Third Notice | | 2/14/2010 | 2/9/2010 | | DONE |
|
|
|
|
Second Notice | | 1/23/2010 | 2/9/2010 | | DONE |
|
|
|
|
First Notice | | 1/7/2010 | 1/13/2010 | | DONE |
|
|
|
sent by mail
|
Permanent Occupancy | | | 12/28/2009 | | DONE |
|
|
|
|
BLD-Final | 11/30/2009 | 11/30/2009 | 11/30/2009 | P | PASS |
Tom Arcoraci
|
|
|
dusanka Phone #: ###-####
|
FIRE-Final Inspection | 11/30/2009 | 11/30/2009 | 11/30/2009 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 11/25/2009 | 11/27/2009 | 11/27/2009 | P | NR |
Jim Sly
|
|
|
DUSANKA Phone #: ###-#### Need OK from CDHD...... and need Final from Fire.
|
FIRE-Final Inspection | 11/25/2009 | 11/27/2009 | 11/27/2009 | A | FAIL |
Troy Cobbley
|
|
|
The exit discharge lights failed to operate when tested.
|
BLD-Aging Inspection | 10/2/2009 | 10/2/2009 | 10/2/2009 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Energy code compliance | 7/30/2009 | 7/30/2009 | 7/30/2009 | P | PASS |
Jim Storey
|
|
|
zuhdiga Phone #: ###-####
|
BLD-Framing/Rough-in | 7/2/2009 | 7/6/2009 | 7/6/2009 | P | PASS |
Tom Arcoraci
|
|
|
zudo Phone #: ###-####
|
BLD-Foundation | 6/12/2009 | 6/12/2009 | 6/12/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Foundation | 6/11/2009 | 6/11/2009 | 6/12/2009 | P | PART |
Tom Arcoraci
|
|
|
|
BLD-Foundation | 6/9/2009 | 6/10/2009 | 6/11/2009 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 6/9/2009 at 5:10:15 PM. Contact: ###-####.
|
BLD-Footing | 6/9/2009 | 6/10/2009 | 6/10/2009 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 6/9/2009 at 5:09:41 PM. Contact: ###-####.
|
BLD-Foundation | 6/8/2009 | 6/9/2009 | 6/9/2009 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 6/8/2009 at 11:32:55 AM. Contact: ###-####.
|
BLD-Footing | 6/8/2009 | 6/9/2009 | 6/9/2009 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 6/8/2009 at 11:32:33 AM. Contact: ###-####. needs to return to plan review
|
BLD-Footing | 6/8/2009 | 6/8/2009 | 6/8/2009 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/8/2009 at 8:12:22 AM. Contact: ###-####. Will reschedule for tommorrow.
|
BLD-Foundation | 6/8/2009 | 6/9/2009 | 6/8/2009 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 6/8/2009 at 8:13:32 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jun 8 2009 11:30AM.
|
Issue PAID IN FULL permit | | | 5/29/2009 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 5/18/2009 | | 5/20/2009 | | PASS |
Tim L. Woodard
|
|
|
Resubmitted plans (5-12-09) approved. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 5/20/2009 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 5/20/2009 | | DONE |
|
|
|
|
Telephone call | | | 5/20/2009 | | DONE |
|
|
|
left message w leslie for rocky at ###-#### - permit ready and fees given - also need gc and rce#
|
Permit Ready to Issue | | | 5/20/2009 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 6/23/2008 | | 5/20/2009 | | PASS |
Tim L. Woodard
|
|
|
5/20/2009 09:36:59 TLW - activity updated through activity BLDA022 from case BLD08-01370.
|
Routing - FIRE | 5/14/2009 | 5/14/2009 | 5/18/2009 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Route to Impact Fee Review | 5/14/2009 | 5/19/2009 | 5/15/2009 | | PASS |
Cindy M. Gould
|
|
|
Added fees to 1,030 new addition.
|
Routing - PLAN CHECK | 8/1/2008 | | 5/14/2009 | | PASS |
Tim L. Woodard
|
|
|
Plans approved per resubmitted items. TLW
|
Plan resubmittals received | | | 5/13/2009 | | |
Tim L. Woodard
|
|
|
Received 1 cover transmittal, 2 copies of sheets Cover, LS1, A0.1, A1.1, A1.2, A1.4, A1.5, A2.1, A3.1, A5.1, A6.1, A7.2, A7.3, A7.4, Envelope, EN0.0, E0, E1, E2 and taken to Tim Woodard's desk 5-13-09 @ 8:42am BAS
|
Permit EXTENDED | | | 2/2/2009 | | DONE |
Rita DeYoung
|
|
|
|
Plan Reviewer's activity | | | 1/20/2009 | | DONE |
Tim L. Woodard
|
|
|
Sent Rocky Towle warning of expiration. Gave him a final deadline of Januaray 23rd, 2009.
|
Telephone call | | | 12/29/2008 | | DONE |
Tim L. Woodard
|
|
|
Left message that permit will expire in 2 weeks unless extension is approved by the Jenifer Gilliland. TLW
|
Case Summary (BLD) | | | 12/17/2008 | | |
|
|
|
|
Routing - FIRE | 7/29/2008 | | 8/1/2008 | | FAIL |
Kenneth R Roule
|
|
|
See IFC review comments attached. Faxed a copy of review to architect.
|
1st review completed | | | 8/1/2008 | | FAIL |
|
|
|
Failed, Offsite structual,plan check and fire.
|
Routing - PLAN CHECK | 7/1/2008 | | 7/29/2008 | | FAIL |
Tim L. Woodard
|
|
|
Needs sprinkler system. Refer to plan review report for additional corrections. TLW
|
Plan resubmittals received | | | 7/25/2008 | | |
Tim L. Woodard
|
|
|
Received three copies of sheets COVER, A1.4, A1.5, A3.1, A7.2; taken to Tim Woodard
|
Routing Off Site - STRUCTURAL | 6/23/2008 | | 7/10/2008 | | FAIL |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 6/27/2008 | | 7/1/2008 | | PASS |
Josh Wilson
|
|
|
DRH08-00085 Josh W.
|
Routing - Erosion and Sediment | 6/26/2008 | | 6/27/2008 | | PASS |
Clint A Smith
|
|
|
Plan waiver approved with attached conditions. ESC08-00521
|
Routing - PUBLIC WORKS | 6/24/2008 | | 6/26/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing - PLANNING Land Div | 6/23/2008 | | 6/24/2008 | | PASS |
Todd Tucker
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/23/2008 | | |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/23/2008 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 6/23/2008 | | DONE |
Tisha Gallop
|
|
|
called Action Couriers for pick up
|
Pending Assignment by MYS | 6/20/2008 | | 6/23/2008 | | DONE |
John Menard
|
|
|
6/23/2008 08:29:55 JCM - activity updated through activity BLDA185 from case BLD08-01370.
|
Application received | | 6/20/2008 | | | |
Tisha Gallop
|
|
|
|