Permit Information
Permit NumberBLD08-00418
StatusFinaled
Name MODULAR STRUCTURES INC
Site Address 1705 S MILWAUKEE ST
Project NameDARMODY OFFICE BLDG
Customer Number 
ePlanReviewNo
Description
Darmody Office Building - To construct a new 9,765 square foot, two story, wood framed office and storage building. There is also a 775 square foot storage mezzanine above storage area #115. Carport - Some of the construction documents indicate a carport on the north side of the proposed building. As indicated on the construction documents, this is a future addition and is not part of the scope of work under this building permit. A separate permit will be required to construct the carport. The future carport will need to be separated from those areas of the building required to be separted by fire barriers. First Floor: 6,225 sq. ft., Second Floor: 3,540 sq. ft.. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD3/4/20093/4/20093/9/2009 DONE
DetailsPatricia Smith
First Notice has not been responded to.
First Notice 1/30/20093/4/2009 DONE
Permanent Occupancy  1/30/2009 DONE
DetailsAlexandra L. DeYoung
BLD-Final1/22/20091/23/20091/29/2009PPASS
DetailsMike Jordan
carl Phone #: ###-####. ok for perm occ.
Zoning Approval1/22/20091/22/20091/29/2009 DONE
DetailsMatthew A Halitsky
Landscaping only. Inspection by Sue Cummings.
FIRE-Final Inspection1/22/20091/23/20091/23/2009APASS
DetailsTroy Cobbley
Life safety passed.
BLD-Final12/5/200812/5/200812/5/2008PPART
DetailsMike Jordan
OK for temp occ. Still needs to provide additional ada signage, instal vertical grab bars in restrooms and repair handrail in storage room, not bein utilized at this time.
FIRE-Final Inspection12/4/200812/5/200812/5/2008APART
DetailsTroy Cobbley
A temporary occupancy was given with sam rogers and gordon goldsmiths permission until the missing fire hydrant is installed, in-duct detectors are installed for operation of the fire/smoke dampers, the exit discharge light is repaired at the main exit, the "Area of Refuge" sign is provided with battery backup and permanent area of refuge signs are placed. Temporary signs have been installed at this time.
BLD-Final12/4/200812/5/200812/5/2008ADEFR
DetailsMike Jordan
carl Phone #: ###-####
Temporary Occupancy12/5/20083/5/200912/5/2008 DONE
DetailsAlexandra L. DeYoung
PubWorks Occupancy Approval12/5/200812/5/200812/5/2008  
Zoning Approval Temp12/5/200812/5/200812/5/2008 DONE
DetailsMatthew A Halitsky
Landscaping only. For final need DR inspection, additional plantings in front planter beds, clean rear lot and hydro-seed, screen rear condensers.
Telephone call  12/5/2008 DONE
Telcon from John Lee, United Water confirming they have received payment for the hydrant installation and work is anticipated to be completed by Dec 12, 2008. (Written confirmation received 12/8/08 attached under Doc's)
FIRE-Final Inspection12/2/200812/3/200812/3/2008AFAIL
DetailsTroy Cobbley
See the front sheet of the city approved drawings for the required corrections which include providing the missing fire hydrant, repair the exit discharge light at the main exit, provide emergency lighting in the main lobby, repair the area of refuge sign on the second floor, provide the area of refuge communication equipment and signage, provide the occupant load sign, mount fire extinguishers and provide the fire lane signage. Also the duct smoke detectors need to be replaced with spot type detectors that are listed for the air flow. These detectors are for damper operation.
FIRE-Conference11/25/200811/25/200811/25/2008PDONE
DetailsTroy Cobbley
carl Phone #: ###-####
BLD-Other11/20/200811/21/200811/21/2008APART
DetailsMike Jordan
carl - fire caulking Phone #: . Areas above grid ok. Needs to stub out at cleanout and make membrane penetration and provide collars at pvc pipe for soda machine.
BLD-Other11/19/200811/20/200811/20/2008APART
DetailsMike Jordan
carl Note: ceiling grid Phone #: ###-####. Ceiling grid, 1st. floor ok, except at areas around 1 and 2 hr. walls. fire caulking not yet complete. Tiles will be left out at these areas.
BLD-Framing/Rough-in11/18/200811/19/200811/19/2008APASS
DetailsMike Jordan
carl - first thing in the morning please Phone #: ###-####. handrail ok.
BLD-Other11/12/200811/12/200811/12/2008PPART
DetailsMike Jordan
carl Note: ceiling grid Phone #: ###-####. Ceiling grid 2nd. floor only. Pend. mech and elec.
BLD-Conference11/10/200811/10/200811/10/2008PPASS
DetailsMike Jordan
BLD-Other11/5/200811/6/200811/6/2008AFAIL
DetailsMike Jordan
CARL Phone #: ###-####. Grid ceiling on 2nd. floor not installed as per approved plan. Also still needs elec. and mech ri insp. above grid.
BLD-Framing/Rough-in10/10/200810/13/200810/13/2008APASS
DetailsMike Jordan
Carl Phone #: ###-####. Verified dratstop at 2nd floor and all fireblocking.
BLD-Framing/Rough-in10/6/200810/6/200810/6/2008PPART
DetailsMike Jordan
1st layer 5/8 type for ceiling assembly.
BLD-Energy code compliance9/29/20089/30/20089/30/2008APASS
DetailsMike Jordan
carl Phone #: ###-####. ok to cover.
BLD-Framing/Rough-in9/30/20089/30/20089/30/2008APASS
DetailsMike Jordan
carl Phone #: ###-####. Interior and exterior wood framed walls on 1st. floor and storage area. 1st and 2nd layers of 5/8 type x at 2hr. walls.
BLD-Energy code compliance9/25/20089/26/20089/26/2008PNR
DetailsMike Jordan
Carl- early pm please Phone #: ###-####
BLD-Framing/Rough-in9/26/20089/26/20089/26/2008PPART
DetailsMike Jordan
Carl- early pm please Phone #: ###-####. Screw pattern for 1st. layer of 5/8 typex at 2hr wall.
BLD-Framing/Rough-in9/25/20089/25/20089/25/2008PPART
DetailsMike Jordan
Interior wood framed walls on 2nd fllor and hardlids. ok to insul.
BLD-Framing/Rough-in9/12/20089/12/20089/12/2008APART
DetailsMike Jordan
Interior shearwall at south stairtower and breakroom. Needs to install straps on girder trusses to beam and need approval from engineer of record for use of staples.
BLD-Framing/Rough-in9/8/20089/8/20089/8/2008PPART
DetailsMike Jordan
carl Phone #: ###-####. Went over 1hr and two const. requirements.
BLD-Foundation8/5/20088/5/20088/5/2008PPASS
DetailsMike Jordan
carl - as early as possible please Phone #: ###-####. Interior column pad footing in storage garage.
BLD-Footing8/4/20088/4/20088/4/2008PNR
DetailsMike Jordan
Carl Phone #: ###-####
BLD-Footing7/18/20087/21/20087/21/2008APART
DetailsMike Jordan
steve Note: mud in 10:30 am Phone #: ###-####. Perimeter stemwalls and elevator pit walls. Will have special insp.
BLD-Footing7/14/20087/14/20087/16/2008PDEFR
DetailsMike Jordan
Steve Phone #: ###-####. Special insp. conc. placed in am.
(F) Reprint permit  6/30/2008  
Issue PAID IN FULL permit  6/27/2008 DONE
Telephone call  6/24/2008 DONE
Details
t/c w patrick mckeegan at ###-#### - permit ready and fees given - also need ACHD receipt
Permit Ready to Issue  6/24/2008 DONE
Details
Plan Reviewer's activity  6/23/2008 PASS
DetailsJohn Menard
Reviewed and approved final structural revisions for truss change at south stair enclosure. JCM
PLANS/APPL TAKEN TO FRONT DESK  6/23/2008 DONE
Print Occupancy Form  6/23/2008 DONE
Details
Routing - PLAN CHECK6/10/2008 6/23/2008 PASS
DetailsJohn Menard
Plan assigned to (JCM)3/10/2008 6/23/2008 PASS
DetailsJohn Menard
6/23/2008 09:52:05 JCM - activity updated through activity BLDA022 from case BLD08-00418.
Plan resubmittals requested  6/20/2008 DONE
DetailsJohn Menard
E-mailed the architect and requested structural calculations to go with the revised structural plans. JCM
Plan resubmittals received  6/19/2008  
DetailsJohn Menard
Received 1 cover transmittal, 2 copies of sheets S1.1, S2.1, S2.3 and inserted into plans by McKeegan Architects 6-19-08 @ 10:13am BAS
Plan resubmittals requested  6/18/2008 DONE
DetailsJohn Menard
E-mailed the architect a request for a revise truss layout. JCM
Plan resubmittals received  6/13/2008  
received comment letter from patrick mckeegan & "2" sets of plans with each sheet of A2.1,A2.3, A2.4, A5.2, A5.3, & A5.4- plans taken back to John Menard-- inserter is Mark Otto
Plan resubmittals received  6/13/2008  
DetailsJohn Menard
Received 2 copies of sheet H1.0 and inserted into plans by Signature Engineering///6-13-08 @ 11:07am BAS
Plan resubmittals requested  6/12/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of a letter requesting additional revisions. JCM
Plan resubmittals received  6/10/2008  
DetailsJohn Menard
Received letter and two copies of sheets A0.0, A2.1, A2.3, A2.4, A5.1, A5.2, A6.1, A6.4, A7.1; inserted by arch. rep. and taken back to John Menard
Routing - FIRE6/9/2008 6/10/2008 PASS
DetailsScott Arellano
Attached updated IFC comments to plans
Routing - PLAN CHECK6/4/2008 6/9/2008 FAIL
DetailsJohn Menard
Plan Reviewer's activity  6/9/2008 PASS
DetailsJohn Menard
Reviewed and approved structural revisions. JCM
Plan resubmittals requested  6/9/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of a letter requesting additional plan revisions. JCM
Routing - PLANNING6/4/2008 6/4/2008 PASS
DetailsMatthew A Halitsky
Resubmitted plans do not affect DR approval.

Routed to Plan Check (John M.)
Routing - PLUMBING5/28/2008 6/2/2008 PASS
DetailsBill VanDegrift
per revised plans and 2003 upc
Routing PW Environmental5/28/2008 5/28/2008 PASS
DetailsWalt Baumgartner
warehouse shop trench drain connects to flamm interceptor, OK
Routing - PUBLIC WORKS5/15/2008 5/28/2008 PASS
DetailsBeverly Hall
Routing PW Sewer Design5/20/2008 5/27/2008 PASS
DetailsJim Pardy
Approximate location of existing sewer service shown on plans, SEWER TAP PERMIT REQUIRED
Plan resubmittals received  5/21/2008  
Received two copies of sheets P1.0, P2.1; inserted by arch. rep. and taken back to Connie B. in Public Works
Routing PW Drainage5/16/2008 5/20/2008 PASS
DetailsBrian Murphy
Routing PW Environmental5/15/2008 5/16/2008 FAIL
DetailsWalt Baumgartner
Plans show interior trench drain routed to single chamber sump. Must use City approved design flammable liquids interceptor. Call Pretreatment office at ###-#### for info.
Telephone call  5/15/2008  
Talked with Ryan Carnie about submitting revised utility plan.
Routing PW Street Lights5/15/2008 5/15/2008 PASS
DetailsBill Colson
Routing PW Sewer Design5/15/2008 5/15/2008 FAIL
DetailsJon R. Gunnerson
Waiting for revised utility plan (sheet 2 of 6)
Routing - PLUMBING5/13/2008 5/15/2008 FAIL
DetailsBill VanDegrift
not ready for review must pass public works pretreatment review prior to plumbing review.
Routing PW Street Lights3/21/2008 5/15/2008 PASS
DetailsBill Colson
CALLED PATRICK MCKEEGAN ARCHITECTS INFORMED DON THAT STREET LIGHT PLAN WOULD NEED TO BE SUBMITTED FOR REVIEW
Routing - PLAN CHECK4/25/2008 5/13/2008  
DetailsJohn Menard
Plan resubmittals received  5/8/2008  
Received two copies of response letter, structural calcs, sheets A0.0, A2.1, A2.2, A2.3, A2.4, A2.7, A3.1, A5.1, A5.2, A5.3, A5.4, A6.2, A6.4, A7.2, A8.1, S0.1, S1.1, S2.1, S2.2, S2.3, E1.0, E1.1, E2.0, E2.1, E3.0, E4.0; inserted by arch. rep and taken back to John Menard.
1st review completed  4/25/2008 FAIL
Failed PW, Structural, Plumbing, Planning, Plan Check, Fire
Routing - FIRE4/23/2008 4/25/2008 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
Routing - PLAN CHECK4/7/2008 4/23/2008 FAIL
DetailsJohn Menard
John Menard.
Plan resubmittals requested  4/23/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Plan resubmittals requested  4/15/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural review requesting revisions. JCM
Plan resubmittals received  4/14/2008  
Received transmittal and two copies of sheets P1.0, P1.2, P2.1; inserted by arch rep. and taken back to John Menard
Routing - PLANNING4/3/2008 4/7/2008 PASS
DetailsMatthew A Halitsky
DRH07-00595 Matt Halitsky
Routing - PLUMBING3/25/2008 4/3/2008 FAIL
DetailsBill VanDegrift
12.56 sq. in. of venting required for the office area. 7.06 sq, in, of venting required on the shop area. list all fixtures on the fixture schedule. public works must pass pretreatment and sewer design review prior to plumbing review acceptance,
Routing Off Site - STRUCTURAL3/10/2008 3/31/2008 FAIL
DetailsJohn Menard
Received comment list from the consulting structural engineer requesting revisions. JCM
Routing PW Drainage3/26/2008 3/26/2008 PASS
DetailsBrian Murphy
Routing - Erosion and Sediment3/23/2008 3/25/2008 PASS
DetailsJames Rogers
Routing PW Solid Waste  3/24/2008 PASS
DetailsPeter J. McCullough
Routing PW Sewer Rating3/21/2008 3/21/2008 PASS
DetailsLouise Waldorf
Routing PW Sewer Design3/20/2008 3/21/2008 FAIL
DetailsJon R. Gunnerson
Routing - PUBLIC WORKS3/11/2008 3/21/2008 FAIL
DetailsLouise Waldorf
Plan resubmittals received  3/18/2008  
received tranmittal from patrick mekeegan & "5" sheets of C3.O1-- Louise Waldorf came & picked up plans from my desk
Routing PW Drainage3/11/2008 3/17/2008 FAIL
DetailsBrian Murphy
NO RAPID SAND FILTER IN SWALE GRASS LENGTH IN O&M PLAN FOR SEEPAGE BED. BRIAN MURPHY ###-####
Routing - PLANNING Land Div3/11/2008 3/11/2008 PASS
DetailsDave Abo
Lot 4, Block 1, Monterey Subdivision
(F) Reprint permit  3/11/2008 DONE
Plans ACCEPTED BY PLAN TECH  3/11/2008  
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  3/11/2008 DONE
DetailsTisha Gallop
Plan routing begun/NEW & ADDTN  3/11/2008 DONE
DetailsTisha Gallop
Telephone call  3/10/2008 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Application received  3/10/2008  
DetailsTisha Gallop
Pending Assignment by MYS3/10/2008 3/10/2008 DONE
DetailsJohn Menard
3/10/2008 15:07:12 JCM - activity updated through activity BLDA166 from case BLD08-00418.