Case Summary (BLD) | | | 3/11/2014 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/11/2014 | | DONE |
|
|
|
|
BLD-Final | 12/22/2008 | 12/22/2008 | 12/22/2008 | P | PASS |
Dave Hannah
|
|
|
john Phone #: ###-####
|
Letter of compliance | | | 12/22/2008 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 12/22/2008 | | DONE |
Darla L Downs
|
|
|
Letter of compliance issued
|
FIRE-Final Inspection | 12/19/2008 | 12/19/2008 | 12/19/2008 | P | PASS |
Forrest France
|
|
|
Fire life safety final inspection completed satisfactory.
|
BLD-Framing/Rough-in | 12/16/2008 | 12/17/2008 | 12/17/2008 | P | PART |
Dave Hannah
|
|
|
john - ceiling Phone #: ###-#### ok to cover ceiling in last section
|
BLD-Framing/Rough-in | 12/5/2008 | 12/5/2008 | 12/8/2008 | P | PART |
Dave Hannah
|
|
|
john Phone #: ###-#### ok to cover entry
|
FIRE-Final Inspection | 12/1/2008 | 12/1/2008 | 12/1/2008 | P | PART |
Forrest France
|
|
|
John Pnone#: ###-####
|
BLD-Framing/Rough-in | 11/25/2008 | 11/26/2008 | 11/26/2008 | A | PART |
Jim Sly
|
|
|
john Phone #: ###-#### Frame OK at Phase 3.......Wound and healing area.
|
BLD-Framing/Rough-in | 11/17/2008 | 11/18/2008 | 11/18/2008 | A | PART |
Dave Hannah
|
|
|
john Phone #: ###-#### ok to cover ceiling in entryway
|
FIRE-Final Inspection | 11/14/2008 | 11/17/2008 | 11/17/2008 | P | PART |
Forrest France
|
|
|
Fire life safety okayed for remodel areas completed to date.
|
BLD-Final | 11/14/2008 | 11/14/2008 | 11/14/2008 | P | CANC |
Dave Hannah
|
|
|
John this is for a temp only Phone #: ###-####ok to move into pn2
|
FIRE-Final Inspection | 11/13/2008 | 11/14/2008 | 11/14/2008 | A | NR |
Forrest France
|
|
|
Inspection for one portion of the remodel area work completed including the reception/waiting rooms, hall 118, cast rm., lymph. room, and some exam rooms. Need project related fire sprinkler work repairs, need to add an additional PFE for the east side as discussed, some missing door hardware.
|
BLD-Framing/Rough-in | 11/12/2008 | 11/12/2008 | 11/12/2008 | P | CANC |
Dave Hannah
|
|
|
john - ceiling Phone #: ###-#### pn 2 wound and healing section ok to cover ceiling
|
BLD-Framing/Rough-in | 10/29/2008 | 10/30/2008 | 10/31/2008 | P | PART |
Dave Hannah
|
|
|
john Phone #: ###-####
|
FIRE-Final Inspection | 10/22/2008 | 10/22/2008 | 10/23/2008 | P | PART |
Forrest France
|
|
|
Partial for work completed to date.
|
BLD-Framing/Rough-in | 10/15/2008 | 10/16/2008 | 10/16/2008 | A | PART |
Dave Hannah
|
|
|
kevin Phone #: ###-#### wound clinck ph 1 ok to cover walls
|
BLD-Final | 9/19/2008 | 9/22/2008 | 9/22/2008 | A | NR |
Dave Hannah
|
|
|
Kevin Phone #: ###-####
|
FIRE-Final Inspection | 9/19/2008 | 9/19/2008 | 9/19/2008 | P | FAIL |
Forrest France
|
|
|
Cannot perform a life safety until fire sprinkler resubmittals have been approved due to the use of sprinkler flex heads that were not shown on sprinkler plans. KR
|
BLD-Framing/Rough-in | 9/16/2008 | 9/17/2008 | 9/17/2008 | A | PART |
Dave Hannah
|
|
|
Kevin- ceiling Phone #: ###-#### ok to cover ceilings in section a part 1
|
BLD-Framing/Rough-in | 8/29/2008 | 8/29/2008 | 8/29/2008 | P | PART |
Dave Hannah
|
|
|
Kevin Phone #: ###-#### wrilpool room ok to cover
|
BLD-Framing/Rough-in | 8/15/2008 | 8/18/2008 | 8/18/2008 | A | PART |
Dave Hannah
|
|
|
Kevin Phone #: ###-#### ok to cover walls in section A or phase 1
|
BLD-Framing/Rough-in | 8/11/2008 | 8/11/2008 | 8/11/2008 | P | PART |
Dave Hannah
|
|
|
kevin Phone #: ###-#### talked to super about how to do phased projects
|
Issue PAID IN FULL permit | | | 7/18/2008 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 5/23/2008 | | 7/17/2008 | | PASS |
Dan Stuart
|
|
|
7/17/2008 08:34:55 DRS - activity updated through activity BLDA022 from case BLD08-01101.
|
Routing - PLAN CHECK | 6/24/2008 | | 7/17/2008 | | PASS |
Dan Stuart
|
|
|
Resubmittals inserted into plans. Plan review modified and plans-redlined. To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/17/2008 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/17/2008 | | DONE |
|
|
|
|
Telephone call | | | 7/17/2008 | | DONE |
|
|
|
t/c w bryan gilbreath at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/17/2008 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/16/2008 | | DONE |
|
|
|
received 1 letter of transmittal,1 review comments,3 ratings for fire rated doors ,and 3 copies of sheets G0.1,A0.1,A2.1,A4.1,A5.1,A7.1,M2.1,E2.1F,E2.1L,E2.1P,E2.15,E3.0 taken to Dan S.
|
Route to Impact Fee Review | 6/23/2008 | 6/26/2008 | 6/24/2008 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - FIRE | 6/23/2008 | 6/23/2008 | 6/24/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 6/24/2008 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 6/3/2008 | | 6/23/2008 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Copy of plan review e-mailed to Steve Turney, ZGA. Routing plans to fire code analyst.
|
Plan resubmittals requested | | | 6/23/2008 | | DONE |
|
|
|
E-mailed plan review to architect.
|
Routing - PLANNING | 6/2/2008 | | 6/3/2008 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLUMBING | 5/27/2008 | | 6/2/2008 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 5/23/2008 | | 5/27/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing - Erosion and Sediment | 5/27/2008 | | 5/27/2008 | | PASS |
Steven Webb
|
|
|
ESC plan waiver approved with attached conditions. ESC08-00455
|
Pending Assignment by MYS | 5/22/2008 | | 5/22/2008 | | DONE |
Tisha Gallop
|
|
|
5/22/2008 14:28:59 LEG - activity updated through activity BLDA175 from case BLD08-01111.
|
Plans ACCEPTED BY PLAN TECH | | | 5/22/2008 | | |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/22/2008 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 5/21/2008 | | | |
Tisha Gallop
|
|
|
|