Letter of compliance/Occupancy | | | 3/18/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 1/13/2009 | 1/13/2009 | 1/13/2009 | P | PASS |
Tony Young
|
|
|
peter - please call for access Phone #: ###-####
|
DOC - Permit Finaled | 1/13/2009 | 1/13/2009 | 1/13/2009 | P | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 10/28/2008 | 10/29/2008 | 10/29/2008 | A | PASS |
Tony Young
|
|
|
peter Phone #: ###-####
|
BLD-Framing/Rough-in | 10/24/2008 | 10/24/2008 | 10/24/2008 | P | PASS |
Mike Jordan
|
|
|
peter Phone #: ###-####
|
BLD-Framing/Rough-in | 10/22/2008 | 10/23/2008 | 10/23/2008 | A | FAIL |
Mike Jordan
|
|
|
peter Phone #: ###-####. Complete all lateral bracing, complete air seal package, strap top plate at plumbing vent penetration. c/n posted.
|
BLD-Framing/Rough-in | 10/22/2008 | 10/22/2008 | 10/22/2008 | P | NR |
Jim Storey
|
|
|
peter Phone #: ###-#### need plans and truss engineering.
|
Routing Walk-In (BLD) | 8/11/2008 | 8/11/2008 | 8/11/2008 | A | DONE |
Perry Paine
|
|
|
8/11/2008 09:17:34 PEP - activity updated through activity BLDA022 from case BLD08-01158.
|
Routing Walk-In (BLD) | 8/8/2008 | 8/8/2008 | 8/11/2008 | P | DONE |
Barbara Stitt
|
|
|
8/11/2008 08:24:04 B_S - activity updated through activity BLDI252 from case BLD08-01158.
|
Case Summary (BLD) | | | 8/11/2008 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/11/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 8/11/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/11/2008 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/11/2008 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 8/8/2008 | 8/8/2008 | 8/8/2008 | P | PASS |
Lucinda Grames
|
|
|
|
BLD-Conference | 7/14/2008 | 7/15/2008 | 7/15/2008 | A | PART |
Tony Young
|
|
|
peter - ###-#### need struct engineer to evaluate,, need to bring items affected up to code,, need all lifesafety up to current code,, as well as plumbing clearances as needed or reqd by plumbing official
|
Application received | | 5/27/2008 | | | |
|
|
|
|