Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD08-00560
StatusFinaled
Name CORY LANE LLC
Site Address 9327 W CORY LN
Project NameAARONBROOKE PLACE
Customer Number 
ePlanReviewNo
Description
To construct a 228 sq.ft. covered entry on north side and a 988 sq.ft. lounge/living area addition and 272 sq. ft. covered patio on the south side of a 25,295 sq.ft. existing assisted living facility for a new total area of 26,783 sq. ft.; to change & install new self- closing, 20 minute & 60 minute / "S" labeled door/frame assemblies, part of original BLD96-01393, with a new door finish pattern; install a new Type I grease hood / exhaust / protected duct assembly and a new Type II hood / exhaust in the kitchen; install two new furnace units and all new PTAC through the wall units & controls; change out / add water heater units; modify plumbing in kitchen; maintain / repair the existing 1-hour occupancy separation, installed under UBC, between the 4 sleeping unit wings and the core activity/dining/lounge/reception/support areas; add new and change out some existing lighting fixture's; protect all penetrations and openings of the existing and new 1-hour roof/ceilng assemblies; install new door hardware/smoke gasketing; upgrade audible/visual alarm system; new class A roof covering on existing roof and new overbuild areas; provide accessible portion of reception counter and new interior finishes per approved plans on file and CUP08-00001. This building is fully sprinkled for allowable area increase and occupancy use groups. A new Certificate of Occupancy is required due to new addition. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD1/2/20091/2/20091/2/2009 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 12/16/20081/2/2009 DONE
BLD-Final12/15/200812/16/200812/16/2008PPASS
DetailsJim Sly
GARY Phone #: ###-####
OK for Perm Occ
Permanent Occupancy UNPAID FEE  12/16/2008 DONE
DetailsBarbara Stitt
BLD-Final12/12/200812/12/200812/12/2008PPART
DetailsJim Sly
gary Phone #: ###-####
OK for Temp Occ. OK for Perm when Plumb Perms.
BLD-Final12/10/200812/11/200812/11/2008ANR
DetailsJim Sly
gary Phone #: ###-####
Need to install Firestop prot. @ 1hr ceiling for can lights.
Meeting  12/11/2008 DONE
Met with structural inspector Jim Sly to review use of a proposed use of a fire rated cover to be installed over can lights in 1-hour ceiling at this job site. Porduct is made by TENMAT INC. and is tested and listed for use provide Luminaires and Luminaire Assemblies classified for fire resistance. UL CDHW.R25010, Type FF109, TENMAT Inc. Also tested for upto 1-hour by Omega Point Lab, Design Number LC 101, Luminary Covers. I stamped, signed and dated U.L. & Omega Point LC 101 & manufactures installation instruction as approved for use with this project. One copy to job site with Jim Sly and I attached one copy to approved office copy of plans.
BLD-Final12/8/200812/9/200812/9/2008ACANC
DetailsJim Sly
gary Phone #: ###-####
BLD-Final12/5/200812/5/200812/5/2008PNR
DetailsJim Sly
gary Phone #: ###-####
Need Ele final
FIRE-Final Inspection12/4/200812/4/200812/4/2008PPASS
DetailsTroy Cobbley
fire life safety passed
FIRE-Final Inspection11/26/200811/26/200811/26/2008PPART
DetailsTroy Cobbley
Per sam rogers a temporary is given until the exit discharge lighting as per the approved plans has been installed and tested.
BLD-Final11/24/200811/24/200811/24/2008PPEND
DetailsJim Sly
Temp occupancy in the new area only-Gary Phone #: ###-####
Need approal from Fire.......
BLD-Energy code compliance10/14/200810/14/200810/14/2008PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 10/14/2008 at 9:14:07 AM. Contact: ###-####.
BLD-Framing/Rough-in10/6/200810/7/200810/7/2008APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 10/6/2008 at 2:49:09 PM. Contact: ###-####.
Shear......OK to cover Exterior.
BLD-Foundation8/26/20088/27/20088/27/2008PPART
DetailsJim Sly
paul Phone #: ###-####
Front entry OK
BLD-Footing8/25/20088/26/20088/26/2008APART
DetailsJim Sly
paul Phone #: ###-####
Not finished forming
BLD-Foundation8/20/20088/21/20088/21/2008PPASS
DetailsJim Sly
paul - wall Phone #: ###-####
BLD-Footing8/19/20088/20/20088/20/2008APASS
DetailsJim Sly
paul Phone #: ###-####
Telephone call  8/4/2008 DONE
DetailsBarbara Stitt
Called Gary and told him that permit is ready & fees due///8/4/08 BAS
Permit Ready to Issue  8/4/2008 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  8/4/2008 DONE
Plan assigned to (DRS)4/10/20084/16/20088/1/2008 PASS
DetailsDan Stuart
8/1/2008 10:20:47 DRS - activity updated through activity BLDA022 from case BLD08-00560.
Routing - PLAN CHECK6/18/2008 8/1/2008 PASS
DetailsDan Stuart
Resubmittals of new structural design details by new structural engineering firm (Call Engineering) were inserted into reviewed plans. Modifications to plan review comments completed. Copy of third party contract structural engineering firm e-mailed copy of report concerning thier review of the 7/29/08 resubmittals. The structural review passed. Taking plans to permit desk to issue.
PLANS/APPL TAKEN TO FRONT DESK  8/1/2008 PASS
Print Occupancy Form  8/1/2008 DONE
Routing Off Site - STRUCTURAL7/29/2008 7/31/2008 PASS
DetailsDan Stuart
Called action courier for pick up 7-29-08 @ 9:50am BAS
7/31/08 - Received copy of e-mail from third party contracrt engineering firm passing review of structural details for this project.
Plan resubmittals requested  7/11/2008  
received "3"sheets each of each sheet 4, 10, & S2-- plans taken to Dan Stuart
Telephone call  7/11/2008 DONE
Call from contract structural engineering plan review concerning data he had received and concerns about the lack of structural calculations from the project engineer to demonstrate his methods of code compliance for infomation he has noted on he plans. Will attempt to address concerns with e-mail to architect, engineer and project manager for the proposed addition.
Routing Off Site - STRUCTURAL7/3/2008 7/7/2008 FAIL
DetailsDan Stuart
7/7/08 - Received copy of failed 3rd party structural re-review. Merlin Phillips submitted documents directly to Dave Haugland, AHJ, 3rd Party structural engineer based upon phone conversation between the two engineers. The data provided was still incomplete. A copy of the engineering review was e-mailed to Mike Fairchild, Merlin Phillips, Gary May and Jenifer Gilliland.
Telephone call  6/26/2008 DONE
Talked with Dave Haugland, AHJ, concerning structural plan re-review failure. Ask if the Merlin Phillips, project engineer could talk with him directly to help resolve the issues. Dave approved and I e-mailed his phone number to Mike Fairchild, Merlin Phillips and Gary May.
Routing Off Site - STRUCTURAL6/24/2008 6/26/2008 FAIL
DetailsDan Stuart
Called Action Courier for pick up on 6-24-08 @ 11:14am BAS
6/24/08 - Received copy of Merlin Phillips response to third party structural report. Copy of new plan sheets and engineers response sent out for 3rd party review.
6/26/08 - Copy of failed Structural re-review failed. Copy of corrections e-mailed to architect, engineer and Gary May, owners rep.
Routing - Erosion and Sediment6/25/2008 6/25/2008 PASS
DetailsClint A Smith
ESC plan approved with attached conditions. ESC08-00248
Plan resubmittals received  6/24/2008  
DetailsDan Stuart
Received 1 response letter dated 6-24-08 from Merlin Phillips, 3 copies of sheets 4, 8, 10, S1, S2 and taken to Dan Stuart's desk 6-24-08 @ 10:15am BAS
Route to Impact Fee Review6/23/20086/26/20086/23/2008 PASS
DetailsCindy M. Gould
Plan resubmittals requested  6/18/2008 DONE
Copy of plan review from 3rd party contract structural engineer with list of items still needing to be addressed by the Design Professional were faxed to architect and engineer with follow up e-mail requesting notification that report was received.
Routing Off Site - STRUCTURAL6/12/2008 6/17/2008 FAIL
DetailsBarbara Stitt
Called Action Courier for pick up on 6-12-08 @ 8:25am BAS
6/17/08 - Received second review report for submittals of 6/10/08. Resubmittals were not approved.
Routing - PLAN CHECK6/16/2008 6/17/2008 FAIL
DetailsDan Stuart
Copy of 3rd party structural engineering review received. Structural review failed for second time. Copy of report faxed to architect Mike Fairchild & engineer Merlin W. Phillips. E-mail to both requesting notification they had received the fax.
Routing - PLAN CHECK6/13/2008 6/16/2008 PEND
DetailsDan Stuart
Resubmittals from Mike Fairchild, architect, inserted into plans providing one new #4 Sheet and one new #10 sheet combining architects & engineers information on each sheet and providing an EN energy code sheet for the envelope, mechanical, water heating service and lighting changes for the addition remodel project. Waiting for approval of 3rd party structural re-review for the project.
Plan resubmittals received  6/13/2008  
DetailsDan Stuart
Received 3 copies of sheets 4,10,EN1, E4 and taken to Dan Stuart 6-13-08 @ 8:11am BAS
Plan resubmittals requested  6/12/2008 DONE
Architect did not respond to all items of original plan review. Energy code compliance certificate & checklist for envelope, HVAC, Hot Water Service and Lighting compliance were not provided. Also received two copies of Sheets 4 & 10 (1 from architect & 1 from engineering) with different incorrect data found on each sheet. To resubmit.
Telephone call  6/12/2008 DONE
Call from Mike Fairchild giving me his new e-mail address and we discussed briefly the missing or incorrect data.
Routing - PLAN CHECK4/24/2008 6/12/2008 FAIL
DetailsDan Stuart
Inserted new resubmittal sheets into original submittals. Resubmittals were incomplete - did not address energy code issues and two copies of Sheets 4 and 10 (1 from architect and 1 from engineer) with incorrect information indicated on both sheets.
Plan resubmittals received  6/10/2008  
DetailsDan Stuart
Received 3 copies of sheet 1, 2, 3, 4, 5, 6, 7, 8, 9, 10-from the architect and sheet 4, 10, E4-Engenieer Merlin Phillips, specs for McKinney Asa Abloy, letter from Keith Fletcher regarding Occupancy use classification, technical product specs for the dryerbox stamped and taken to Dan Stuart 6-10-08 @ 4:45pm BAS
Plan resubmittals requested  4/25/2008 DONE
Copy of 3rd party structural engineering report requiring resubmittals e-mailed to Mike Fairchild as the architect for this project.
Routing Off Site - STRUCTURAL4/10/2008 4/25/2008 FAIL
DetailsBethany Sullins
3rd set of plans finally received. Plans now routing off site for outside structural review.///Called Action Courier for pick up 4-10-08 @ 1:00pm BAS
4/25/08 - Received cover letter and copy of structural plan review from 3rd party structural engineer. Resubmittals are required. Attached copy of engineering report to e-mail to Mike Fairchild, architect @architect@wizardwire.net.
Routing - FIRE4/22/20086/23/20084/24/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  4/24/2008 FAIL
Failed ESC, Plan Check
Plan resubmittals requested  4/22/2008 DONE
Copy of plan review requirements e-mailed to Mike Fairchild.
Routing - PLAN CHECK4/9/2008 4/22/2008 FAIL
DetailsDan Stuart
Corrections e-mailed to architect.Routing to fire code analyst.
Pending Assignment by JCM3/26/2008 4/16/2008 DONE
DetailsBethany Sullins
4/16/2008 06:14:45 DRS - activity updated through activity BLDA168 from case BLD08-00560.
Routing - PLANNING4/7/2008 4/9/2008 PASS
DetailsSusan Riggs
Susan Riggs CUP08-00001
Routing - PUBLIC WORKS4/4/2008 4/7/2008 PASS
DetailsBeverly Hall
Routing - Erosion and Sediment4/7/2008 4/7/2008 FAIL
DetailsSteven Webb
ESC plan waiver request denied. Informed applicant that a ESC plan is required. ESC08-00248
Routing - PLUMBING4/7/2008 4/7/2008 PASS
DetailsBill VanDegrift
per plans and 2003 upc
Routing - PLANNING Land Div4/4/2008 4/4/2008 PASS
DetailsJoan Johnson
combination lot
Routing PW Drainage4/4/2008 4/4/2008 PASS
DetailsBrian Murphy
LESS THAN 10% OF TOTAL IMPERVIOUS SURFACE
Routing PW Sewer Rating4/4/2008 4/4/2008 PASS
DetailsLouise Waldorf
Plan resubmittals received  4/3/2008  
Received 3rd set of plans, 3 copies structural cals, esc app and waiver letter///4-3-08
Plans ACCEPTED BY PLAN TECH  3/26/2008 PASS
DetailsBethany Sullins
Application received  3/25/2008  
Recd Pcfee & Taken To Pln CK  3/25/2008 DONE
Plan resubmittals received     
DetailsDan Stuart
Received 3 copies of structural calculations by Call engineering dated 7-28-08, 3 copies of sheets S1.0, S2.0, S2.1, S3.1, S3.2///7-29-08 BAS 1 set of everything routed to off site structural engineers and 2 sets to Dan Stuart's desk///7-29-08 @ 10:00am BAS