Third Notice BLD | 12/22/2008 | 12/22/2008 | 1/23/2009 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 9/22/2008 | 9/22/2008 | 12/22/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 8/26/2008 | 9/22/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 8/26/2008 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 8/18/2008 | 8/19/2008 | 8/19/2008 | A | PASS |
Jim Sly
|
|
|
don Phone #: ###-#### OK for perm occ.
|
BLD-Final | 8/13/2008 | 8/14/2008 | 8/14/2008 | A | NR |
Jim Sly
|
|
|
DON Phone #: ###-####
|
BLD-Final | 8/13/2008 | 8/13/2008 | 8/13/2008 | P | PART |
Jim Sly
|
|
|
chad - suite 104 Phone #: ###-#### OK for Temp Occ. OK to Perm when Plumb perms.
|
FIRE-Final Inspection | 8/8/2008 | 8/11/2008 | 8/11/2008 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety passed.
|
BLD-Framing/Rough-in | 6/13/2008 | 6/13/2008 | 6/13/2008 | P | PASS |
Jim Sly
|
|
|
Don Phone #: ###-####
|
BLD-Energy code compliance | 6/13/2008 | 6/13/2008 | 6/13/2008 | P | PASS |
Jim Sly
|
|
|
Don Phone #: ###-####
|
BLD-Framing/Rough-in | 6/11/2008 | 6/11/2008 | 6/11/2008 | P | PART |
Jim Sly
|
|
|
Chad Phone #: ###-#### C/N Draftstop....OK to insulate.
|
FIRE-Final Inspection | 6/10/2008 | 6/11/2008 | 6/11/2008 | A | FAIL |
Troy Cobbley
|
|
|
This project is not ready for a final inspection. I went over life safety items with Chad.
|
BLD-Conference | 6/4/2008 | 6/5/2008 | 6/4/2008 | A | CANC |
Jim Sly
|
|
|
Don Phone #: ###-####
|
Print Occupancy Form | | | 5/19/2008 | | DONE |
|
|
|
|
Telephone call | | | 5/19/2008 | | DONE |
|
|
|
t/c w chad crocker at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 5/19/2008 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/19/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/16/2008 | | 5/16/2008 | | PASS |
Dan Stuart
|
|
|
Resubmittals added to plans. Routing to permit desk to issue permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2008 | | PASS |
|
|
|
|
Plan assigned to (DRS) | 4/24/2008 | | 5/16/2008 | | PASS |
Dan Stuart
|
|
|
5/16/2008 17:35:25 DRS - activity updated through activity BLDA022 from case BLD08-00840.
|
Routing - FIRE | 5/13/2008 | | 5/16/2008 | | PASS |
Kenneth R Roule
|
|
|
No review notes attached, Subject to field verification by PDS fire inspector. All items annotated on plans by Structural review shall be completed before final fire inspection.
|
1st review completed | | | 5/16/2008 | | FAIL |
|
|
|
Failed plan check
|
Plan resubmittals received | | | 5/15/2008 | | |
|
|
|
received response letter (2) sets & "3" pages each from architecture northwest. Also "3" sets of plans including each sheet of A-O.O, A-1.O, A-2.O, A-3.O, E-1.O--plans taken to Dan Stuart
|
Routing - PLAN CHECK | 4/25/2008 | | 5/13/2008 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Copy of plan review faxed to Randy Haverfield. Routing plans to fire code analyst.
|
Plan resubmittals requested | | | 5/13/2008 | | DONE |
|
|
|
Fax of plan review corrections required faxed to Randy Haverfield.
|
Plan resubmittals received | | | 5/9/2008 | | |
|
|
|
Received three copies of mechanical and lighting compliance on full size plan sheet; taken to Dan Stuart
|
Routing - PUBLIC WORKS | 4/24/2008 | | 4/25/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 4/25/2008 | | 4/25/2008 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 4/24/2008 | 4/24/2008 | | DONE |
Bethany Sullins
|
|
|
|
Pending Assignment by MYS | 4/24/2008 | | 4/24/2008 | | DONE |
Marlene Southard
|
|
|
4/24/2008 16:22:05 MYS - activity updated through activity BLDA168 from case BLD08-00840.
|
Plans ACCEPTED BY PLAN TECH | | | 4/24/2008 | | |
Marlene Southard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/24/2008 | | DONE |
Bethany Sullins
|
|
|
|