Third Notice BLD | 12/22/2008 | 12/22/2008 | 1/15/2009 | | DONE |
Cathy Brown
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 11/7/2008 | 11/7/2008 | 12/22/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 10/17/2008 | 11/7/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/17/2008 | | DONE |
|
|
|
|
BLD-Final | 10/15/2008 | 10/16/2008 | 10/16/2008 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/15/2008 at 12:30:57 PM. ok for perm occ.
|
FIRE-Final Inspection | 10/15/2008 | 10/16/2008 | 10/16/2008 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 10/13/2008 | 10/14/2008 | 10/14/2008 | A | FAIL |
Troy Cobbley
|
|
|
Remove the nonrequired exit sign, install door hardware so it can be verified and install and tag fire extinguishers as discussed.
|
BLD-Other | 9/4/2008 | 9/5/2008 | 9/5/2008 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/4/2008 at 8:06:20 AM. Contact: ###-####. grid for hardlid, center portion. ok
|
BLD-Other | 8/28/2008 | 8/29/2008 | 8/29/2008 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/28/2008 at 8:20:09 AM. Contact: ###-####. framing for hardlids on eas and west ends of store. Center section not ready . Pending elc. and mech. ri insp.
|
BLD-Framing/Rough-in | 8/20/2008 | 8/21/2008 | 8/21/2008 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/20/2008 at 11:30:18 AM. Framing for hardlids and backing in restrooms for ada. Also combustibles were removed and replaced. ok.
|
BLD-Framing/Rough-in | 8/14/2008 | 8/15/2008 | 8/18/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/14/2008 at 8:35:11 AM. Contact: ###-####. Interior framed walls only. no grid or hardlids. Needs to in stall backing for ada restrooms, remove combustible backing.
|
Issue PAID IN FULL permit | | | 7/17/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/17/2008 | | 6/25/2008 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/25/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/25/2008 | | DONE |
|
|
|
|
Telephone call | | | 6/25/2008 | | DONE |
|
|
|
t/c w jeff smith at ###-#### - permit ready and fees given - also need gc name and rce#
|
Permit Ready to Issue | | | 6/25/2008 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 5/21/2008 | | 6/25/2008 | | PASS |
Tim L. Woodard
|
|
|
6/25/2008 10:42:21 TLW - activity updated through activity BLDA022 from case BLD08-01055.
|
Plan resubmittals received | | | 6/20/2008 | | |
Tim L. Woodard
|
|
|
received letter of transmittal sheet & letter from cortland morgan architects & "3" sets of plans with each sheet A1.O.O, A1.1.O, A1.3.O, A1.4.O, A4.7.O, & F2.O.1--took plans to Tim Woodard
|
Routing - PLAN CHECK | 5/30/2008 | | 6/17/2008 | | FAIL |
Tim L. Woodard
|
|
|
Refer to plan review report for corrections.
|
Routing - FIRE | 6/17/2008 | | 6/17/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 6/17/2008 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PUBLIC WORKS | 5/21/2008 | | 5/29/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Street Lights | 5/23/2008 | | 5/23/2008 | | PASS |
Bill Colson
|
|
|
|
Pending Assignment by MYS | 5/21/2008 | | 5/21/2008 | | DONE |
Marlene Southard
|
|
|
5/21/2008 14:26:48 MYS - activity updated through activity BLDA185 from case BLD08-01055.
|
Plans ACCEPTED BY PLAN TECH | | | 5/21/2008 | | |
Tisha Gallop
|
|
|
received revised cover sheet with code analysis
|
Recd Pcfee & Taken To Pln CK | | | 5/21/2008 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 5/16/2008 | | | |
Tisha Gallop
|
|
|
need revised code analysis prior to routing plans for review
|