Second Notice | | 7/22/2009 | 8/5/2009 | | DONE |
|
|
|
|
First Notice | | 5/12/2009 | 7/22/2009 | | DONE |
|
|
|
|
BLD-Final | 5/12/2009 | 5/12/2009 | 5/12/2009 | P | PASS |
Mike Jordan
|
|
|
joe - around 1 please Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 5/12/2009 | | DONE |
|
|
|
|
BLD-Final | 3/4/2009 | 3/6/2009 | 3/6/2009 | P | PART |
Tom Arcoraci
|
|
|
Joe Phone #: ###-#### ok for temp
|
FIRE-Final Inspection | 3/5/2009 | 3/6/2009 | 3/6/2009 | A | PASS |
Troy Cobbley
|
|
|
LIfe safety passed. Alan is to verify the operation of the fire smoke dampers. Mark Senteno approved the narrow gates and the deletion of the Opticon systm and the Knox key box
|
FIRE-Final Inspection | 3/4/2009 | 3/5/2009 | 3/5/2009 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm permit needs to be finaled. Mount the occupant load signs, provide signage on the riser room and facp rooms as discussed. Provide exit discharge light at the main exit.
|
FIRE-Final Inspection | 3/3/2009 | 3/4/2009 | 3/4/2009 | A | FAIL |
Troy Cobbley
|
|
|
The only items inspected today was the exit signs/emergency lighting. See the city approved plans for locations where devices are missing or inoperative.
|
BLD-Final | 3/2/2009 | 3/3/2009 | 3/3/2009 | A | NR |
Mike Jordan
|
|
|
Joe Phone #: ###-####. Needs other trades and zoning first. Contacted Joe wtih EKC and let him know what needed to be completed prior to structural sign off.
|
FIRE-Conference | 3/2/2009 | 3/2/2009 | 3/2/2009 | P | DONE |
Troy Cobbley
|
|
|
All a/v's are now meeting the height requirements of NFPA 72.
|
BLD-Wall cover | 2/25/2009 | 2/26/2009 | 2/26/2009 | A | PASS |
Jim Storey
|
|
|
Joe- cover Phone #: ###-#### new entry ok to cover 2 layers 5/8 gyp
|
BLD-Framing/Rough-in | 2/25/2009 | 2/25/2009 | 2/25/2009 | P | DEFR |
Jim Storey
|
|
|
Joe- cover Phone #: ###-#### work not ready for insp. defered to am.301
|
Meeting | | | 2/23/2009 | | DONE |
|
|
|
Fire - Alternative Design approval - per Email received 2/23/09. Sam, I will approve the installation of the two security gates at City Hall West without the Opticom system if the following two conditions are met: 1. In the event of a power outage, the gate locks fail unlocked (the gate is balanced so it can be manually opened) 2. In the event of a fire alarm, the gates open and remain open until the alarm is reset. Thank you,
Mark Senteno
|
BLD-Framing/Rough-in | 2/18/2009 | 2/19/2009 | 2/19/2009 | A | PART |
Jim Sly
|
|
|
Joe Phone #: ###-#### Framing OK Panic vestible....Fire caulk OK at interrogation area rated walls.
|
BLD-Conference | 2/11/2009 | 2/11/2009 | 2/11/2009 | P | PART |
Mike Jordan
|
|
|
Inspected required structural upgrade, also inspected membrane and thruogh penetrations for 1hr. wall. Info from architect is incomplete, received design listings only no details. Called and left message with architect.
|
BLD-Other | 2/5/2009 | 2/5/2009 | 2/5/2009 | P | PASS |
Mike Jordan
|
|
|
joe Note: rebar - 4:00 pour schedule Phone #: ###-####
|
BLD-Footing | 1/30/2009 | 2/2/2009 | 2/2/2009 | A | DONE |
Tom Arcoraci
|
|
|
joe Phone #: ###-#### flag pole
|
BLD-Framing/Rough-in | 1/21/2009 | 1/21/2009 | 1/21/2009 | P | PART |
Mike Jordan
|
|
|
Performed general walk through to see progress of job. Noted that contractor has received membrane and thru penetration details from architect. wip
|
BLD-Footing | 1/21/2009 | 1/21/2009 | 1/21/2009 | P | PASS |
Mike Jordan
|
|
|
Remainder of footing for masonry screen wall.
|
BLD-Framing/Rough-in | 1/12/2009 | 1/12/2009 | 1/12/2009 | P | PASS |
Mike Jordan
|
|
|
1hr. wall, 2nd layer ok.
|
BLD-Framing/Rough-in | 1/7/2009 | 1/8/2009 | 1/8/2009 | A | PART |
Mike Jordan
|
|
|
joe Phone #: ###-####. Interior steel stud framing at 1hr. walls for I occ. hardlids ok, 1st. layer ok. Issued c/n for architect to provide UL approved assemblies for all membrane and thru penetrations.
|
BLD-Foundation | 1/8/2009 | 1/8/2009 | 1/8/2009 | A | PART |
Mike Jordan
|
|
|
wip on conc. art wall. Will have special insp.
|
BLD-Framing/Rough-in | 12/29/2008 | 12/30/2008 | 12/30/2008 | P | PART |
Jim Sly
|
|
|
Joe Please call first If possible around 3pm Phone #: ###-#### 1st layer 2hr walls near S.W. corner of bldg...OK
|
BLD-Other | 12/29/2008 | 12/29/2008 | 12/29/2008 | P | PART |
Jim Sly
|
|
|
logan- stem wall Phone #: ###-#### OK pending MTI special insp, tests and approvals.
|
BLD-Framing/Rough-in | 12/23/2008 | 12/23/2008 | 12/23/2008 | P | PASS |
Mike Jordan
|
|
|
Interior steel stud framing for soffitts.
|
BLD-Framing/Rough-in | 12/11/2008 | 12/11/2008 | 12/11/2008 | P | PASS |
Mike Jordan
|
|
|
nterior steel stud framed walls for area D.
|
BLD-Footing | 12/10/2008 | 12/11/2008 | 12/11/2008 | A | PART |
Mike Jordan
|
|
|
logan Phone #: ###-####. Footings for art wall. Noted special insp.
|
BLD-Framing/Rough-in | 12/8/2008 | 12/8/2008 | 12/8/2008 | P | PART |
Mike Jordan
|
|
|
Joe Phone #: ###-####. Interior steel stud framed walls in area D.
|
BLD-Framing/Rough-in | 11/12/2008 | 11/12/2008 | 11/12/2008 | P | PART |
Mike Jordan
|
|
|
joe Phone #: ###-####. Interior steel stud framed walls in areas A , B. ok to one side only.
|
BLD-Footing | 11/3/2008 | 11/4/2008 | 11/4/2008 | P | DEFR |
Mike Jordan
|
|
|
logan Phone #: ###-####. Footings for new vestibule. Already placed when on site. Did note that special insp. was done.
|
BLD-Footing | 10/30/2008 | 10/31/2008 | 10/31/2008 | A | PASS |
Mike Jordan
|
|
|
logan Phone #: ###-####. Footing for permiter screen wall, South and west portions of site. Special insp. also on site.
|
BLD-Footing | 10/23/2008 | 10/24/2008 | 10/24/2008 | P | PART |
Mike Jordan
|
|
|
logan Phone #: ###-####. Fooring for screenwall, Southwest end of site. Will have special insp.
|
Issue & PRINT to be Invoiced | | | 9/10/2008 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 8/29/2008 | 8/29/2008 | 9/9/2008 | | PASS |
Scott Arellano
|
|
|
*9/2/08* Plans on hold. FD access roadway width at security gates being evaluated by Sam Rogers and Dave Hanneman. *9/9/08* Approved by dave Hanneman. Attached updated IFC comments to plans.
|
Routing - PLAN CHECK | 9/9/2008 | | 9/9/2008 | | |
|
|
|
Routed to Planning for review of revised drawings.
|
Routing - PLAN CHECK | 9/9/2008 | | 9/9/2008 | | |
|
|
|
Routed to Plan Check (Carl W.)
|
Routing - PLAN CHECK | 9/9/2008 | | 9/9/2008 | | DONE |
Carl Westfall
|
|
|
All agencies signed-off.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/9/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/9/2008 | | DONE |
|
|
|
|
Telephone call | | | 9/9/2008 | | DONE |
|
|
|
left vm for liza morris at ###-#### - permit ready and fees given - also need gc name, rce# and rp name
|
Permit Ready to Issue | | | 9/9/2008 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 6/20/2008 | | 9/9/2008 | | PASS |
Carl Westfall
|
|
|
9/9/2008 12:20:47 CJW - activity updated through activity BLDA022 from case BLD08-01321.
|
Routing - PLANNING | 9/9/2008 | | 9/9/2008 | | PASS |
Matthew A Halitsky
|
|
|
Revised drawings were submitted. Please re-review the drawings and add back "red lined" notes where required.
|
Telephone call | | | 9/4/2008 | | DONE |
Scott Arellano
|
|
|
Call from Cory Nelson regarding the status of the fire review on the resubmitted plan sheets for Boise City Hall West. Informed Cory that the plans are being evaluated by Sam Rogers and Dave Hanneman regarding fire department access roadway widths.
|
Telephone call | | | 9/1/2008 | | DONE |
Scott Arellano
|
|
|
Call from Cory Nelson regarding the status of the fire review on the resubmitted plan sheets for Boise City Hall West. Informed Cory plan review should be finished today.
|
Route to Impact Fee Review | 8/29/2008 | 9/4/2008 | 8/29/2008 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no fees
|
Routing - PLAN CHECK | 8/15/2008 | | 8/29/2008 | | PASS |
Carl Westfall
|
|
|
Drawings approved after the resubmittal review.
|
Plan resubmittals received | | | 8/27/2008 | | |
Carl Westfall
|
|
|
Received 1 cover transmittal, 2 copies of response comments dated 8-20-08 from Cory Nelson (2 pgs), 2 copies of response letter for mechanical review and calcs (3pgs), 2 structural calcs books, 2 copies of sheets A3.0, A5.0, A5.1, A6.1, S0.01, S1.01, S2.01, S4.01, S5.01, S6.01, M1.1 and taken to Carl Westfall's desk 8-27-08 @ 3:51pm BAS
|
Routing - FIRE | 8/8/2008 | 8/8/2008 | 8/15/2008 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 8/15/2008 | | FAIL |
|
|
|
Failed Plan Check, Fire
|
Route to Impact Fee Review | 8/8/2008 | 8/13/2008 | 8/8/2008 | | PASS |
Shelly L. Hendrikse
|
|
|
Tenant improvements, no fees.
|
Routing - PLAN CHECK | 7/1/2008 | | 8/8/2008 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on July 25, 2008 and was finished on August 8, 2008. Revised drawings were required. See the plan review report.
|
Plan resubmittals received | | | 7/30/2008 | | |
Carl Westfall
|
|
|
Received transmittal and two copies of Project Manual; taken to Carl Westfall
|
Plan resubmittals received | | | 7/21/2008 | | |
Carl Westfall
|
|
|
Received transmittal and two copies of Structural Supplement Calculations; taken to Carl Westfall
|
Plan resubmittals received | | | 7/17/2008 | | |
|
|
|
Received 1 cover transmittal, 3 new complete sets of plans due to plan modification///7-17-08 BAS/// Sets include- a0.0 a0.1 c1.01 c2.01 c1.0 c2.0 a1.0 a1.1 a1.2 a1.3 a1.4 a1.5 a2.0 a2.01 a2.1 a2.2 a2.3 a2.4 a2.5 a2.6 a2.7 a3.0 a4.0 a4.1 a5.0 a6.0 a6.1 a7.0 a7.1 a8.0 a8.1 a8.2 a8.3 a8.4 a8.5 a9.0 a9.1 a9.2 a9.3 a9.4 a9.5 id1.1 id1.2 s0.01 s1.01 s2.01 s4.01 s5.01 s5.02 s5.03 s5.04 s6.01 mg1.1 mg1.2 m0.1 m1.1 m1.2 m1.3 m1.4 m1.5 m2.1m m2.2 m3.1 m4.1 p0.1 p1.1 p1.2 p1.3 p1.4 p1.5 p2.1 e0.0 e0.2 e0.3 e0.4 e0.5 e0.6 e1.1 e1.2 e1.3 e1.4 e1.5 e1.6 e1.7 e1.8 e2.1 e2.2 e2.3 e2.4 e3.1 e3.2e e3.3e e3.4 e4.1 e4.2 e4.3 e4.4 e4.5 e5.1 e5.2 e5.3 e5.4
|
Routing - PLANNING | 7/1/2008 | | 7/1/2008 | | PASS |
Matthew A Halitsky
|
|
|
Route to Plan Check (Carl W.)
|
Routing - PLANNING | 6/27/2008 | | 6/27/2008 | | PASS |
Joshua Johnson
|
|
|
routed to DRH08-00125 Matt Halitsky
|
Routing - PUBLIC WORKS | 6/24/2008 | | 6/27/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing - Erosion and Sediment | 6/27/2008 | | 6/27/2008 | | PASS |
Clint A Smith
|
|
|
ESC plan approved with attached conditions. ESC08-00532
|
Routing PW Sewer Rating | 6/26/2008 | | 6/26/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PLANNING Land Div | 6/20/2008 | | 6/24/2008 | | PASS |
Dave Abo
|
|
|
Parcel A on Record Of Survey #4760. Previously Lots 50-52, Block 2, Corporate Center No. 4 Subdivision.
|
Pending Assignment by MYS | 6/16/2008 | | 6/20/2008 | | DONE |
Marlene Southard
|
|
|
6/20/2008 14:21:17 MYS - activity updated through activity BLDA172 from case BLD08-01321.
|
Plans ACCEPTED BY PLAN TECH | | | 6/17/2008 | | |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/17/2008 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 6/16/2008 | | | |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | | | |
Carl Westfall
|
|
|
Received 1 cover transmittal, 2 books of Boise City Hall West Hazardous Materials List books and taken to Carl Westfall///8-12-08 @ 8:10am BAS
|
Plan resubmittals received | | | | | |
Carl Westfall
|
|
|
Received 1 cover transmittal, 1 transmittal to fire review, 1 copy of email dated 8-20-08 from Mark Senteno with fire, 2 copies of sheet A1.0, A1.1 and taken to Carl Westfall///8-20-08 @ 1:15pm BAS
|