Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD08-01640
StatusFinaled
Name EPSTEIN CONSTRUCTION INC
Site Address 2390 E FREIGHT ST
Project NameWinco Distribution Center T I
Customer Number 
ePlanReviewNo
Description
Winco Distribution Center - Tenant Improvement - To finish a new 712,555 square foot, one story warehouse and office shell building for occupancy. The cold shell was constructed under permit BLD08-01555. This building will contain a 250,500sq. ft. cooler/freezer warehouse, a 391,095 sq. ft. dry goods warehouse, a 10,990 sq. ft. shift exchange area, a 15,780 sq. ft. battery charging area, a 7,740 sq. ft. maintenance area, 4,290 sq. ft. refrigeration/electrical area, 640 sq. ft. of sprinkler valve rooms, a 24,000 sq. ft. main office area, a 3,760 sq. ft. dry good office and a 3,760 sq. ft. perishable goods office. This building is fully fire sprinkled. The sprinklers are used for unlimited area building. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 3/29/20104/15/2010 DONE
Third Notice 3/9/20103/15/2010 DONE
e-mailed and faxed Stu White
Third Notice 2/23/20102/23/2010 DONE
e-mailed Stu White and faxed
Second Notice 2/5/20102/18/2010 DONE
First Notice 1/23/20101/26/2010 DONE
FIRE-Final Inspection1/13/20101/13/20101/13/2010PPASS
DetailsForrest France
C/N items completed, fire life safety finaled.
Permanent Occupancy UNPAID FEE  1/13/2010 DONE
BLD-Final1/5/20101/6/20101/6/2010APASS
DetailsForrest France
Correction items completed, fire life safety final approved.
BLD-Final1/5/20101/5/20101/6/2010PPASS
DetailsJim Storey
final set per angie b.
PubWorks Occupancy Approval1/6/20101/6/20101/6/2010 DONE
DetailsAngela Brosious
Ok for final occupancy per Jim Wylie.
BLD-Final9/29/20099/29/20099/29/2009PPART
DetailsJim Storey
need to test exit door mag lock control devices that are deactavated for temp occ at this time. pending engineer of record letter of review of all rfi's and si records for complance of design. temp occ. aproved.
FIRE-Final Inspection9/10/20099/15/20099/15/2009APART
DetailsForrest France
George Phone #: ###-####
Temporary Occupancy UNPAID FEE  9/15/2009 DONE
BLD-Final8/4/20098/5/20098/7/2009APART
DetailsJim Storey
george Phone #: ###-#### temp occ. ok for training of three groups to cert. for fork lift oparation. life saftey in drygoods and office in place and aproved for this use.
BLD-Framing/Rough-in7/23/20097/24/20097/24/2009APART
DetailsJim Storey
j.c. - ceiling grid for cover Phone #: ###-####
BLD-Conference7/22/20097/22/20097/22/2009APASS
DetailsJim Storey
wlked deep freezer/parshiables and exterior site for final review/ waiting for landings in progess exit signage being added to north end of smal freezer in tunal/ fire stopping of ele piping and glazing at machine rm pending instaltion. all other isues ok.
FIRE-Final Inspection6/2/20096/2/20096/3/2009PPART
DetailsForrest France
On site conference regarding fire alarm permit work site inspection schedule and related fire sprinkler system interconnections.
BLD-Energy code compliance5/28/20095/29/20095/29/2009APART
DetailsJim Sly
JC ###-####
Main office....Bldg envelope Energy code....OK.
BLD-Energy code compliance5/27/20095/28/20095/28/2009PNR
DetailsJim Sly
jc Phone #: ###-####.....Re-Sched.....
BLD-Framing/Rough-in5/21/20095/21/20095/21/2009PPART
DetailsJim Storey
CFraming inspection for main office and energy inspection for battery complex please-JC Phone #: ###-#### main office ok to cover pending plm. c/n isued for envlope of produce area.
BLD-Conference5/14/20095/15/20095/15/2009APASS
DetailsJim Storey
10:00 am meetting w/strata to review bolting. waked the job with si rep.
FIRE-Conference5/13/20095/13/20095/13/2009ADONE
DetailsForrest France
On site conference regarding project schedule.
BLD-Energy code compliance5/12/20095/13/20095/13/2009PPASS
DetailsJim Storey
J.C. Phone #: ###-#### office ok to cover walls and hard lids in produce area.
BLD-Framing/Rough-in5/11/20095/12/20095/12/2009APART
DetailsJim Storey
JC- call 30 mins prior to going Phone #: ###-#### ok to insulate
Plan resubmittals received  5/5/2009 DONE
DetailsScott Arellano
Received updated HMIS from Stuart White. HMIS is approved and within allowable limits of hazardous materials.
BLD-Energy code compliance4/15/20094/16/20094/16/2009APASS
DetailsJim Storey
j.c. - first thing in the morning please Phone #: ###-#### dry goods office ok
BLD-Framing/Rough-in4/14/20094/15/20094/15/2009APASS
DetailsJim Storey
j.c. Phone #: ###-####
Issue PAID IN FULL permit  3/12/2009 DONE
Plan assigned to (JCM)7/31/20087/31/20083/9/2009 PASS
DetailsJohn Menard
3/9/2009 14:04:41 JCM - activity updated through activity BLDA022 from case BLD08-01640.
Routing - PLAN CHECK1/15/2009 3/9/2009 PASS
DetailsJohn Menard
Plan Reviewer's activity  3/9/2009 PASS
DetailsJohn Menard
Reviewed and approved final resubmitted revisions. JCM
PLANS/APPL TAKEN TO FRONT DESK  3/9/2009 DONE
DetailsJohn Menard
Print Occupancy Form  3/9/2009 DONE
Details
Telephone call  3/9/2009 DONE
Details
left message w esther for mike at ###-#### - permit ready and fees given
Permit Ready to Issue  3/9/2009 DONE
Details
Plan resubmittals received  3/6/2009  
DetailsJohn Menard
by mail received two copies of pages A-901, A-103; taken to John Menard
Routing - MECHANICAL2/3/2009 2/6/2009 PASS
DetailsJohn Menard
Received letter from Power Engineers approving outside review of the final refrigeration resubmittals. JCM
Plan resubmittals received  2/3/2009  
Received 1 response letter,4 copies of refrigation documents and 4 copies of sheets R-301,R-401,M-103 taken to John M.
Routing - MECHANICAL12/4/2008 1/21/2009 FAIL
DetailsJohn Menard
Sent out to Power Engineers to review refrigeration system resubmittals. DLD Received comment list requesting additional submittals. JCM
Plan resubmittals requested  1/21/2009 DONE
DetailsJohn Menard
E-mailed the applicant a copy of the refrigeration 2nd review requestng additional resubmittals. JCM
Routing - FIRE1/12/2009 1/15/2009 PASS
DetailsScott Arellano
Attached IFC comments to plans.
Plan resubmittals requested  1/13/2009 DONE
DetailsJohn Menard
E-mailed the architect a letter requesting additional submittals. JCM
Telephone call  1/13/2009 DONE
Spoke to Chip with PCA regarding the hazardous materials inventory statement. Chip rescheduled a telephone conference for later to go over the materials list due to schedule conflict.
Routing - PLAN CHECK12/12/2008 1/12/2009 FAIL
DetailsJohn Menard
Will finalize comments for required resubmittals after discussions with the building official concerning bollard locations at shift exchange area. JCM
Telephone call  1/9/2009 DONE
DetailsScott Arellano
Left message with Chip with PCA (Paul Carlson Associates), regarding the WINCO hazardous materials statement. Briefly explained specific issues in which clarification is needed in order to quantify materials in respective hazard categories. Specifically, the listing of a single chemical in multiple hazard classification categories? Left office number for call back...
Plan resubmittals received  12/26/2008  
DetailsJohn Menard
Rec'd by mail one transmittal letter, two copies of response report packet, and two copies of sheet A-101, A-102, A-103, A-104, A-105, A-106, A-405-, A-600, A-901; taken to John M
Routing - FIRE12/11/2008 12/12/2008 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
Routing - PLAN CHECK12/1/2008 12/11/2008 FAIL
DetailsJohn Menard
Plan resubmittals requested  12/11/2008 DONE
DetailsJohn Menard
E-mailed the architect a letter requesting additional revisions. JCM
Plan resubmittals received  12/4/2008 DONE
received 1 transmittal,1 response, and sheets R-1,R-2,R-3.R-4,R-5,R-100,R-101,R-102,R-103,R-104,R-105,R-106,R-107,R-108,R-109,R-200,R-300,R-301,R-302,R-303,R-400,R-401,R-500,R-501 Sent out to outside engineering ///dld
Routing - FIRE11/25/2008 12/1/2008 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
Routing - PLUMBING11/24/2008 11/25/2008 PASS
DetailsBill VanDegrift
per plans and 2003 upc
Routing - PLAN CHECK10/6/2008 11/24/2008  
DetailsJohn Menard
Plan resubmittals received  11/12/2008  
received transmittal letter from epstein & sons. Also "2" sheets each of A-101, A-102, A-103, A-104, A-105, A-106, A-107, A-108, A-109, A-200, A-405, A-901, M-2, M-100, M-101, M-102, M-103, M-104, M-200, M-300, P-100, P-101, P-102, P-103, P-400, P-600, P-601, P-700, R-2, R-3, R-4, R-100, R-101, R-105, R-200, R-300, R-301, R-400, & R-401----Also received "2" sheets each of E-201, E-202, E-204, E-205, E-206, & E-207--took plans to John Menard
1st review completed  10/6/2008 FAIL
Failed PW, Plumbing, Planning, Plan Check, Fire
Routing - FIRE9/30/2008 10/6/2008 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
Routing - PLAN CHECK8/14/2008 9/30/2008 FAIL
DetailsJohn Menard
Plan resubmittals requested  9/30/2008 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review list requesting revisions. JCM
Routing - PUBLIC WORKS9/17/2008 9/17/2008 PASS
DetailsBeverly Hall
Plan resubmittals requested  9/2/2008 DONE
DetailsJohn Menard
E-maield the architect a copy of the third party review comments and fire review response for the ammonia refrigeration system requesting revisions. JCM
Routing - MECHANICAL8/1/2008 8/27/2008 FAIL
DetailsJohn Menard
Called Action Couriers for pick up to take to Power Engineers - DLD - Received comment list from consulting mechanical engineer requesting revisions on the refrigeration system. JCM
Routing - PLUMBING8/6/2008 8/14/2008 FAIL
DetailsLee Rice
public works pretreatment approval required prior to plumbing review approval. provide downstream vents on the neutralizing tank. upstream and downstream vents on the OWS may not be tied together. locate upper end vents on the combination waste and vent system downstream of upper fixture. provide loadings on the hub drains and floor drains. combination waste and vent traps and branches must be two pipe sizes larger than the fixtures. provide a fixture schedule listing waste and water requirements for SSH-1, FD1,2,3, OHD. HS-1 will require a pressure vacuum breaker. water main sizing through out building doesn't match details or from page to page. water piping details dont match corresponding details, P601 and P501.
Plan resubmittals requested  8/11/2008 DONE
DetailsJohn Menard
E-mailed the applicant a copy of the Mechanical review requesting revisions. JCM
Routing - MECHANICAL8/1/2008 8/8/2008 FAIL
DetailsJohn Menard
Plans were FedEx'd to ICC for review of Mechanical construction documents. Ammonia refrigerant review will be done by local mechanical consulting engineer. JCM - REceived comment list from ICC requesting revisions.
Routing - PUBLIC WORKS7/31/2008 8/6/2008 FAIL
DetailsConnie Baumgartner
Routing PW Environmental8/5/2008 8/5/2008 PASS
DetailsWalt Baumgartner
May need further review by Public Works Environmental.
Routing PW Sewer Rating8/4/2008 8/4/2008 PASS
DetailsConnie Baumgartner
Plans ACCEPTED BY PLAN TECH  7/31/2008 DONE
DetailsDarla L Downs
Recd Pcfee & Taken To Pln CK  7/31/2008 DONE
Application received 7/29/20087/29/2008 DONE
DetailsMarsha Smylie