First Notice | | 9/16/2014 | 11/3/2014 | | DONE |
|
|
|
old permit
|
Case Summary (BLD) | | | 3/11/2014 | | DONE |
|
|
|
|
Agreement of Future work | 4/23/2010 | 11/29/2013 | 3/6/2014 | | DONE |
Carl Westfall
|
|
|
This building has an upgrade agreeement on file. This permit covers Phase II of the atrium smoke control upgrade. Phase I is to be completed by October 31, 2009, Phase II is to be completed by December 31, 2010, and Phase III is to be completed by December 31, 2011. See the attached document for specifics. CJW
12/2/13 Received email notification from architect that the project is nearing completion.
7/16/13 New Upgrade Agreement attached to this case. Phase II to be completed by 11/29/13 and Phase III to be completed by 8/29/14. If Phase II is not completed by specified date, a bond shall be posted in the amount to cover both Phase II and Phase III.
4/29/10 New updated/signed Upgrade Agreement completed and attached to this case. New agreement has been recorded at Ada County. This Agreement replaces the previous approved agreement. New date to complete all work under the Agreement is June 30, 2013.
12/9/13 Project is progressing. Could be finished in the next 3-4 weeks. Contractor status indicates:
Generator / Trash enclosure has been modified with new CMU wall with D/W wall on top and lid to generator space drywalled. Gates still need to be modified will be completed over the next 3 weeks
Transfer switch is due to arrive the 18 or 19 of Dec. Generator is due to arrive on the 30th of Dec which will be installed right after they arrive
Structural Steel support structure is all installed on rooftop and ready for mechanical equipment and plenum. HVAC equipment to be on site around the 19th and I will get an exact date it will be placed on the roof.
About 80% electrical rough in conduit pathways and junction boxes for generator and door and window controls are complete. We still need to run the conduit pathways for the north and west door and wind controls back up to the rooftop pane which will be done this week.
Door openers, mag locks and electric strikes have been delivered and will be installed over the next 3 weeks
Window opening in North stairwell has been modified and is ready for Storefront operable windows that have been ordered. I need to verify ship date.
3/6/14 Work outlined in the Upgrade Agreement is complete. A copy of the recorded Notice of Compliance is attached to this case.
|
DOC - Permit Finaled | | | 3/4/2014 | | DONE |
Christina Prado
|
|
|
Per Dave Hannah 3-4-14
|
BLD-Final | 2/7/2014 | 2/10/2014 | 2/10/2014 | A | PASS |
Dave Hannah
|
|
|
Boyd Phone #: ###-####
|
Zoning Approval | 2/6/2014 | 2/6/2014 | 2/6/2014 | | DONE |
Matthew A Halitsky
|
|
|
Interior work.
|
FIRE-Final Inspection | 2/5/2014 | 2/5/2014 | 2/5/2014 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
BLD-Aging Inspection | 11/18/2013 | 11/18/2013 | 11/25/2013 | | PEND |
Dave Hannah
|
|
|
|
BLD-Footing | 11/20/2013 | 11/20/2013 | 11/21/2013 | P | PASS |
Dave Hannah
|
|
|
BOYD Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 9/9/2013 | | DONE |
Tisha Gallop
|
|
|
plan mod issued
|
Telephone call | | | 8/27/2013 | | DONE |
Christina Prado
|
|
|
called Jessica to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 8/27/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 8/8/2013 | 8/8/2013 | 8/23/2013 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLAN CHECK | 8/8/2013 | | 8/23/2013 | | PASS |
Carl Westfall
|
|
|
Approved the plan modification
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/23/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan Modification Accepted | | | 8/8/2013 | | DONE |
Tisha Gallop
|
|
|
Plan modification accepted for Bld08-01293 & Bld08-00378 (8th Street Marketplace) to organize the previously approved phased work in (2) phases, clearly identifying remaing work to be completed to install an updated Smoke Evacuation System in the Mercantile Bldg. Originally the (3) phased project was under two different permit numbers. The majority of work under Bld08-00378 has been completed, with the exception of the construction of the smoke exhaust plenum - sheet a5.12 from Bld08-00378 is now included in the Phase 2 (Bld08-01293) work and part of our Plan Modification request is for Bld08-01293. Per sheet a5.12 - there is NO change in the structura design, only including scope in the new Phase 2; submitted on plan sheets a0.01, a0.02, a3.12, a3.13, a5.12, and structural calcs; routed to Carl Westfall.
|
BLD-Aging Inspection | 3/5/2013 | 3/5/2013 | 3/13/2013 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 9/21/2012 | 9/21/2012 | 9/21/2012 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 5/25/2012 | 5/25/2012 | 5/29/2012 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 2/6/2012 | 2/6/2012 | 2/9/2012 | | PEND |
Dave Hannah
|
|
|
|
Change Expiration Date Only | | | 1/25/2012 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 1/25/2012 | | DONE |
Jason Blais
|
|
|
This permit valid until 6/30/13 based on specific Upgrade Agreement (attached to case). Phase II date extended out to Phase III date to complete project.
|
BLD-Aging Inspection | 8/12/2011 | 8/12/2011 | 8/12/2011 | | PEND |
Dave Hannah
|
|
|
|
Extend Review Timeline | | | 4/12/2011 | | DONE |
|
|
|
extended 180 days per jason
|
BLD-Conference | 4/4/2011 | 4/5/2011 | 4/6/2011 | P | DEFR |
Dave Hannah
|
|
|
Ken Beck from Guho Construction ###-#### (cell) would like to meet on site at 2:00 pm. Request for permit extension needs to be turned in to Jason Blais.
|
Extend Review Timeline | | | 10/15/2010 | | DONE |
|
|
|
extend 180 days per jason - new expiration date will be 4-13-11
|
Telephone call | | | 10/15/2010 | | DONE |
|
|
|
left message w kay for andrew erstad at ###-#### - his extension request has been granted - permit will expire on 4-13-11
|
FIRE-Final Inspection | 5/28/2010 | 6/1/2010 | 6/1/2010 | A | NR |
Forrest France
|
|
|
Intended by contractor for FIR08-00378- Phase II work per this permit scope is not complete.
|
Issue PAID IN FULL permit | | | 4/21/2010 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 2/3/2010 | | 2/5/2010 | | PASS |
Carl Westfall
|
|
|
Drawings approved for issuance.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2010 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/5/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/5/2010 | | DONE |
|
|
|
|
Telephone call | | | 2/5/2010 | | DONE |
|
|
|
called Andy Erstad left message permit ready and fee given 2-5-10 dld
|
Plan assigned to (CJW) | 6/18/2008 | | 2/5/2010 | | PASS |
Carl Westfall
|
|
|
2/5/2010 10:04:07 CJW - activity updated through activity BLDA022 from case BLD08-01293.
|
Routing - PUBLIC WORKS | | | 2/4/2010 | | DONE |
|
|
|
Discussed trash enclosure and size of gates with Peter McCullough. He was OK with the changes.
|
Routing - FIRE | 2/1/2010 | | 2/3/2010 | | PASS |
Scott Arellano
|
|
|
Attached updated IFC comments to plans
|
Routing - PLAN CHECK | 12/29/2009 | | 2/1/2010 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
Plan Reviewer's activity | | | 1/11/2010 | | FAIL |
|
|
|
Reviewed resubmitted documents. Could not accept it. Sent E-mail to Tegan explaining why.
|
Plan resubmittals received | | | 1/8/2010 | | |
Carl Westfall
|
|
|
rec'd 2 sets of engineer specs- taken to carl W
|
Routing - PLAN CHECK | 9/17/2009 | | 12/29/2009 | | FAIL |
Carl Westfall
|
|
|
Completed the resubmittal review. Still concerned about the 1-hr room for the generator. Sent Tegan an E-mail and left a voice mail message.
|
Plan resubmittals received | | | 12/24/2009 | | |
Carl Westfall
|
|
|
Rec'd response letter and two copies of sheets- a3.12; e1.10; e1.11; e2.10; e2.11; e2.13; e2.14; taken to Carl W
|
Routing - PLAN CHECK | 10/17/2008 | | 9/17/2009 | | FAIL |
Carl Westfall
|
|
|
Carl Westfall, Plans Examiner, did not become aware that resubmittals had been received until 9-14-09. The permits desk routed the plans to him on that date. Completed the resubmittal review on 9-17-09. One item still needs to be resolved. Sent E-mail to Tegan Bohannan, Architect's rep.
|
Telephone call | | | 9/14/2009 | | DONE |
|
|
|
Called and talked to Andy Erstad. Ask for a letter explaining the status of the requested resubmittal. Phase II is required to be done by Dec. 31, 2010 per the upgrade agreement. Don't really want to expire the permit to do phase II. Later that day found out that the resubmittal had been sitting at the permits desk for 3 months.
|
Plan resubmittals received | | | 6/18/2009 | | DONE |
|
|
|
received 1 transmittal,2 memorandum, 2 heating ventilation and air conditioning,2 electrical general provisions, and 2 copies of sheets A0.01,A0.02,A0.03,A2.41,A3.12,A3.13,E1.10,E1.11,E2.10,E2.11,E2.13,E2.14 Waiting for bond to come in before sending to Carl W. 6-18-09 ///dld 9-14-09 plans taken to Carl Westfall ///dld
|
Extend Permit 180 days | | 12/9/2008 | 6/8/2009 | | DONE |
|
|
|
Jenifer approved an extension of the permit application to June 8, 2009.
|
CHANGE STATUS TO (REV) | | | 2/18/2009 | | DONE |
|
|
|
For some reason, the permit was put in the issued status. This is NOT correct. The status was changed to REV.
|
Plan Reviewer's activity | | | 1/22/2009 | | DONE |
|
|
|
Sent a letter to Tegan informing her that the permit application needs to be extended or it will expire.
|
Routing - FIRE | 10/15/2008 | 10/15/2008 | 10/17/2008 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 10/17/2008 | | FAIL |
|
|
|
Failed Plan Check, Fire
|
Route to Impact Fee Review | 10/15/2008 | 10/20/2008 | 10/15/2008 | | PASS |
Cindy M. Gould
|
|
|
Building improvement no new square footage, therefore no impact fees required.
|
Routing - PLAN CHECK | 6/25/2008 | | 10/15/2008 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on October 7, 2008 and was finished on October 15, 2008. Revised drawings were required. See the plan review report. An application suitable for review was submitted on October 2, 2008. The review was delayed while the architect worked out issues regarding the phasing of this project.
|
Plan resubmittals received | | | 10/2/2008 | | |
Carl Westfall
|
|
|
received transmittal and three copies of sheets a0.01, a2.41, a3.12, a3.13, s1.0, s1.2, mg1.10, m1.11, m1.14, e1.10, e1.11, e2.10, e2.11, e2.13, e2.14; taken to Carl Westfall
|
Additional plans submitted | | | 9/9/2008 | | DONE |
Barbara Stitt
|
|
|
Received 4 copies of a letter to Dave Hanneman & George Slane dated 9-8-08 (2 pgs) from Andy Erstad, 1 to Jenifer Gilliland, 1 george Slane, 1 to Sam Rogers, 1 to Carl Westfall///9-9-08 BAS
|
Routing - PLANNING | 6/20/2008 | | 6/24/2008 | | PASS |
Julie Archambeault
|
|
|
DRh08-00168
|
Routing - Erosion and Sediment | 6/18/2008 | | 6/20/2008 | | PASS |
Clint A Smith
|
|
|
ESC plan waiver approved with attached conditions. ESC08-00524
|
Pending Assignment by MYS | 6/12/2008 | | 6/18/2008 | | DONE |
Marlene Southard
|
|
|
6/18/2008 11:56:36 MYS - activity updated through activity BLDA172 from case BLD08-01293.
|
Plans ACCEPTED BY PLAN TECH | | | 6/12/2008 | | |
Marsha Smylie
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/11/2008 | | |
Marsha Smylie
|
|
|
|
Application received | | 6/11/2008 | | | |
Marsha Smylie
|
|
|
|