Case Summary (BLD) | | | 6/23/2011 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 8/4/2009 | | DONE |
|
|
|
|
BLD-Final | 7/31/2009 | 8/3/2009 | 8/3/2009 | P | PASS |
Dave Hannah
|
|
|
brad Phone #: ###-#### pass
|
FIRE-Final Inspection | 7/31/2009 | 8/3/2009 | 8/3/2009 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed. Note: no signature card available on site.
|
FIRE-Final Inspection | 7/21/2009 | 7/22/2009 | 7/22/2009 | A | NR |
Forrest France
|
|
|
Need project related fire alarm permit issued, requested for inspection and finaled prior to BLD final.
|
BLD-Final | 7/22/2009 | 7/22/2009 | 7/22/2009 | P | NR |
Dave Hannah
|
|
|
Brad Phone #: ###-#### needs fire final
|
BLD-Final | 7/16/2009 | 7/17/2009 | 7/18/2009 | P | NR |
Dave Hannah
|
|
|
Brad Phone #: ###-#### neeeds fire finals
|
BLD-Framing/Rough-in | 3/20/2009 | 3/20/2009 | 3/23/2009 | P | PASS |
Dave Hannah
|
|
|
Brad Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/8/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Telephone call | | | 12/8/2008 | | DONE |
|
|
|
t/c w john price at ###-#### - called and gave john the breakdown of fees for units 1###-#### - also emailed him a copy of the fee breakdown
|
Telephone call | | | 9/18/2008 | | DONE |
|
|
|
t/c w john price at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 9/18/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/17/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2008 | | DONE |
Carl Westfall
|
|
|
|
Routing - PLAN CHECK | 8/19/2008 | | 8/20/2008 | | DONE |
Carl Westfall
|
|
|
|
Plan assigned to (CJW) | 6/2/2008 | | 8/20/2008 | | PASS |
Carl Westfall
|
|
|
8/20/2008 10:46:31 CJW - activity updated through activity BLDA022 from case BLD08-01141.
|
Routing - FIRE | 8/15/2008 | 8/15/2008 | 8/19/2008 | | PASS |
Scott Arellano
|
|
|
|
1st review completed | | | 8/19/2008 | | PASS |
|
|
|
|
Route to Impact Fee Review | 8/15/2008 | 8/20/2008 | 8/18/2008 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 6/3/2008 | | 8/15/2008 | | PASS |
Carl Westfall
|
|
|
The IBC plan review was started on August 15, 2008 and was completed the same day. The drawings were approved.
|
Routing - PUBLIC WORKS | 6/2/2008 | | 6/3/2008 | | PASS |
Beverly Hall
|
|
|
|
Pending Assignment by MYS | 5/30/2008 | | 6/2/2008 | | DONE |
Marlene Southard
|
|
|
6/2/2008 15:56:37 MYS - activity updated through activity BLDA172 from case BLD08-01141.
|
Application received | | 5/27/2008 | 5/27/2008 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/27/2008 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/27/2008 | | DONE |
Tisha Gallop
|
|
|
|