Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD08-00512
StatusFinaled
Name KRBC HOLDINGS LLC
Site Address 1945 N WILDWOOD AVE
Project NameSTEELWOOD FLEX CONDOS
Customer Number 
ePlanReviewNo
Description
(KRBC HOLDINGS LLC - STEELWOOD UNITS 8-10) This building is NOT fire sprinklered. To create a 8,520 square foot two story office, storage, and fabrication tenant space within a new building (5,890 square foot 1st story, 2,630 square foot 2nd story, 564 square foot 2nd story unfinished attic, 617 square foot 2nd story mechanical equipment attic, and 82 square foot enclosed stairway at the 2nd story). The 2nd story will be constructed under this permit and includes concrete footings, steel columns, wood beams, bearing walls, shear walls, TJI floor joists, wood ledgers, and wood floor sheathing. Other work includes interior nonbearing walls, 3 restrooms accessible to the disabled, 1 private restroom adaptable to the disabled, a 1-hr stairway enclosure, an open stairway, suspended acoustical ceilings, and interior finishes. An incidental use separation is required around the 2nd story storage room. Two attic areas located on the 2nd story (564 square foot unfinished attic and 617 square foot mechanical equipment attic) are considered to be attic areas because the ceiling height will be less than 5 feet tall. These attic areas do not add any floor area to this tenant space. Neither attic area is approved for storage. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD1/29/20091/29/20092/5/2009 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD1/2/20091/2/20091/29/2009 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 11/5/20081/2/2009 DONE
BLD-Final11/4/200811/5/200811/5/2008APASS
DetailsJim Sly
ELE is final now
OK for Perm Occ.
Permanent Occupancy  11/5/2008 DONE
BLD-Final10/10/200810/13/200810/13/2008APART
DetailsJim Sly
joe Phone #: ###-####
OK for Temp Occ........OK to Perm when Electrical perms. (electr on Temp)
Temporary Occupancy10/13/20081/11/200910/13/2008 DONE
DetailsTisha Gallop
BLD-Final10/1/200810/1/200810/1/2008PFAIL
DetailsJim Sly
Joe Would like this to be a temp final Phone #: ###-####
Need handrails at both sides......(2) stairways.
BLD-Final8/29/20088/29/20088/29/2008PFAIL
DetailsJim Sly
dave Phone #: ###-####
C/N posted...... Note......Plumbing on Temp....
FIRE-Final Inspection8/28/20088/29/20088/29/2008APASS
DetailsTroy Cobbley
fire life safety passed
FIRE-Final Inspection8/28/20088/28/20088/28/2008PFAIL
DetailsTroy Cobbley
The duct smoke detectors have not been installed correctly. Per the plans and HVAC schedules they are not required. I gave the contractor the option to either install and test or to remove the duct smoke detectors. All other items are ok.
BLD-Other8/19/20088/19/20088/19/2008PPASS
DetailsJim Sly
david Note: ceiling grid Phone #: ###-####
BLD-Other8/15/20088/15/20088/15/2008PNR
DetailsMike Jordan
Dave- ceiling grid Phone #: ###-####. Needs mech ri insp. first.
(F) Reprint permit  8/14/2008 DONE
BLD-Framing/Rough-in7/15/20087/16/20087/16/2008APART
DetailsMike Jordan
dave Phone #: ###-####. 1hr ceiling enclosure on rated stairway.
BLD-Conference6/30/20087/1/20087/1/2008APASS
DetailsJim Sly
/Mark ###-####
1hr wall /ceiling ok
BLD-Framing/Rough-in6/30/20086/30/20086/30/2008PCANC
DetailsJim Sly
Mark Phone #: ###-####
FIRE-Final Inspection6/27/20086/27/20086/27/2008PPART
DetailsForrest France
See city approved plans for area marked in red for tempory occupancy. As per Mark Senteno.Door hardware, exit signs, egress lights and fire extinguishers are approved.One hour rated fire wall shall be completed and approved by Jim Sly before area occupancy. KR
FIRE-Final Inspection6/25/20086/26/20086/26/2008APEND
DetailsForrest France
This permit was to be a fire conf. Not a final. Contractor wanted a tempory occupancy. Refered him to Dave Hannamen.KR
BLD-Framing/Rough-in6/25/20086/26/20086/26/2008APASS
DetailsJim Sly
Mark Phone #: ###-####
OK to cover 1hr walls and 1hr ceilings.
BLD-Framing/Rough-in6/19/20086/20/20086/20/2008ADONE
DetailsJim Sly
Scheduled by a contractor via Hello! on 6/19/2008 at 12:11:17 PM. Contact: ###-####.
Conference with Mark.
BLD-Footing5/29/20085/30/20085/30/2008APART
DetailsMike Jordan
Scheduled by a contractor via Hello! on 5/29/2008 at 4:21:18 PM. Contact: ###-####.wip.
Issue PAID IN FULL permit  5/28/2008 DONE
Telephone call  5/6/2008 DONE
DetailsTisha Gallop
Spoke with Mark Vangulick w/Vertical Construction. Told him permit fees and need ACHD
Plan assigned to (CJW)3/24/2008 4/29/2008 PASS
DetailsCarl Westfall
4/29/2008 07:14:49 CJW - activity updated through activity BLDA022 from case BLD08-00512.
PLANS/APPL TAKEN TO FRONT DESK  4/29/2008 DONE
Print Occupancy Form  4/29/2008  
Telephone call  4/29/2008 DONE
Called Elizabeth Cooper permit ready and fee given . Also need ACHD, GC # ///DLD
CHANGE STATUS TO (RDY)  4/29/2008 DONE
Routing - PLAN CHECK4/21/2008 4/28/2008 PASS
DetailsCarl Westfall
Drawings approved after resubmittal review.
Routing - PUBLIC WORKS4/28/2008 4/28/2008 DONE
Added another drinking fountain.
Routing - PLANNING Land Div4/28/2008 4/28/2008 PASS
DetailsDave Abo
Approved per Section 27.2 (Right to Combine Units) of the Steelwood Condominiums Declaration and Covenants, Conditions, Restrictions and Reservations.
Plan resubmittals received  4/23/2008  
DetailsCarl Westfall
Received 1 cover transmittal, 2 copies of sheets A1.0, A1.1, A2.0, A2.1, A3.0 and taken to Carl Westfall///4-23-08 @ 9:25am BAS
1st review completed  4/21/2008 FAIL
Failed Planning, Plan Check
Routing - PLAN CHECK3/25/2008 4/21/2008 FAIL
DetailsCarl Westfall
The IBC plan review was started on April 15, 2008 and was finished on April 21, 2008. Revised drawings were required. See the plan review report.
Routing - FIRE4/21/2008 4/21/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
Routing PW Sewer Rating3/25/2008 3/25/2008 PASS
DetailsLouise Waldorf
Routing - PLANNING3/25/2008 3/25/2008 PASS
DetailsSarah Schafer
Sarah Schafer. Expansion by adding a 3,716 sq.ft. 2nd floor over 3 units in Building #5.

the area has the extra parking to take on the additional square footage.
Routing - PUBLIC WORKS3/24/2008 3/25/2008 PASS
DetailsBeverly Hall
Routing - PLANNING Land Div3/24/2008 3/24/2008 FAIL
DetailsDave Abo
Prior to issuance of building permit, a revised condominum plat shall be submitted to PDS Subdivision. The amended condominium plat and amended declarations shall be recorded prior to issuance of Certificate of Occupancy.
Pending Assignment by MYS3/21/2008 3/24/2008 DONE
DetailsMarlene Southard
3/24/2008 15:06:57 MYS - activity updated through activity BLDA172 from case BLD08-00512.
Plans ACCEPTED BY PLAN TECH  3/21/2008  
Recd Pcfee & Taken To Pln CK  3/21/2008 DONE
Application received  3/20/2008