BLD-Final | 8/18/2009 | 8/19/2009 | 8/19/2009 | A | DONE |
Mike Jordan
|
|
|
Barbara-permits desk Phone #: ###-####
|
DOC - Permit Expired | 8/19/2009 | 8/19/2009 | 8/19/2009 | A | PASS |
Mike Jordan
|
|
|
Barbara-permits desk Phone #: ###-####Work has been completed and appears that public works has signed off. Permit is expired.
|
PubWorks Occupancy Approval | 1/21/2009 | 1/21/2009 | 1/21/2009 | | DONE |
|
|
|
Project final sign off by R. Anderson
|
BLD-Conference | 11/18/2008 | 11/18/2008 | 11/19/2008 | P | PASS |
Mike Jordan
|
|
|
wip.
|
BLD-Framing/Rough-in | 9/9/2008 | 9/10/2008 | 9/10/2008 | A | CANC |
Mike Jordan
|
|
|
andy Phone #: ###-####
|
BLD-Framing/Rough-in | 9/9/2008 | 9/9/2008 | 9/9/2008 | P | DEFR |
Jim Storey
|
|
|
andy Phone #: ###-#### out of time cloned to mike
|
Issue PAID IN FULL permit | | | 6/23/2008 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 6/19/2008 | | |
|
|
|
|
Telephone call | | | 6/12/2008 | | |
|
|
|
left mess for jeff ward at ###-#### that permit is ready & gave fees & need r/p
|
Routing - PUBLIC WORKS | 6/11/2008 | | 6/11/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Solid Waste | 6/11/2008 | | 6/11/2008 | | PASS |
Peter J. McCullough
|
|
|
|
Inspection Record Card- Bld | | | 6/11/2008 | | |
Marsha Smylie
|
|
|
|
Routing - PLAN CHECK | 6/9/2008 | | 6/11/2008 | | PASS |
Marsha Smylie
|
|
|
verified each set had the proper paperwork --took office copy to records & issue copy in the drawer.
|
Routing - FIRE | 6/4/2008 | | 6/9/2008 | | PASS |
Kenneth R Roule
|
|
|
Attached updated IFC comments to plans
|
Plan resubmittals received | | | 6/4/2008 | | |
|
|
|
received (2) sheets of A1.3 site plans & letter of response from cshqa (2) pages & united water flow sheet & cross access easement--- inserter is Jim Marsh
|
1st review completed | | | 5/16/2008 | | FAIL |
|
|
|
Failed PW/ PW Solid Waste and Fire.
|
Routing - FIRE | 5/14/2008 | | 5/16/2008 | | FAIL |
Kenneth R Roule
|
|
|
Faxed copy of reveiw to architect.
|
Route to Impact Fee Review | 5/14/2008 | 5/19/2008 | 5/15/2008 | | PASS |
Cindy M. Gould
|
|
|
site improvements only no fees
|
Routing - PLANNING | 5/13/2008 | | 5/14/2008 | | PASS |
Sue Hansen
|
|
|
|
Routing - PLUMBING | 5/13/2008 | | 5/13/2008 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Routing - Erosion and Sediment | 5/12/2008 | | 5/13/2008 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. Need certified RP. ESC08-00367
|
Routing - PUBLIC WORKS | 5/2/2008 | | 5/12/2008 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 5/5/2008 | | 5/12/2008 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 5/12/2008 | | 5/12/2008 | | PASS |
Bill Colson
|
|
|
|
Routing PW Sewer Rating | 5/12/2008 | | 5/12/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing PW Solid Waste | 5/12/2008 | | 5/12/2008 | | FAIL |
Peter J. McCullough
|
|
|
Trash enclosure gate opening is require to be 12' wide. It is shown as 10' on the plans. Also, the depth of the enclosure needs to be increased to 12'. Contact Peter McCullough at ###-####.
|
Routing PW Environmental | 5/12/2008 | | 5/12/2008 | | PASS |
Walt Baumgartner
|
|
|
West Boise Sewer Dist. Two GI's indicated on grading plans for pad A & B. OK
|
Plans ACCEPTED BY PLAN TECH | | | 5/2/2008 | | |
Marsha Smylie
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/2/2008 | | |
Marsha Smylie
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 5/2/2008 | | |
Dave Abo
|
|
|
|
Routing - PLANNING Land Div | 5/2/2008 | | 5/2/2008 | | PASS |
Dave Abo
|
|
|
grading and drainage only
|
Pending Assignment by MYS | 4/30/2008 | | 5/1/2008 | | DONE |
Marsha Smylie
|
|
|
|
Application received | | 4/30/2008 | | | |
Marsha Smylie
|
|
|
|
Routing - PLAN CHECK | 5/16/2008 | | | | PEND |
Marsha Smylie
|
|
|
put plans in hold bin waiting for resubmittals from fire & public works
|