jordan
BLD-Other5/12/20085/13/20085/14/2008PDEFR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 5/12/2008 at 10:37:12 AM. Contact: ###-####. no time
CHANGE STATUS TO (ISS)  4/22/2008 DONE
this plan mod was put on wrong bld. It goes to bld08-00281
Plan assigned to (TLW)4/17/2008 4/21/2008 DONE
DetailsTim L. Woodard
Plan mod approved.**TLW**
PLANS/APPL TAKEN TO FRONT DESK  4/21/2008 DONE
this plan mod should have been on bld08-00281 not 08-00280
Case Summary (BLD)  4/21/2008 DONE
Print Occupancy Form  4/21/2008 DONE
Telephone call  4/21/2008 DONE
t/c w dawna jenkins at ###-#### - permit ready and fees given
Permit Ready to Issue  4/21/2008 DONE
Plan Modification Accepted  4/17/2008  
plan modification accepted for bld08-00281 for the redesign of changing "2" offices to "3". No change in square footage. on sheets A-1, M-1, P-1, E-1, & E-2. Routed to Tim Woodard.
BLD-Energy code compliance4/8/20084/9/20084/9/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 4/8/2008 at 7:29:08 PM. Contact: ###-####.
BLD-Framing/Rough-in4/8/20084/9/20084/9/2008APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 4/8/2008 at 7:28:33 PM. Contact: ###-####. Interior steel stud framed walls and hardlid only. no grid.
Issue PAID IN FULL permit  4/8/2008 DONE
Print Occupancy Form  4/7/2008 DONE
Telephone call  4/7/2008 DONE
t/c w dawn jenkins at ###-#### - permit ready and fees given
Permit Ready to Issue  4/7/2008 DONE
Routing - PLAN CHECK4/3/2008 4/4/2008 PASS
DetailsTim L. Woodard
Plans approved with redlines.
PLANS/APPL TAKEN TO FRONT DESK  4/4/2008 DONE
Plan assigned to (TLW)2/21/2008 4/4/2008 PASS
DetailsTim L. Woodard
4/4/2008 15:48:19 TLW - activity updated through activity BLDA022 from case BLD08-00281.
Routing - FIRE3/30/2008 4/3/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  4/3/2008 PASS
Routing - PLAN CHECK2/22/2008 3/30/2008 PASS
DetailsTim L. Woodard
Approval per approved plans and plan review report attached.
Plan Reviewer's activity  3/10/2008 DONE
PARTIAL PERMIT issued at the request of Jonathan Seel representing the parcel owner. See CONDITION attached to this permit.
Early Start Permit  3/10/2008 DONE
DetailsTisha Gallop
Telephone call  3/10/2008 DONE
DetailsTisha Gallop
called Jonathan Seel and told him partial permit is ready for pick up
Routing - PUBLIC WORKS2/21/2008 2/22/2008 PASS
DetailsBeverly Hall
Routing PW Sewer Rating2/22/2008 2/22/2008 PASS
DetailsLouise Waldorf
Pending Assignment by MYS2/19/2008 2/21/2008 DONE
DetailsMarlene Southard
2/21/2008 15:50:55 MYS - activity updated through activity BLDA185 from case BLD08-00281.
Plans ACCEPTED BY PLAN TECH  2/20/2008  
Application received  2/19/2008  
Recd Pcfee & Taken To Pln CK  2/19/2008