Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD08-00399
StatusFinaled
Name HILL CONSTRUCTION CO
Site Address 8585 W OVERLAND RD
Project Name 
Customer Number 
ePlanReviewNo
Description
Boise New Hope of the Nazarene Church (Addition) To convert the sanctuary, offices, storage and entry in the existing 4,180 square foot building to additional classrooms and nursery. The existing building will contain classrooms and restrooms. To construct a 10,220 square foot, one story addition on the east side of the existing church building. The addition will contain new administrative offices, restrooms, large entry, sanctuary, multi-purpose room, kitchen and storage room. All areas of this building will be fully fire sprinkled. The sprinklers are used for area increase. All construction per the approved plans and attached comment list. JCM nstruct as
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 2/24/20092/26/2009 DONE
Permanent Occupancy  2/24/2009 DONE
DetailsBarbara Stitt
BLD-Final2/19/20092/20/20092/20/2009APASS
DetailsTom Arcoraci
john - mid-morning please Phone #: ###-####
FIRE-Final Inspection2/19/20092/20/20092/20/2009APASS
DetailsTroy Cobbley
fire life safety passed
BLD-Other1/29/20091/29/20091/29/2009PPASS
DetailsJim Storey
john Note: sheet rock Phone #: ###-#### sw coner ok for cover.
BLD-Energy code compliance1/7/20091/8/20091/8/2009APASS
DetailsMike Jordan
john Phone #: ###-####
BLD-Other1/2/20091/2/20091/2/2009PPART
DetailsDave Hannah
JOHN - NOTE; COVER Phone #: ###-#### ok to insulate ok to one side contractor will use insulation for fire blocking on hallway walls
Temporary Occupancy UNPAID FEE  12/11/2008 DONE
BLD-Final12/8/200812/8/200812/8/2008PPASS
DetailsMike Jordan
john- temporary occupancy Phone #: ###-####. Ok for temp occ.
BLD-Final12/5/200812/5/200812/5/2008PNR
DetailsMike Jordan
Zoning Approval12/5/200812/5/200812/5/2008 PASS
DetailsAndrea Tuning
BLD-Final12/4/200812/4/200812/4/2008PNR
DetailsMike Jordan
john Phone #: ###-####
FIRE-Final Inspection12/1/200812/2/200812/3/2008APART
DetailsTroy Cobbley
Per Ken Roule and Mark Sentenno the new area can be occupied until the existing areas have been remodeled and the rest of the construction is completed.
FIRE-Final Inspection11/20/200811/21/200811/21/2008APART
DetailsTroy Cobbley
See redlined notes on city approved plans of area tested and completed. Contractor is looking for a temp occupancy for this area while they remodel the existing building under the same building permit. Contractor will be required tto contact Mark Senteno for temp occupancy. KR
Zoning Approval11/13/200811/13/200811/14/2008 FAIL
DetailsAndrea Tuning
The applicant has unfinished planter beds located along the front elevation, has one additional man door located on the north elevation, and has installed rock mulch throuhgout the site as opposed to the organic bark mulch that was approved with DRH07-00532 and DRH08-00103.

I have called the applicant and explained these issues.

ANT 11-14-08
BLD-Energy code compliance9/17/20089/18/20089/18/2008APASS
DetailsMike Jordan
John Phone #: ###-####. ok to cover.
BLD-Framing/Rough-in9/18/20089/18/20089/18/2008APART
DetailsMike Jordan
John Phone #: ###-####. All framing issues resolved. ok to insul. issued c/n to contractor to have architect supply detalis for 1hr wall and ceiling assemblies for fire riser room.
BLD-Framing/Rough-in9/8/20089/8/20089/8/2008PPART
DetailsMike Jordan
john Phone #: ###-####. Needs to do airseal, complete nailing of hangars,and girder trusses.
BLD-Conference8/25/20088/26/20088/26/2008APASS
DetailsMike Jordan
john Phone #: ###-####. ME twith contractor on site to go over specs for platform lift to stage.
BLD-Framing/Rough-in8/12/20088/12/20088/12/2008PNR
DetailsMike Jordan
john Phone #: ###-####. Needs ri insp. from other trades first.
BLD-Framing/Rough-in7/21/20087/22/20087/22/2008APART
DetailsMike Jordan
John Phone #: ###-####. Nailing for roof diaphragm, hand stack portion of roof framing and roof to cmuwall connections.
BLD-Framing/Rough-in7/10/20087/11/20087/11/2008APART
DetailsMike Jordan
john Phone #: ###-####. Shear nailing on exterior walls ok. Also reveiwed special insp. reports on puddle wels and joist to base plate connections for gym roof. ok. Als noted rfi from engineer on conversions for staples.
BLD-Framing/Rough-in7/7/20087/8/20087/8/2008APART
DetailsMike Jordan
John Phone #: ###-####. Need RFI from engineer of record for use of staples in leiu of nails for shear wall. Needs to provide straps at double top plate splices and complete install of straps from cmu wall to roof diaphragm.
BLD-Concrete6/10/20086/11/20086/11/2008ADEFR
DetailsMike Jordan
John Phone #: ###-####. Placement for slab on grade, non structural item. Special insp. on site. Will reveiw reports on next insp.
BLD-Other6/9/20086/10/20086/9/2008ACANC
DetailsMike Jordan
Scheduled by a contractor via Hello! on 6/9/2008 at 12:12:57 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jun 9 2008 1:04PM.
Plan resubmittals received  6/4/2008  
received "3" sheets each of C3.O1, C7.O1, & letter of transmittal from advanced engineering & drainage calcs. (6) pages----also "2"sets each of C1.O1,C2.O1, C3.O1, C4.O1, C5.O1, C6.O1, C6.O2, & C7.O1---plans taken to Brian Murphy
BLD-Footing5/29/20085/30/20085/30/2008ADEFR
DetailsMike Jordan
john Phone #: ###-####. Conc. placed when on site. Noted special insp. on site.
BLD-Foundation5/23/20085/23/20085/23/2008PPART
DetailsMike Jordan
john Note: pouring concrete at 1:00 pm Phone #: ###-####
BLD-Footing5/22/20085/22/20085/22/2008PPART
DetailsJim Sly
john - pouring at 2:30 Phone #: ###-####
Footing gridline F 5........Wall Gridline J 6.....OK pending MTI special inspections, tests, and approvals.
BLD-Footing5/21/20085/21/20085/21/2008PPART
DetailsMike Jordan
John; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt. Stemwall at existing bldg. and north side.
BLD-Footing5/19/20085/19/20085/19/2008PPART
DetailsMike Jordan
john Note: concrete coming by 1:00 Phone #: ###-####. North footing.
BLD-Footing5/15/20085/16/20085/16/2008APART
DetailsMike Jordan
john Phone #: ###-####. wip on perimeter footings. Noted that job wil have special insp. Also reviewed special insp. reports for soils work done to date. Noted to contractor that city approved plans need to be on the job site.
Issue PAID IN FULL permit  5/15/2008 DONE
CHANGE STATUS TO (RDY)  5/8/2008 DONE
Print Occupancy Form  5/7/2008 DONE
Routing - PLAN CHECK5/5/2008 5/6/2008 PASS
DetailsJohn Menard
Plan Reviewer's activity  5/6/2008 PASS
Reviewed and approved structural and nonstructural revisions with attached clarification list and red lined notes. JCM
PLANS/APPL TAKEN TO FRONT DESK  5/6/2008 DONE
DetailsJohn Menard
Plan assigned to (JCM)3/6/2008 5/6/2008 PASS
DetailsJohn Menard
5/6/2008 15:28:24 JCM - activity updated through activity BLDA022 from case BLD08-00399.
Routing - PLUMBING4/29/2008 5/5/2008 PASS
DetailsBill VanDegrift
per plans and 2003 upc
Plan resubmittals received  4/30/2008  
DetailsJohn Menard
Received 1 cover transmittal, 4 copies of sheet C4.01 and inserted into plans Advanced Engineering 4-30-08 @ 4:30pm BAS
Routing - PLANNING4/25/2008 4/29/2008 PASS
DetailsSusan Riggs
Per resubmitted site plan dated april 17, 2008 all street setbacks shall be a minimum of 20'.
Routing - PUBLIC WORKS4/23/2008 4/25/2008 PASS
DetailsBeverly Hall
Routing - PLAN CHECK4/21/2008 4/23/2008  
DetailsJohn Menard
Plan resubmittals received  4/22/2008  
DetailsJohn Menard
Received from upstairs Public works 2 copies of sheet A-1.1 and inserted in plans for John Menard 4-22-08 @ 10:00am BAS
Routing PW Sewer Design4/18/2008 4/21/2008 PASS
DetailsJon R. Gunnerson
Approximate location of sewer service for existing building depicted onto plans, sewer tap permit required
Routing PW Solid Waste4/21/2008 4/21/2008 FAIL
DetailsPeter J. McCullough
Increase enclosure gate opening to 12'. Peter McCullough, ###-####
Routing PW Sewer Rating4/21/2008 4/21/2008 PASS
DetailsLouise Waldorf
Routing - PUBLIC WORKS4/18/2008 4/21/2008 FAIL
DetailsLouise Waldorf
Routing - PLAN CHECK4/16/2008 4/18/2008  
Plan resubmittals received  4/17/2008  
received transmittal letter from arch northwest, "3" copies of structural calcs (28 pages, & "2" pages each of comment responses (3 total) also "3" sets of plans including sheets "7" sheets each of A-2.O, A-2.1, A-2.2, A-5.O, A-7.1, A-7.2, S-1.O with "2" copies--Also transmittal sheet from arch northwest & comment response letter (3) pages with "2" of each & "5" sheets each of A-1.O, A-3.O, A-3.2, A-3.3, A-7.O- with "2" sets---plans taken to
1st review completed  4/16/2008 FAIL
Failed Planning, Building, Structural, Public Works, Planning Land Div & Plumbing.
Routing - FIRE4/14/2008 4/16/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
Routing - PLAN CHECK3/26/2008 4/14/2008  
DetailsJohn Menard
John M
Plan resubmittals requested  4/14/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Plan resubmittals requested  4/7/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural review requesting revisions. JCM
Plan resubmittals received  4/2/2008  
received letter of transmittal from advanced engineering & "2" sheets of C4.O1-- plans taken back to John Menard
Plan resubmittals received  3/26/2008 DONE
received 1 transmittal, and 2 copies of sheet A-1.1 taken to John M.
Routing - PLANNING3/24/2008 3/26/2008 FAIL
DetailsSusan Riggs
Susan R. CUP07-00124-Fail; A streetside setback of 20' is required. Spoke with the Architect at 3:30 today. New architectural site plan will be required. CER 3-25-08

The landscape plan and elevations do not match what was approved through DRH07-00532. The applicant will be required to build what was approved or will be required to receive a DR modification. Applicant was called and notified of the requirements. Andrea Tuning ###-#### 3-26-08
Routing - PLUMBING3/21/2008 3/24/2008 FAIL
DetailsBill VanDegrift
provide a civil plan showing the rain drainage piping from the building to the point of disposal. provide a civil plan showing the new water service.
Routing - Erosion and Sediment3/21/2008 3/21/2008 PASS
DetailsSteven Webb
ESC plan approved with attached conditions. ESC08-00141.
Routing - PUBLIC WORKS3/11/2008 3/21/2008 FAIL
DetailsLouise Waldorf
Routing Off Site - STRUCTURAL3/10/2008 3/21/2008 FAIL
DetailsJohn Menard
Called Action Couriers for pick up - Received comment list from the consulting structural engineer requesting revisions. JCM
Routing PW Sewer Design3/11/2008 3/21/2008 FAIL
DetailsJon R. Gunnerson
Routing PW Solid Waste  3/21/2008 FAIL
DetailsPeter J. McCullough
Routing PW Environmental3/19/2008 3/19/2008 PASS
DetailsWalt Baumgartner
must use City approved design for kitchen grease interceptor. I attached cutsheet of approved design to both sets plans.
Routing PW Sewer Rating3/19/2008 3/19/2008 PASS
DetailsLouise Waldorf
Routing PW Street Lights  3/13/2008 PASS
DetailsBill Colson
Routing PW Drainage  3/13/2008 PASS
DetailsBrian Murphy
Routing - PLANNING Land Div3/12/2008 3/12/2008 PASS
DetailsJoan Johnson
recorded deed, notice of buildable parcel and Assessors Land records parcel activity form rec'd RS 8199 parcel consolidation ROS
Telephone call  3/11/2008 DONE
Notified Steve Z that a verification of legal lot worksheet is required.
Recd Pcfee & Taken To Pln CK  3/7/2008 DONE
Routing - PLANNING Land Div3/7/2008 3/7/2008 FAIL
DetailsJoan Johnson
building over lot lines - fail
Plans ACCEPTED BY PLAN TECH  3/7/2008  
Plan routing begun/NEW & ADDTN  3/7/2008  
Application received  3/5/2008  
Routing PW Solid Waste4/23/2008   PASS
DetailsPeter J. McCullough