Plan Reviewer's activity | | | 4/10/2013 | | DONE |
Tim L. Woodard
|
|
|
Fire requested a C of O for expanded liquor store. I didn't require a new C of O at the time due to an existing C of O being on file; however, in order to clearly show the extent of this space the decision was made to issue a new C of O with the expansion area. TLW
|
Permanent Occupancy | | | 4/10/2013 | | DONE |
Tisha Gallop
|
|
|
|
Second Notice BLD | 9/22/2008 | 9/22/2008 | 11/24/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | 9/11/2008 | 9/11/2008 | 9/22/2008 | | DONE |
Jim Storey
|
|
|
|
BLD-Final | 9/10/2008 | 9/11/2008 | 9/11/2008 | A | PASS |
Jim Storey
|
|
|
David Phone #: ###-####
|
DOC - Permit Finaled | 9/11/2008 | 9/11/2008 | 9/11/2008 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 9/8/2008 | 9/9/2008 | 9/9/2008 | A | NR |
Jim Storey
|
|
|
david Phone #: ###-####
|
FIRE-Final Inspection | 9/5/2008 | 9/8/2008 | 9/8/2008 | A | PASS |
Forrest France
|
|
|
Fire life safety passed, door hardware at the south side-see red-lines on approved plans-to be removed prior to structural final inspection as discussed.
|
FIRE-Conference | 9/4/2008 | 9/4/2008 | 9/4/2008 | A | DONE |
Forrest France
|
|
|
On site visit, regarding door hardware completion.
|
BLD-Final | 8/21/2008 | 8/22/2008 | 8/22/2008 | A | NR |
Jim Storey
|
|
|
david Phone #: ###-####
|
BLD-Framing/Rough-in | 8/7/2008 | 8/8/2008 | 8/8/2008 | A | PART |
Dave Hannah
|
|
|
David- ceiling grid Phone #: ###-#### ok to cover ceiling
|
BLD-Framing/Rough-in | 7/30/2008 | 7/31/2008 | 7/31/2008 | A | PASS |
Jim Storey
|
|
|
David Phone #: ###-####
|
BLD-Framing/Rough-in | 7/29/2008 | 7/30/2008 | 7/30/2008 | A | FAIL |
Jim Storey
|
|
|
David Phone #: ###-#### dimition bust for lay out of ada spacing.
|
BLD-Concrete | 7/25/2008 | 7/28/2008 | 7/28/2008 | A | PASS |
Jim Storey
|
|
|
David Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/27/2008 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/26/2008 | | DONE |
|
|
|
|
Telephone call | | | 6/26/2008 | | DONE |
|
|
|
t/c w hal hofheins at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/26/2008 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/25/2008 | | |
Tim L. Woodard
|
|
|
received "2" sets of plans including each sheet of A.1.O, A2.O, A3.O-- plans taken to Tim Woodard
|
Routing - PLAN CHECK | 6/25/2008 | | 6/25/2008 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/25/2008 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 6/23/2008 | | 6/25/2008 | | PASS |
Tim L. Woodard
|
|
|
6/25/2008 15:58:19 TLW - activity updated through activity BLDA022 from case BLD08-01358.
|
Routing - FIRE | | | 6/24/2008 | | PASS |
|
|
|
All Fire requirements from 2006 IFC will be field verified by fire inspector.
|
1st review completed | | | 6/24/2008 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 6/23/2008 | | 6/24/2008 | | FAIL |
Tim L. Woodard
|
|
|
Refer to plan review report.
|
Routing - PLAN CHECK | 6/20/2008 | | 6/24/2008 | | PEND |
Ron Hill
|
|
|
Ron Hill / Re- Routed to Tim W.
|
Plan assigned to (R_H) | 6/20/2008 | 6/20/2008 | 6/23/2008 | | DONE |
Ron Hill
|
|
|
|
Routing - PUBLIC WORKS | 6/20/2008 | | 6/20/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 6/20/2008 | | 6/20/2008 | | PASS |
Louise Waldorf
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/20/2008 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | 6/19/2008 | 6/19/2008 | | DONE |
Barbara Stitt
|
|
|
|