Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD08-00575
StatusFinaled
Name SPECIALTY CONTRACTING LLC
Site Address 5520 N EAGLE RD
Project NameGriffeth Building
Customer Number 
ePlanReviewNo
Description
Griffeth Office Building (Shell & Core Only) - To construct a new 3,255 square foot, one story, wood framed office shell and core building and related site improvements. The core area is 525 square feet and contains an entry lobby, two restrooms, a janitor closet and electrical room. This building is being proposed for three separate office tenant spaces. The mechanical equipment is located on a mechanical platform in the attic. This is shell and core permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD1/29/20091/29/20093/18/2009 DONE
DetailsPatricia Smith
Second Notice has not been responded to.
Second Notice BLD1/16/20091/16/20091/29/2009 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice12/29/200812/29/20081/16/2009 DONE
DetailsJim Sly
BLD-Final12/29/200812/29/200812/29/2008APASS
DetailsJim Sly
C/C issued previously
DOC - Permit Finaled12/29/200812/29/200812/29/2008PPASS
DetailsJim Sly
BLD-Final12/23/200812/23/200812/23/2008PPASS
DetailsJim Sly
Rod Phone ###-####
BLD-Final12/3/200812/3/200812/3/2008PPASS
DetailsJim Sly
val Phone #: ###-####
C/C issued
FIRE-Final Inspection12/2/200812/3/200812/2/2008APASS
DetailsTroy Cobbley
Life safety passed. The fire hydrant at the property entrance that is mounted too high will be followed up on by the fire dept. Mark Sentenno is aware of the problem.
FIRE-Final Inspection11/26/200811/26/200811/26/2008PFAIL
DetailsTroy Cobbley
See the correction notice listed on the first page of the city approved plans.
Zoning Approval11/25/200811/25/200811/25/2008 DONE
DetailsMatthew A Halitsky
BLD-Framing/Rough-in8/26/20088/26/20088/26/2008PPASS
DetailsJim Sly
val Phone #: ###-####
BLD-Framing/Rough-in7/30/20087/31/20087/31/2008APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 7/30/2008 at 8:18:33 AM. Contact: ###-####.
OK to start TI in selected area....
BLD-Other7/22/20087/22/20087/22/2008PPASS
DetailsJim Sly
van Note: shear Phone #: ###-####
Shear OK
BLD-Other7/17/20087/21/20087/21/2008AFAIL
DetailsJim Sly
val Note: shear Phone #: ###-####
Shear Fail.....Need to extend OSB shear all the way to 8x8 posts
BLD-Conference7/17/20087/21/20087/21/2008ADONE
DetailsJim Sly
val Note: earliest as possible please - call 1/2 hr prior to inspection Phone #: ###-####
FIRE-Final Inspection6/13/20086/13/20086/13/2008PCANC
DetailsTroy Cobbley
Wrong inspection type called in.
BLD-Foundation6/13/20086/13/20086/13/2008PPASS
DetailsJim Sly
Mark- founation wall Phone #: ###-####
BLD-Footing6/10/20086/11/20086/11/2008APASS
DetailsJim Sly
Mark Phone #: ###-####
Called Engineer....2500 PSI design.
(F) Reprint permit  6/5/2008  
Issue PAID IN FULL permit  6/4/2008 DONE
OVERRIDE  5/20/2008  
Telephone call  5/20/2008 DONE
t/c w wes edwards at ###-#### - permit ready and fees given - also need ACHD receipt
Permit Ready to Issue  5/20/2008 DONE
Routing - PLANNING5/19/2008 5/19/2008 PASS
DetailsMatthew A Halitsky
Routed to Plan Check.
Routing - PLAN CHECK5/19/2008 5/19/2008 PASS
DetailsJohn Menard
John Menard.
PLANS/APPL TAKEN TO FRONT DESK  5/19/2008 DONE
DetailsJohn Menard
Inspection Record Card- Bld  5/19/2008  
Plan assigned to (JCM)3/27/2008 5/19/2008 PASS
DetailsJohn Menard
5/19/2008 10:40:04 JCM - activity updated through activity BLDA022 from case BLD08-00575.
Routing - PLAN CHECK5/12/2008 5/13/2008 PASS
DetailsJohn Menard
Plan Reviewer's activity  5/13/2008 PASS
Reviewed and approved nonstructural revisions. JCM
Routing - FIRE5/8/20085/8/20085/12/2008 PASS
DetailsScott Arellano
See fire plan review notes.
Plan resubmittals received  5/12/2008  
Received response letter, copy of plat and two copies of sheets A1.1, A7.1, A9.1; inserted by arch. rep. and taken back to Ken Roule
1st review completed  5/12/2008 DONE
Route to Impact Fee Review5/8/20085/13/20085/8/2008 PASS
DetailsCindy M. Gould
No impact fees permit recieved prior to 5/1/08
Plan Reviewer's activity  5/8/2008 PASS
Reviewed and approved structural revisions. JCM
Plan resubmittals requested  5/8/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of plan review requesting revisions JCM
Routing - PLAN CHECK4/7/2008 5/8/2008 FAIL
DetailsJohn Menard
John Menard
Plan resubmittals received  4/21/2008 DONE
received 1 letter, 1 response letter,2 structural calcs,and 2 copies of sheets S0.0,S1.0,S2.0,S3.0,S4.0,S4.1, inserted by David Millett from Ruby Edwards Arch plans taken back to John M ///dld
Plan resubmittals requested  4/15/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural review requesting revisions. JCM
Routing Off Site - STRUCTURAL3/28/2008 4/15/2008 FAIL
DetailsJohn Menard
Called Action Courier for pick up 3-28-08 @ 8:45AM BAS - Received comment list from consulting structural engineer requesting revisions. JCM
Routing - PLUMBING4/4/2008 4/7/2008 PASS
DetailsDaryl Spivey
Routing - PLANNING4/7/2008 4/7/2008 FAIL
DetailsMatthew A Halitsky
DRH08-00062 Matt Halitsky

Conditions of DRH08-62 not met.

Routed to Plan Check (John Menard).
Routing - PUBLIC WORKS3/28/2008 4/4/2008 PASS
DetailsBeverly Hall
Routing - Erosion and Sediment4/4/2008 4/4/2008 PASS
DetailsSteven Webb
ESC plan approved with attached conditions. ESC08-00215
Routing PW Sewer Rating4/3/2008 4/3/2008 PASS
DetailsLouise Waldorf
Routing PW Drainage4/2/2008 4/3/2008 PASS
DetailsBrian Murphy
approved under waring sub
Routing PW Solid Waste4/3/2008 4/3/2008 PASS
DetailsPeter J. McCullough
Approved for carts only. Carts to be taken to collection point agreed upon with Allied Waste. No dumster enclosures approved.
Routing PW Street Lights4/1/2008 4/2/2008 PASS
DetailsBill Colson
Routing PW Sewer Design3/28/2008 4/1/2008 PASS
DetailsJon R. Gunnerson
Routing - PLANNING Land Div3/27/2008 3/28/2008 PASS
DetailsTodd Tucker
Parcel is a platted lot.
Plans ACCEPTED BY PLAN TECH  3/27/2008 DONE
DetailsBethany Sullins
Recd Pcfee & Taken To Pln CK  3/27/2008 DONE
Plan routing begun/NEW & ADDTN  3/27/2008 DONE
Application received  3/27/2008  
Pending Assignment by MYS3/27/2008 3/27/2008 DONE
DetailsJohn Menard
3/27/2008 14:38:37 JCM - activity updated through activity BLDA166 from case BLD08-00575.
Routing - PLANNING5/13/2008