Letter of compliance | | | 10/24/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
DOC - Permit Finaled | | | 10/24/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
BLD-Final | 10/21/2008 | 10/23/2008 | 10/23/2008 | P | PASS |
Dave Hannah
|
|
|
bryson Phone #: ###-####
|
FIRE-Final Inspection | 10/21/2008 | 10/22/2008 | 10/22/2008 | A | PASS |
Forrest France
|
|
|
Verified items on correction notice are in compliance, fire life safety passed, noted seals at fire doors to be installed prior to structural final.
|
FIRE-Final Inspection | 10/20/2008 | 10/21/2008 | 10/21/2008 | A | FAIL |
Forrest France
|
|
|
Door hardware at the elevator lobby egress needs to be changed, provide means for testing the two duct smoke detection devices for unit shutdown and remote annunciator functionality, remiander of life safety items are satisfactory.
|
BLD-Final | 10/17/2008 | 10/20/2008 | 10/21/2008 | P | PART |
Dave Hannah
|
|
|
don Phone #: ###-#### needs fire finals
|
BLD-Other | 10/3/2008 | 10/6/2008 | 10/6/2008 | A | PART |
Dave Hannah
|
|
|
don Note: ceiling grid Phone #: ###-#### ok to cover ceiling
|
BLD-Conference | 10/1/2008 | 10/2/2008 | 10/2/2008 | A | PASS |
Dave Hannah
|
|
|
Bycen Phone #: ###-####
|
BLD-Framing/Rough-in | 9/9/2008 | 9/10/2008 | 9/10/2008 | A | PART |
Tony Young
|
|
|
Brycen Phone #: ###-#### east side of break room ok to cover
|
BLD-Framing/Rough-in | 9/8/2008 | 9/8/2008 | 9/9/2008 | P | PASS |
Dave Hannah
|
|
|
brycen - as soon as possible please Phone #: ###-#### ok to cover corradors ceilings and other int walls after other trades ok
|
Issue PAID IN FULL permit | | | 8/20/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/19/2008 | | DONE |
|
|
|
left message w tony for rick bugatsch at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/19/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/18/2008 | | 8/18/2008 | | PASS |
Tim L. Woodard
|
|
|
Plans approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/18/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/18/2008 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/18/2008 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 8/7/2008 | | 8/18/2008 | | PASS |
Tim L. Woodard
|
|
|
8/18/2008 09:38:16 TLW - activity updated through activity BLDA022 from case BLD08-01657.
|
Plan resubmittals received | | | 8/15/2008 | | |
Tim L. Woodard
|
|
|
Received transmittal and two copies of sheets MG-1, MG-2, M-1, M-2; taken to Tim Woodard
|
Routing - PLAN CHECK | 8/4/2008 | | 8/14/2008 | | PEND |
Tim L. Woodard
|
|
|
Plans passed pending submittal of Mechanical plans.
|
1st review completed | | | 8/14/2008 | | DONE |
|
|
|
Waiting on mechanical plans.
|
Plan assigned to (R_H) | 7/31/2008 | 7/31/2008 | 8/7/2008 | | DONE |
Ron Hill
|
|
|
|
Routing - PUBLIC WORKS | 7/31/2008 | | 8/4/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 8/1/2008 | | 8/4/2008 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/31/2008 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/31/2008 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 7/31/2008 | | | |
Tisha Gallop
|
|
|
|