Permit Information
Permit NumberBLD08-00657
StatusExpired
Name GINGERICH SITE & UNDERGROUND
Site Address 2450 E SHAW MOUNTAIN RD
Project Name 
Customer Number 
ePlanReviewNo
Description
This project is for the placement/construction of a 50 lineal feet of retaining wall seven feet tall in the A-1 zoning district with a hillside overlay requiring hillside restrictions including: engineering for retaining wall, ESC plan. (erosion and sediment control plan) approved by Steve Webb. "A letter from the applicant's geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Per the letter attached. Call Terry Records at 384-3946." The A-1 zoning is approved through CFH08-00012 by David Moser. All per the approved plans; engineering Engineer's details and calculations, ESC approvals and Public Works attached drainage plans. pep
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection9/22/20109/22/20109/24/2010 FAIL
DetailsTony Young
DOC - Permit Expired9/22/20109/23/20109/23/2010APASS
DetailsTony Young
BLD-Aging Inspection7/20/20107/20/20107/28/2010 PEND
DetailsTony Young
BLD-Aging Inspection5/12/20105/12/20105/13/2010 PEND
DetailsTony Young
BLD-Aging Inspection2/24/20102/24/20103/4/2010 PEND
DetailsTony Young
FIRE-Final Inspection10/21/200810/22/200810/21/2008PCANC
DetailsTroy Cobbley
Wrong inspection type and number set up
BLD-Wall cover5/13/20085/13/20085/14/2008PPASS
DetailsDave Hannah
eric Phone #: ###-####
BLD-Footing5/9/20085/12/20085/12/2008APART
DetailsDave Hannah
eric Phone #: ###-####
BLD-Footing5/8/20085/9/20085/9/2008ANR
DetailsMike Jordan
eric Phone #: ###-####. Needs Geo-tech insp and letter. Also needs to resolve esc. issues.
PubWorks Subgrade Approval5/9/20085/9/20085/9/2008 DONE
DetailsTerry Records
Footing subgrade approved
Routing Walk-In (Zoning)4/25/20084/25/20084/29/2008PDONE
Details
4/29/2008 09:23:10 PEP - activity updated through activity BLDA022 from case BLD08-00657.
Plan assigned to (PEP)4/7/20084/7/20084/29/2008 PASS
DetailsPerry Paine
4/29/2008 09:23:10 PEP - activity updated through activity BLDA022 from case BLD08-00657.
Routing - PLANNING4/29/2008 4/29/2008 PASS
DetailsDavid Moser
CFH08-00012; Routed to Plan Check
Case Summary (BLD)  4/29/2008  
Case Summary (BLD)  4/29/2008  
Inspection Record Card- Bld  4/29/2008  
PLANS/APPL TAKEN TO FRONT DESK  4/29/2008 DONE
Inspector's copy Bld permit  4/29/2008 DONE
Inspection Record Card- Bld  4/29/2008 DONE
Issue PAID IN FULL permit  4/29/2008 DONE
Routing - PUBLIC WORKS GRADING4/25/2008 4/25/2008 PASS
DetailsTerry Records
Approved as Category 1 CFH08-00012
Routing - Erosion and Sediment4/4/2008 4/7/2008 PASS
DetailsSteven Webb
ESC plan waiver approved with attached conditions. ESC08-00251
PLANS/APPL TAKEN TO FRONT DESK  4/7/2008  
To DLD.
Application received  4/4/2008  
Routing - PLAN CHECK4/29/2008    
Perry P.
Routing - PUBLIC WORKS GRADING4/8/2008   FAIL
Must have Hillside development application approved first. Left message with applicant