Third Notice BLD | 1/29/2009 | 1/29/2009 | 4/3/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 1/2/2009 | 1/2/2009 | 1/29/2009 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 12/22/2008 | 1/2/2009 | | DONE |
|
|
|
|
BLD-Final | 12/22/2008 | 12/22/2008 | 12/22/2008 | P | PASS |
Jim Sly
|
|
|
ron Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy | | | 12/22/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
FIRE-Final Inspection | 11/26/2008 | 11/28/2008 | 11/28/2008 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 7/17/2008 | 7/17/2008 | 7/17/2008 | P | CANC |
Troy Cobbley
|
|
|
The tenant space was not ready for an inspection. Contractor is going to reschedule.
|
BLD-Framing/Rough-in | 6/19/2008 | 6/20/2008 | 6/20/2008 | A | PASS |
Jim Sly
|
|
|
Ron Phone #: ###-####
|
Telephone call | | | 5/23/2008 | | DONE |
|
|
|
t/c w elizabeth at ###-#### x 4 - permit ready and fees given - also need gc name and rce#
|
Permit Ready to Issue | | | 5/23/2008 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/23/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/22/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/22/2008 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/18/2008 | | 5/22/2008 | | PASS |
Carl Westfall
|
|
|
5/22/2008 10:01:29 CJW - activity updated through activity BLDA022 from case BLD08-00763.
|
Routing - PLAN CHECK | 5/13/2008 | | 5/21/2008 | | PASS |
Carl Westfall
|
|
|
Drawings approved after the resubmittal review.
|
Routing - PUBLIC WORKS | 5/21/2008 | | 5/21/2008 | | DONE |
|
|
|
Added another drinking fountain. Reviewed by Connie.
|
Route to Impact Fee Review | 5/13/2008 | 5/16/2008 | 5/15/2008 | | PASS |
Cindy M. Gould
|
|
|
Tennet improvement no fees permit before 5/1
|
Plan resubmittals received | | | 5/15/2008 | | |
Carl Westfall
|
|
|
Received 1 cover-response letter dated 5-14-08 from Elizabeth Cooper, 2 copies of sheets A1.0, A2.0 and taken to Carl Westfalls desk 5-15-08 @ 10:45am BAS
|
Routing - FIRE | 5/9/2008 | 5/9/2008 | 5/13/2008 | | PASS |
Scott Arellano
|
|
|
See fire plan review notes.
|
1st review completed | | | 5/13/2008 | | FAIL |
|
|
|
Failed plan check
|
Routing - PLAN CHECK | 4/21/2008 | | 5/9/2008 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on May 9, 2008 and was finished the same day. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 4/18/2008 | | 4/21/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 4/21/2008 | | 4/21/2008 | | PASS |
Louise Waldorf
|
|
|
|
Pending Assignment by MYS | 4/16/2008 | | 4/18/2008 | | DONE |
Marlene Southard
|
|
|
4/18/2008 12:11:56 MYS - activity updated through activity BLDA172 from case BLD08-00763.
|
Plans ACCEPTED BY PLAN TECH | | | 4/16/2008 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/16/2008 | | DONE |
|
|
|
|
Application received | | | 4/16/2008 | | |
|
|
|
|