Third Notice BLD | 1/29/2009 | 1/29/2009 | 2/5/2009 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 1/2/2009 | 1/2/2009 | 1/29/2009 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 11/5/2008 | 1/2/2009 | | DONE |
|
|
|
|
BLD-Final | 11/4/2008 | 11/5/2008 | 11/5/2008 | A | PASS |
Jim Sly
|
|
|
ELE is final now OK for Perm Occ.
|
Permanent Occupancy | | | 11/5/2008 | | DONE |
|
|
|
|
BLD-Final | 10/10/2008 | 10/13/2008 | 10/13/2008 | A | PART |
Jim Sly
|
|
|
joe Phone #: ###-#### OK for Temp Occ........OK to Perm when Electrical perms. (electr on Temp)
|
Temporary Occupancy | 10/13/2008 | 1/11/2009 | 10/13/2008 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 10/1/2008 | 10/1/2008 | 10/1/2008 | P | FAIL |
Jim Sly
|
|
|
Joe Would like this to be a temp final Phone #: ###-#### Need handrails at both sides......(2) stairways.
|
BLD-Final | 8/29/2008 | 8/29/2008 | 8/29/2008 | P | FAIL |
Jim Sly
|
|
|
dave Phone #: ###-#### C/N posted...... Note......Plumbing on Temp....
|
FIRE-Final Inspection | 8/28/2008 | 8/29/2008 | 8/29/2008 | A | PASS |
Troy Cobbley
|
|
|
fire life safety passed
|
FIRE-Final Inspection | 8/28/2008 | 8/28/2008 | 8/28/2008 | P | FAIL |
Troy Cobbley
|
|
|
The duct smoke detectors have not been installed correctly. Per the plans and HVAC schedules they are not required. I gave the contractor the option to either install and test or to remove the duct smoke detectors. All other items are ok.
|
BLD-Other | 8/19/2008 | 8/19/2008 | 8/19/2008 | P | PASS |
Jim Sly
|
|
|
david Note: ceiling grid Phone #: ###-####
|
BLD-Other | 8/15/2008 | 8/15/2008 | 8/15/2008 | P | NR |
Mike Jordan
|
|
|
Dave- ceiling grid Phone #: ###-####. Needs mech ri insp. first.
|
(F) Reprint permit | | | 8/14/2008 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 7/15/2008 | 7/16/2008 | 7/16/2008 | A | PART |
Mike Jordan
|
|
|
dave Phone #: ###-####. 1hr ceiling enclosure on rated stairway.
|
BLD-Conference | 6/30/2008 | 7/1/2008 | 7/1/2008 | A | PASS |
Jim Sly
|
|
|
/Mark ###-#### 1hr wall /ceiling ok
|
BLD-Framing/Rough-in | 6/30/2008 | 6/30/2008 | 6/30/2008 | P | CANC |
Jim Sly
|
|
|
Mark Phone #: ###-####
|
FIRE-Final Inspection | 6/27/2008 | 6/27/2008 | 6/27/2008 | P | PART |
Forrest France
|
|
|
See city approved plans for area marked in red for tempory occupancy. As per Mark Senteno.Door hardware, exit signs, egress lights and fire extinguishers are approved.One hour rated fire wall shall be completed and approved by Jim Sly before area occupancy. KR
|
FIRE-Final Inspection | 6/25/2008 | 6/26/2008 | 6/26/2008 | A | PEND |
Forrest France
|
|
|
This permit was to be a fire conf. Not a final. Contractor wanted a tempory occupancy. Refered him to Dave Hannamen.KR
|
BLD-Framing/Rough-in | 6/25/2008 | 6/26/2008 | 6/26/2008 | A | PASS |
Jim Sly
|
|
|
Mark Phone #: ###-#### OK to cover 1hr walls and 1hr ceilings.
|
BLD-Framing/Rough-in | 6/19/2008 | 6/20/2008 | 6/20/2008 | A | DONE |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/19/2008 at 12:11:17 PM. Contact: ###-####. Conference with Mark.
|
BLD-Footing | 5/29/2008 | 5/30/2008 | 5/30/2008 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/29/2008 at 4:21:18 PM. Contact: ###-####.wip.
|
Issue PAID IN FULL permit | | | 5/28/2008 | | DONE |
|
|
|
|
Telephone call | | | 5/6/2008 | | DONE |
Tisha Gallop
|
|
|
Spoke with Mark Vangulick w/Vertical Construction. Told him permit fees and need ACHD
|
Plan assigned to (CJW) | 3/24/2008 | | 4/29/2008 | | PASS |
Carl Westfall
|
|
|
4/29/2008 07:14:49 CJW - activity updated through activity BLDA022 from case BLD08-00512.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/29/2008 | | |
|
|
|
|
Telephone call | | | 4/29/2008 | | DONE |
|
|
|
Called Elizabeth Cooper permit ready and fee given . Also need ACHD, GC # ///DLD
|
CHANGE STATUS TO (RDY) | | | 4/29/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 4/21/2008 | | 4/28/2008 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
Routing - PUBLIC WORKS | 4/28/2008 | | 4/28/2008 | | DONE |
|
|
|
Added another drinking fountain.
|
Routing - PLANNING Land Div | 4/28/2008 | | 4/28/2008 | | PASS |
Dave Abo
|
|
|
Approved per Section 27.2 (Right to Combine Units) of the Steelwood Condominiums Declaration and Covenants, Conditions, Restrictions and Reservations.
|
Plan resubmittals received | | | 4/23/2008 | | |
Carl Westfall
|
|
|
Received 1 cover transmittal, 2 copies of sheets A1.0, A1.1, A2.0, A2.1, A3.0 and taken to Carl Westfall///4-23-08 @ 9:25am BAS
|
1st review completed | | | 4/21/2008 | | FAIL |
|
|
|
Failed Planning, Plan Check
|
Routing - PLAN CHECK | 3/25/2008 | | 4/21/2008 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on April 15, 2008 and was finished on April 21, 2008. Revised drawings were required. See the plan review report.
|
Routing - FIRE | 4/21/2008 | | 4/21/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing PW Sewer Rating | 3/25/2008 | | 3/25/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PLANNING | 3/25/2008 | | 3/25/2008 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer. Expansion by adding a 3,716 sq.ft. 2nd floor over 3 units in Building #5.
the area has the extra parking to take on the additional square footage.
|
Routing - PUBLIC WORKS | 3/24/2008 | | 3/25/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing - PLANNING Land Div | 3/24/2008 | | 3/24/2008 | | FAIL |
Dave Abo
|
|
|
Prior to issuance of building permit, a revised condominum plat shall be submitted to PDS Subdivision. The amended condominium plat and amended declarations shall be recorded prior to issuance of Certificate of Occupancy.
|
Pending Assignment by MYS | 3/21/2008 | | 3/24/2008 | | DONE |
Marlene Southard
|
|
|
3/24/2008 15:06:57 MYS - activity updated through activity BLDA172 from case BLD08-00512.
|
Plans ACCEPTED BY PLAN TECH | | | 3/21/2008 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/21/2008 | | DONE |
|
|
|
|
Application received | | | 3/20/2008 | | |
|
|
|
|