Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD08-00406
StatusFinaled
Name EXCELSIOR CONSTRUCTION CO
Site Address 2121 N COLE RD
Project NameFAIRMONT JUNIOR HIGH SCHOOL
Customer Number 
ePlanReviewNo
Description
(FAIRMONT JUNIOR HIGH SCHOOL - LIBRARY & CLASSROOM SWITCH) To relocate the existing Library and shelving to the Industrial Arts room and add desks and equipment to the existing Shop room and vacated Library for use as classrooms. Each new room use area has or will have two exits with proper separation. To modify the electrical system within each room to allow proper function of required classroom equipment. Door hardware, exit signage and emergency egress illumination, if not existing is required to meet current code, 2006 IBC, Chapter 10. Scope of work does no increase building area, occupant load or occupancy use group. This building is NOT sprinklered. The existing exit corridor is listed as non-rated. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD1/29/20091/29/20093/10/2009 DONE
DetailsPatricia Smith
Second Notice has not been responded to.
Second Notice BLD1/2/20091/2/20091/29/2009 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice12/10/200812/10/20081/2/2009 DONE
DetailsJim Sly
BLD-Final12/10/200812/10/200812/10/2008PPASS
DetailsJim Sly
chris - please call 1/2 hr or more prior Phone #: ###-####
C/C issued
DOC - Permit Finaled12/10/200812/10/200812/10/2008PPASS
DetailsJim Sly
BLD-Final12/8/200812/10/200812/10/2008ACANC
DetailsJim Sly
Chris please call 30 min before going out Phone #: ###-####
FIRE-Final Inspection11/20/200811/21/200811/21/2008APASS
DetailsTroy Cobbley
Life safety completed. KR
BLD-Final11/6/200811/10/200811/10/2008ANR
DetailsMike Jordan
Chris Please call 1/2 before going out Phone #: ###-####. Needs life/safety final fist. Contacted Chris and number provided and left message.
BLD-Conference8/27/20088/28/20088/28/2008ADONE
DetailsJim Sly
Talked to Chris at Excelsior Constr...Need fire final and Bldg final.
BLD-Conference8/27/20088/27/20088/28/2008PCANC
DetailsJim Sly
David ###-####
Issue PAID IN FULL permit  5/28/2008 DONE
Inspection Record Card- Bld  4/8/2008 DONE
Telephone call  4/8/2008 DONE
t/c w david blenker at ###-#### -permit ready and fees given - also need gc name and rce#
Permit Ready to Issue  4/8/2008 DONE
Plan assigned to (DRS)3/12/2008 4/7/2008 PASS
DetailsDan Stuart
4/7/2008 16:23:21 DRS - activity updated through activity BLDA022 from case BLD08-00406.
Routing - FIRE4/2/2008 4/7/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  4/7/2008 PASS
Routing - PLAN CHECK4/7/2008 4/7/2008 PASS
DetailsDan Stuart
To permit desk to issue
PLANS/APPL TAKEN TO FRONT DESK  4/7/2008 PASS
Print Pending Permit.LaserJet4  4/2/2008  
Case Summary (BLD)  4/2/2008  
Routing - PLAN CHECK3/12/2008 4/2/2008 PEND
DetailsDan Stuart
Routing to fire code analyst.
Pending Assignment by MYS3/6/2008 3/12/2008 DONE
DetailsMarlene Southard
3/12/2008 14:28:26 MYS - activity updated through activity BLDA168 from case BLD08-00406.
Plans ACCEPTED BY PLAN TECH  3/6/2008 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  3/6/2008 DONE
DetailsTisha Gallop
Application received  3/6/2008  
DetailsTisha Gallop