Permit Information
Permit NumberBLD08-01595
StatusFinaled
Name ESI
Site Address 800 W IDAHO ST
Project NameTHE MODE BUILDING
Customer Number 
ePlanReviewNo
Description
**(THE MODE BUILDING - CORE & SHELL EXTERIOR REMODEL ONLY)** To remodel the exterior of the 3 story 33,400 sq ft mode building per approved plans, attached engineering and DRH08-00220. Work to include, replacement of 46 lf of storefront glazing on first floor street level Idaho street side including new entrance doors, to create three new 11'x7' openings on the second floor level in the nonbearing exterior wall and install new glazing located along Idaho street, replace five windows on the third floor along Idaho street, to replace six windows on the second floor level and eight windows on the third floor along eighth street side of building, miscellaneous exterior related finishes, this building is fully fire sprinkled for one-hour fire resistive substitution any alterations to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed and maintained per NFPA #13 as regulated by the fire department. RmH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 9/15/200910/6/2009 DONE
Telephone call  10/6/2009 DONE
DetailsTisha Gallop
phone call from Julie/ESI said final values for this project inclueded in final values given for Bld08-01464.
Telephone call  10/2/2009 DONE
DetailsTisha Gallop
called and spoke with Julie need final values, she said will work on today and get to me asap.
Telephone call  9/16/2009 DONE
DetailsTisha Gallop
call from ESI working on final value for this permit, may have been included in final value of another permit pulled on this address. She will get back to me in couple of days.
Third Notice 9/4/20099/15/2009 DONE
Telephone call  9/15/2009 DONE
DetailsTisha Gallop
called and left voice message for Janae w/ESI need final values
Third Notice 8/5/20099/4/2009 DONE
Second Notice 7/22/20098/5/2009 DONE
First Notice2/27/20092/27/20097/22/2009 DONE
DetailsDave Hannah
Letter of compliance  3/12/2009 DONE
DetailsTisha Gallop
BLD-Final2/26/20092/27/20092/27/2009APASS
DetailsDave Hannah
Joe Phone #: ###-####
DOC - Permit Finaled2/27/20092/27/20092/27/2009PPASS
DetailsDave Hannah
Zoning Approval12/15/200812/15/200812/15/2008 PASS
DetailsSarah Schafer
Approved per the DRH08-00220.
BLD-Final12/11/200812/12/200812/12/2008ANR
DetailsDave Hannah
bill Phone #: ###-#### needs zonig final
FIRE-Final Inspection11/4/200811/5/200811/5/2008ACANC
DetailsForrest France
vaugn Note: North face TI Phone #: ###-####
BLD-Framing/Rough-in8/11/20088/11/20088/11/2008PPART
DetailsDave Hannah
Von Phone #: ###-#### looked at top mounted hangeds all ok
Issue PAID IN FULL permit  8/4/2008 DONE
Plan assigned to (R_H)7/24/20087/24/20087/30/2008 PASS
DetailsRon Hill
7/30/2008 08:44:52 RMH - activity updated through activity BLDA022 from case BLD08-01595.
1st review completed  7/30/2008 DONE
PLANS/APPL TAKEN TO FRONT DESK  7/30/2008 DONE
Inspection Record Card- Bld  7/30/2008 DONE
Details
Telephone call  7/30/2008 DONE
Details
left vm for nate coombs at ###-#### - permit ready and fees given - also need rp name
Permit Ready to Issue  7/30/2008 DONE
Details
Routing - PLAN CHECK7/24/2008 7/29/2008 PASS
DetailsRon Hill
Case Summary (BLD)  7/29/2008 DONE
Routing - PLANNING7/29/2008 7/29/2008 PASS
DetailsSarah Schafer
Approved per DRH08-00220. SMS
Routing - FIRE  7/29/2008 PASS
Routing - PLAN CHECK7/29/2008 7/29/2008 PASS
DetailsRon Hill
Plans ACCEPTED BY PLAN TECH  7/24/2008  
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  7/24/2008 DONE
DetailsTisha Gallop
Zoning Approval12/15/200812/15/2008   
DetailsSarah Schafer
Application received 7/23/2008   
DetailsTisha Gallop