Case Summary (BLD) | | | 2/23/2012 | | DONE |
Tisha Gallop
|
|
|
Sent case summary to IBOL inspector Charles Ewing.
|
BLD-Final | 3/12/2009 | 3/12/2009 | 3/12/2009 | P | PASS |
Tony Young
|
|
|
Bill Phone #: ###-#### c of c issued,, need to final out ESC at a later date
|
DOC - Permit Finaled | 3/12/2009 | 3/12/2009 | 3/12/2009 | P | PASS |
Tony Young
|
|
|
|
BLD-Conference | 2/11/2009 | 2/12/2009 | 2/12/2009 | P | PART |
Tony Young
|
|
|
Bill Phone #: ###-#### general ?s,, handrails, guardrails
|
BLD-Energy code compliance | 12/29/2008 | 12/30/2008 | 12/30/2008 | A | PASS |
Tony Young
|
|
|
bill Phone #: ###-####
|
BLD-Framing/Rough-in | 12/18/2008 | 12/19/2008 | 12/19/2008 | A | PASS |
Tony Young
|
|
|
bill Phone #: ###-####
|
BLD-Framing/Rough-in | 12/5/2008 | 12/8/2008 | 12/8/2008 | A | PART |
Tony Young
|
|
|
bill Phone #: ###-#### on site conf,, need seal pack,, ok to cover part of elevator shaft
|
BLD-Framing/Rough-in | 10/20/2008 | 10/20/2008 | 10/20/2008 | P | PART |
Tony Young
|
|
|
bill Phone #: ###-#### ok to cover pert of garage walls for mech install,, no other trades involved
|
(F) Reprint permit | | | 10/15/2008 | | |
|
|
|
|
BLD-Conference | 10/6/2008 | 10/6/2008 | 10/7/2008 | P | PASS |
Tony Young
|
|
|
bill Phone #: ###-####
|
BLD-Conference | 10/6/2008 | 10/7/2008 | 10/7/2008 | A | PASS |
Tony Young
|
|
|
bill Phone #: ###-####,, bond release 1st floor is on,, starting on second floor
|
BLD-Foundation | 9/11/2008 | 9/11/2008 | 9/11/2008 | P | PASS |
Jim Storey
|
|
|
mike Phone #: ###-####
|
BLD-Footing | 9/8/2008 | 9/9/2008 | 9/9/2008 | A | PASS |
Dave Hannah
|
|
|
Mike Phone #: ###-####
|
PubWorks Subgrade Approval | 8/29/2008 | 8/29/2008 | 8/29/2008 | | DONE |
Terry Records
|
|
|
Footing subgrade approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 8/8/2008 | | DONE |
Tisha Gallop
|
|
|
|
Routing Walk-In (BLD) | 8/1/2008 | 8/1/2008 | 8/7/2008 | A | DONE |
Perry Paine
|
|
|
8/7/2008 13:03:06 PEP - activity updated through activity BLDA022 from case BLD08-01659.
|
Case Summary (BLD) | | | 8/7/2008 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/7/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2008 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/7/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 8/7/2008 | | |
|
|
|
|
Routing Walk-In (PW Hillside) | 8/1/2008 | 8/1/2008 | 8/1/2008 | A | PASS |
Terry Records
|
|
|
Per Terry Records ok to get building permit; A letter from the applicant's geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection.
|
Routing Walk-In (Zoning) | 8/1/2008 | 8/1/2008 | 8/1/2008 | A | PASS |
Lucinda Grames
|
|
|
|
Application received | | 8/1/2008 | | | |
|
|
|
|