(CAMP BOW WOW) To complete interior demolition work and remodel for the new tenant. All demolition work per demolition plan and to include: patch and repair existing walls, doors,and columns as required. Remove existing floor finishes, clean and repair for new. New work to include: construct new interior walls for office areas, lobby, utility, reception area, and prep. areas. Install kennels for indoor dog day care/boarding facility with chain link fencing and gates. Install kennels for outdoor dog day care/boarding facility with fencing and gates. New electrical work, mechanical work, doggy online cameras, ceiling work, new flooring, and install three new mechanical roof top units. Accessible bathrooms are existing and no structural work is proposed. A new cerificate of occupancy with the new occupant load total is to be issued when completed and approved. This building was originally constructed in Ada county and later annexed into Boise city. The existing envelope is not being affected by this permit. NOTE: this building is not fire sprinklered. All work per approved plans, plan review comments, engineering and CZC08-00092. *SRZ*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD12/22/200812/22/20082/5/2009 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD11/7/200811/7/200812/22/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 10/9/200811/7/2008 DONE
FIRE-Final Inspection10/9/200810/9/200810/9/2008PPASS
DetailsForrest France
Previous C/N items are finished, noted three exit signs at the east side above doors leading into outside pen enclosures to be removed per review comments and plan revision prior to structural final inspection as agreed.
BLD-Final10/8/200810/9/200810/9/2008PPASS
DetailsJim Storey
JOHN NOTE; CAMP BOW Phone #: ###-####final ok
Permanent Occupancy  10/9/2008 DONE
FIRE-Final Inspection10/3/200810/6/200810/6/2008AFAIL
DetailsTroy Cobbley
Need the project related fire alarm permit finaled. I did note that the keyed hardware out of the northwest corner of the business needs single action hardware installed. The exit signs and emergency lights tested ok. The fire extinguishers were being placed as I left and position as shown on the plans will need to be verified.
BLD-Final10/3/200810/6/200810/6/2008PCANC
DetailsJim Storey
John Phone #: ###-####
BLD-Other9/26/20089/29/20089/29/2008APASS
DetailsJim Storey
john Note: ceiling grid cat bowing Phone #: ###-####
BLD-Conference9/3/20089/3/20089/4/2008PPASS
DetailsJim Storey
john Phone #: ###-####
BLD-Framing/Rough-in8/27/20088/28/20088/28/2008APASS
DetailsJim Storey
john Phone #: ###-####
Issue PAID IN FULL permit  7/23/2008 DONE
DetailsTisha Gallop
Print Occupancy Form  7/22/2008 DONE
Details
Telephone call  7/22/2008 DONE
Details
left vm for robert clark at ###-#### - permit ready and fees given - also need gc name and rce#
Permit Ready to Issue  7/22/2008 DONE
Details
Routing - PLAN CHECK7/18/2008 7/21/2008 PEND
DetailsSam Zahorka
Pending others to pass.
Plan resubmittals received  7/21/2008 DONE
DetailsSteven Webb
Received name and certification number of ESC RP. Still need plan waiver request letter.
Routing - Erosion and Sediment7/21/2008 7/21/2008 PASS
DetailsSteven Webb
ESC plan waiver approved with attached conditions. ESC08-00530
Routing - PLAN CHECK7/21/2008 7/21/2008 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  7/21/2008 DONE
DetailsSam Zahorka
Plan assigned to (SRZ)6/18/2008 7/21/2008 PASS
DetailsSam Zahorka
7/21/2008 14:02:27 SRZ - activity updated through activity BLDA022 from case BLD08-01106.
Routing - FIRE7/15/2008 7/18/2008 PASS
DetailsScott Arellano
Attached updated IFC comments to plans
Routing - PLAN CHECK7/14/2008 7/15/2008 PEND
DetailsSam Zahorka
Pending others to pass.
Plan resubmittals received  7/15/2008  
DetailsSam Zahorka
Received 1 cover transmittal, 1 letter dated 7-11-08 from Robert Clark to Scott Arellano, 1 copy of Life Safety & Security Proposal, 3 copies of sheets A1.0 & E-3 and taken to Sam Zahorka's desk///7-15-08 @ 10:21am BAS
Routing - PLAN CHECK7/9/2008 7/14/2008 PEND
DetailsSam Zahorka
Pending others to Pass.
Routing - PLANNING7/14/2008 7/14/2008 PASS
DetailsAndrea Tuning
Plan resubmittals received  7/10/2008  
DetailsSam Zahorka
Received tranmittal, two copies of sheets M-4, E-5, three copies of sheets A1.0, A1.2, A1.3, A2.0; taken to Sam Z.
Routing - FIRE7/3/20087/3/20087/9/2008 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
1st review completed  7/9/2008 FAIL
Failed ESC, Planning, Plan Check, Fire
Route to Impact Fee Review7/3/20087/9/20087/3/2008 PASS
DetailsCindy M. Gould
Tenant improvement no fees
Case Summary (BLD)  7/3/2008 DONE
DetailsSam Zahorka
Routing - PLAN CHECK6/20/2008 7/3/2008 FAIL
DetailsSam Zahorka
Emailed Plan corrections to the Architect. Routed plans to Fire. (SRZ)
Routing - PLANNING6/20/2008 6/20/2008 FAIL
DetailsAndrea Tuning
The applicant has not submitted a site plan with the building plans. Prior to Planning approving the building plans, teh applicant will be required to show that the applicatn is complying with the conditions of CZC08-00092.
Routing - Erosion and Sediment6/19/2008 6/20/2008 FAIL
DetailsSteven Webb
ESC plan does not meet the requirements per BMC 8-17 or the plan designer class. Did not submit a narrative or plan waiver request. Plan submitted was not prepared by a Boise City certified as PD.
Routing - PUBLIC WORKS6/18/2008 6/19/2008 PASS
DetailsBeverly Hall
Routing - Addressing6/18/2008 6/18/2008 PASS
DetailsApril Wing
Pending Assignment by MYS6/13/2008 6/18/2008 DONE
DetailsMarlene Southard
6/18/2008 09:42:11 MYS - activity updated through activity BLDA160 from case BLD08-01106.
Plan resubmittals received  6/13/2008  
DetailsBarbara Stitt
Received 1 ESC application and 2 copies of sheet G1.0///6-13-08 BAS
Plans ACCEPTED BY PLAN TECH  6/13/2008 DONE
DetailsBarbara Stitt
Recd Pcfee & Taken To Pln CK  6/13/2008 DONE
DetailsBarbara Stitt
Plan resubmittals received  5/28/2008 DONE
DetailsBarbara Stitt
Received 1 cover transmital, 3 copies of revised indexes (8 1/2x11) 3 copies of sheets M-4 & E-5. Taken and attached with set of plans that are already here but pending zoning approval///5-28-08 @ 10:21am BAS
Plans ACCEPTED BY PLAN TECH  5/22/2008 FAIL
DetailsBethany Sullins
No zoning approval for this project and after talking with Lucinda -it was determined that he needs to talk to zoning before we can accept these plans--Lighting compliance not on correct size sheets-per my phone coversation with Steve Webb- he has spoken with the architects office and per thier discussion no ESC plans or app required. I did talk to Steve reqarding the Pea gravel, new fencing and redirecting new down spouts and he does say that no esc is required but will keep an eye on this project--Called and left voice message for robert Clark to contact Lucinda Grames regarding zoning approval for his project--permit voided until Zoning approved and new sheets with Lighting compliance recieved ///5-22-08 @ 11:00am BAS
VOIDED CHANGE STATUS  5/22/2008 DONE
DetailsBethany Sullins
No zoning approval for this project and after talking with Lucinda -it was determined that he needs to talk to zoning before we can accept these plans--Lighting compliance not on correct size sheets---Called and left voice message for robert Clark to contact Lucinda Grames regarding zoning approval for his project--permit voided until Zoning approved and new sheets with Lighting compliance recieved ///5-22-08 @ 11:00am BAS
Application received 5/22/2008