BLD-Final | 9/18/2008 | 9/19/2008 | 9/19/2008 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/18/2008 at 5:36:17 PM. Contact: ###-####.
|
DOC - Permit Finaled | 9/19/2008 | 9/19/2008 | 9/19/2008 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 9/12/2008 | 9/15/2008 | 9/15/2008 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/12/2008 at 2:11:20 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/5/2008 | 8/6/2008 | 8/6/2008 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/5/2008 at 3:47:56 PM. Contact: ###-####.
|
BLD-Footing | 8/6/2008 | 8/6/2008 | 8/6/2008 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/5/2008 at 3:47:56 PM. Contact: ###-####.
|
Routing Walk-In (Zoning) | 7/22/2008 | 7/22/2008 | 7/22/2008 | P | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 7/22/2008 | 7/22/2008 | 7/22/2008 | P | DONE |
Perry Paine
|
|
|
7/22/2008 14:03:16 PEP - activity updated through activity BLDA022 from case BLD08-01579.
|
Case Summary (BLD) | | | 7/22/2008 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/22/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2008 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/22/2008 | | DONE |
|
|
|
|
Application received | | 7/22/2008 | | | |
|
|
|
|