FIRE-Final Inspection | 6/8/2009 | 6/8/2009 | 6/8/2009 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 5/10/2009 | 5/11/2009 | 5/11/2009 | A | PASS |
Tom Arcoraci
|
|
|
The City plan review set of drawings are at the customer counter of Snake River Pool & Spa. Phone #: ###-#### Internet Inspection Request from: Mark Bowen
|
Zoning Approval | 5/7/2009 | 5/7/2009 | 5/7/2009 | | PASS |
Andrea Tuning
|
|
|
|
BLD-Aging Inspection | 4/6/2009 | 4/6/2009 | 4/6/2009 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 2/3/2009 | 2/3/2009 | 2/3/2009 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 12/4/2008 | 12/4/2008 | 12/4/2008 | | NR |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 9/4/2008 | 9/5/2008 | 9/5/2008 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 9/3/2008 | 9/4/2008 | 9/4/2008 | P | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for deficiencies marked in red which include inactive exit sign at the east exit, additional emergency light/exit sign in the new show room and the removal of locks on the new show room double doors into the existing show room area.
|
BLD-Framing/Rough-in | 8/5/2008 | 8/5/2008 | 8/5/2008 | P | PASS |
Dave Hannah
|
|
|
All framing is complete. Phone #: ###-#### Internet Inspection Request from: Mark Bowen
|
BLD-Framing/Rough-in | 7/10/2008 | 7/10/2008 | 7/10/2008 | P | PART |
Tom Arcoraci
|
|
|
Partial framing in conjunction with BLD08-001003 Phone #: ###-#### Internet Inspection Request from: Mark Bowen
|
Issue PAID IN FULL permit | | | 6/2/2008 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/29/2008 | | DONE |
|
|
|
|
Telephone call | | | 5/29/2008 | | DONE |
|
|
|
left vm for mark bowen at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 5/29/2008 | | DONE |
|
|
|
|
1st review completed | | | 5/28/2008 | | PASS |
|
|
|
|
Plan assigned to (TLW) | 5/13/2008 | | 5/28/2008 | | DONE |
Tim L. Woodard
|
|
|
Plans approved per approved plans and plan review report.
|
Routing - FIRE | | | 5/28/2008 | | PASS |
Tim L. Woodard
|
|
|
Field Verify all 2006 IFC requirements. All modifications to the sprinkler system are required to have plans submitted and approved.
|
Routing PW Sewer Rating | 5/28/2008 | | 5/28/2008 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 5/28/2008 | | 5/28/2008 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLAN CHECK | 5/28/2008 | | 5/28/2008 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/28/2008 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 5/12/2008 | | 5/14/2008 | | DONE |
Ron Hill
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/12/2008 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/9/2008 | | |
|
|
|
|
Application received | | 5/9/2008 | | | |
|
|
|
|