Third Notice | | 4/30/2010 | 5/11/2010 | | DONE |
|
|
|
faxed and called
|
Third Notice | | 3/26/2010 | 4/15/2010 | | DONE |
|
|
|
started with third notice to match Bld08-01105 notices. ///faxed and called
|
Telephone call | | | 4/15/2010 | | DONE |
Tisha Gallop
|
|
|
called and spoke with Cathy/Beniton Const. she said almost done with all change orders, will check w/project manager on status.
|
BLD-Final | 11/23/2009 | 11/23/2009 | 11/23/2009 | P | PEND |
Tom Arcoraci
|
|
|
need to close out grading permit//Ryan ###-####
|
DOC - Permit Finaled | 11/23/2009 | 11/23/2009 | 11/23/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 10/2/2009 | 10/2/2009 | 10/2/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 10/2/2009 | 10/2/2009 | 10/2/2009 | | PASS |
Tom Arcoraci
|
|
|
|
Telephone call | | | 8/7/2009 | | DONE |
|
|
|
Talked with Ryan and he will need to bond for the remaining work (i.e. Complete landscaping around new school, demo of old school and landscape the playground area) in order to get a Temp Occup. sign off from Zoning. He will call back when ready for Temp Occ inspection.
|
Inspection Record Card- Bld | | | 8/5/2009 | | DONE |
|
|
|
|
BLD-Aging Inspection | 6/18/2009 | 6/18/2009 | 6/18/2009 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 4/14/2009 | 4/14/2009 | 4/14/2009 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 2/9/2009 | 2/9/2009 | 2/10/2009 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 12/10/2008 | 12/10/2008 | 12/10/2008 | P | PASS |
Tom Arcoraci
|
|
|
spec insp on concrete and masonary wip ok
|
BLD-Aging Inspection | 12/10/2008 | 12/10/2008 | 12/10/2008 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 10/10/2008 | 10/10/2008 | 10/10/2008 | | PASS |
Mike Jordan
|
|
|
wip on job site.
|
Issue PAID IN FULL permit | | | 7/2/2008 | | DONE |
|
|
|
|
OVERRIDE | | | 6/20/2008 | | |
|
|
|
|
Routing - PLUMBING | 6/20/2008 | | 6/20/2008 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Routing - PLAN CHECK | 6/19/2008 | | 6/20/2008 | | PEND |
Tisha Gallop
|
|
|
routed to plumbing
|
Routing - PLAN CHECK | 6/20/2008 | | 6/20/2008 | | PASS |
Tisha Gallop
|
|
|
passed all departments
|
Case Summary (BLD) | | | 6/20/2008 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 6/20/2008 | | DONE |
Tisha Gallop
|
|
|
called Greg Baer (The Land Group) and left voice message that permit is ready and fee//6/20/08 4:36pm LEG
|
Permit Ready to Issue | | | 6/20/2008 | | DONE |
Tisha Gallop
|
|
|
|
1st review completed | | | 6/19/2008 | | FAIL |
|
|
|
Failed Plumbing
|
Routing - FIRE | 6/17/2008 | | 6/19/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Plan resubmittals received | | | 6/18/2008 | | |
Barbara Stitt
|
|
|
Received 2 copies of C5.00 and taken and attached to plans in Fire///6-18-08 @ 11:47am BAS
|
Routing - Erosion and Sediment | 6/16/2008 | | 6/17/2008 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC08-00457
|
Routing - PLANNING | 6/17/2008 | | 6/17/2008 | | PASS |
David Moser
|
|
|
CUP08-00023 David Moser, Routed to Plan Check - Tisha G.
|
Routing - PLUMBING | 6/17/2008 | | 6/17/2008 | | FAIL |
Bill VanDegrift
|
|
|
need revised C5 showing 6" sewer.
|
Routing PW Drainage | 6/17/2008 | | 6/17/2008 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 6/12/2008 | | 6/16/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing - PLANNING Land Div | 6/11/2008 | | 6/12/2008 | | PASS |
Todd Tucker
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/11/2008 | | |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/11/2008 | | DONE |
Tisha Gallop
|
|
|
|
Zoning Approval | 8/18/2009 | 8/18/2009 | | | PASS |
|
|
|
The work is not completed yet and esc measures are still in place on site. As per Hal Simmons, they do not need bonding for project.
|
Application received | | 6/10/2008 | | | |
Tisha Gallop
|
|
|
|