First Notice | 3/16/2010 | 3/16/2010 | 4/12/2010 | | DONE |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 3/15/2010 | 3/15/2010 | 3/16/2010 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 3/16/2010 | 3/16/2010 | 3/16/2010 | A | PASS |
Dave Hannah
|
|
|
|
PubWorks Occupancy Approval | 1/8/2010 | 1/8/2010 | 1/8/2010 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Aging Inspection | 10/23/2008 | 10/23/2008 | 10/23/2008 | | PART |
Dave Hannah
|
|
|
exps on 01/11/09
|
Issue PAID IN FULL permit | | | 7/15/2008 | | DONE |
|
|
|
|
Routing PW Drainage | 7/10/2008 | | 7/11/2008 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 7/10/2008 | | 7/11/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing - PLAN CHECK | 7/11/2008 | | 7/11/2008 | | PASS |
Marsha Smylie
|
|
|
verified that everything was the same in each set of plans--took office copy to records
|
Permit Ready to Issue | | | 7/11/2008 | | |
|
|
|
|
Telephone call | | | 7/11/2008 | | |
|
|
|
called brook at ###-#### that permit is ready
|
Plan resubmittals received | | | 7/9/2008 | | |
Marsha Smylie
|
|
|
received material testing & inspection (2) pages, & e-mail from peter olsen--took plans to Brian Murphy
|
Routing - PUBLIC WORKS | 6/13/2008 | | 6/17/2008 | | FAIL |
Louise Waldorf
|
|
|
|
Routing PW Drainage | 6/13/2008 | | 6/17/2008 | | FAIL |
Brian Murphy
|
|
|
NEED WELL LOGS MENTIONED IN GEOTECH REPORT. BRIAN MURPHY ###-####
|
Routing - FIRE | 6/5/2008 | | 6/6/2008 | | PASS |
Scott Arellano
|
|
|
No fire review comments attached to plans.
|
1st review completed | | | 6/6/2008 | | FAIL |
|
|
|
Failed PW, ESC
|
Routing - Erosion and Sediment | 6/4/2008 | | 6/5/2008 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC08-00442
|
Routing - PLANNING | 6/2/2008 | | 6/4/2008 | | PASS |
Matthew A Halitsky
|
|
|
Routed to Plan Check (Marsha)
|
Plan resubmittals received | | | 6/3/2008 | | |
|
|
|
received an esc permit application & "2" sets of plans (54) pages- routed plans to Steve Webb
|
Routing - PLUMBING | 5/29/2008 | | 6/2/2008 | | PASS |
Bill VanDegrift
|
|
|
no plumbing
|
Plan resubmittals received | | | 5/30/2008 | | |
Barbara Stitt
|
|
|
Received 1 cover transmittal, 5 copies of revised O & M manual, 5 copies of sheetsC-001, C-002, C-003, CS-101, CS-501, CG-101, CG-501 inserted by Peter Olson and taken back to plumbing review box///5-30-08 @ 10:45am BAS
|
Routing - PUBLIC WORKS | 5/20/2008 | | 5/29/2008 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 5/29/2008 | | 5/29/2008 | | FAIL |
Steven Webb
|
|
|
Did not receive a plan waiver letter or a esc plan. Informed applicant.
|
Routing PW Solid Waste | 5/28/2008 | | 5/28/2008 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Street Lights | 5/28/2008 | | 5/28/2008 | | PASS |
Hank Alarcon
|
|
|
|
Routing PW Sewer Rating | 5/28/2008 | | 5/28/2008 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 5/20/2008 | | 5/27/2008 | | FAIL |
Brian Murphy
|
|
|
Need new crosssection BRIAN MURPHY ###-####
|
Routing - PLANNING Land Div | 5/19/2008 | | 5/20/2008 | | PASS |
Joan Johnson
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/16/2008 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/16/2008 | | |
|
|
|
|
Application received | | 5/16/2008 | | | |
|
|
|
|
Routing - PLAN CHECK | 6/6/2008 | | | | |
Marsha Smylie
|
|
|
|
Routing - PLAN CHECK | 6/19/2008 | | | | |
Marsha Smylie
|
|
|
pending with pubic works for resubmittals
|