Permit Information
Permit NumberBLD08-00949
StatusFinaled
Name CHEVRON PIPE LINE CO
Site Address 201 N PHILLIPPI ST
Project NameCHEVRON PIPELINE
Customer Number 
ePlanReviewNo
Description
(CHEVRON PIPELINE - CANOPY OVER BIOFUELS OFFLOADING FACILITY) To construct a 42' x 82' x 22 ' high freestanding steel canopy with 3 open sides to provide weather protection over a biofuel offloading location per approved engineered plans and DRH08-00106. (SRZ)
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD12/22/200812/22/200812/24/2008 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD9/22/20089/22/200812/22/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice8/26/20088/26/20089/22/2008 DONE
DetailsJim Storey
BLD-Final8/26/20088/26/20088/26/2008PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/26/2008 at 9:57:34 AM. Contact: ###-####. l/c on site.
DOC - Permit Finaled8/26/20088/26/20088/26/2008PPASS
DetailsJim Storey
FIRE-Final Inspection8/26/20088/26/20088/26/2008PPASS
DetailsTroy Cobbley
All no smoking signs were posted. KR
BLD-Final8/25/20088/25/20088/25/2008PNR
DetailsMike Jordan
floyd Phone #: ###-#### - please call 1/2 hr prior to inspection. Needs to post no smoking signs as per fire insp. Structure is ok. reviewed special insp. reports. ok. Contractor to post signs and recall for finals.
FIRE-Final Inspection8/22/20088/25/20088/25/2008AFAIL
DetailsTroy Cobbley
Need to install no smoking signs at all entrances of facility. KR
Code Occupancy Approval8/22/20088/22/20088/22/2008PPASS
DetailsCarol Montgomery
Meets compliance with DRH08-0106 and CUP08-00049
BLD-Final8/21/20088/22/20088/22/2008ANR
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/21/2008 at 8:23:37 AM. Contact: ###-####. Contacted contractor and told him that he still needed code enforcement and life/safety finals.
BLD-Other7/28/20087/29/20087/29/2008APASS
DetailsTom Arcoraci
BLD-Framing/Rough-in7/28/20087/29/20087/29/2008ANR
DetailsTom Arcoraci
jessie Phone #: ###-####
BLD-Other7/28/20087/28/20087/28/2008ACANC
DetailsTom Arcoraci
BLD-Footing6/10/20086/10/20086/10/2008PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 6/10/2008 at 11:16:07 AM. Contact: ###-####.
Issue PAID IN FULL permit  6/3/2008 DONE
Telephone call  6/2/2008 DONE
t/c w joe thompson at ###-#### - permit ready and fees given
Permit Ready to Issue  6/2/2008 DONE
Inspection Record Card- Bld  5/30/2008 DONE
Routing - Erosion and Sediment5/28/2008 5/29/2008 PASS
DetailsSteven Webb
ESC plan waiver approved with attached conditions. ESC08-00396
Routing - PLAN CHECK5/29/2008 5/29/2008 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  5/29/2008 DONE
DetailsSam Zahorka
Plan assigned to (SRZ)5/6/2008 5/29/2008 PASS
DetailsSam Zahorka
5/29/2008 14:52:47 SRZ - activity updated through activity BLDA022 from case BLD08-00949.
Routing - FIRE5/14/20085/14/20085/27/2008 PASS
DetailsKenneth R Roule
*5/20/08 - Routed to Sam Rogers for review*
*5/22/08 - Requested meeting with Dave Hanneman to review the proposed Bio Fuel unloading operation.

*5/27/08 - Attached IFC comments to plans. BFD to determine extent of fire protection required.
1st review completed  5/27/2008 FAIL
Failed ESC
Route to Impact Fee Review5/14/20085/19/20085/19/2008 PASS
DetailsCindy M. Gould
no fee
Routing - PLAN CHECK5/9/2008 5/14/2008 PEND
DetailsSam Zahorka
others to pass. routed to fire
Routing - PLANNING5/9/2008 5/9/2008 PASS
DetailsSusan Riggs
Routing - Erosion and Sediment5/7/2008 5/8/2008 FAIL
DetailsSteven Webb
ESC Responsible Person listed on application is not certified by Boise City. ESC08-00396
Routing PW Drainage5/7/2008 5/7/2008 PASS
DetailsBrian Murphy
LESS THAN 10PERCENT NEW TOTAL SITE NO DRAINAGE PLAN REQUIRED PER KELLY KERHER
Routing PW Sewer Rating5/7/2008 5/7/2008 PASS
DetailsLouise Waldorf
Routing - PUBLIC WORKS5/6/2008 5/7/2008 PASS
DetailsBeverly Hall
Pending Assignment by MYS5/6/2008 5/6/2008 DONE
DetailsMarlene Southard
5/6/2008 19:21:29 MYS - activity updated through activity BLDA160 from case BLD08-00949.
Recd Pcfee & Taken To Pln CK  5/6/2008  
DetailsBethany Sullins
Customer came in with check from Chevron for too much money so I put that check in the safe and he is requesting a new check for the correct amount. I verbaly ok'd with Rita///5-6-08 BAS
Plans ACCEPTED BY PLAN TECH  5/6/2008  
DetailsBethany Sullins
Plans taken and started stamping-contacted Will Evans to notify that we need a 3rd S1.1 & S5.1 signed by the engineer the sheets turned in did not have signature and were dated prior to 3-10-08.
Application received 5/6/2008   
DetailsBethany Sullins
Routing Off Site - STRUCTURAL5/7/2008    
Called Action Courier for pick up 5-7-08 @ 8:23am BAS
Routing - PLANNING5/8/2008    
DetailsAndrea Tuning
Approved per DRH08-00106 and routed to Susan R. for CU approval. 5-8-08.
Routing - PLAN CHECK5/27/2008   PEND
DetailsSam Zahorka
See ESC Comments.