BLD-Final | 10/22/2008 | 10/24/2008 | 10/24/2008 | P | PASS |
Mike Jordan
|
|
|
tom or ###-#### vaugh Phone #: ###-####
|
DOC - Permit Finaled | 10/24/2008 | 10/24/2008 | 10/24/2008 | P | PASS |
Mike Jordan
|
|
|
Cert. of compliance issued.
|
BLD-Energy code compliance | 9/16/2008 | 9/17/2008 | 9/17/2008 | A | PASS |
Tony Young
|
|
|
vaughn Phone #: ###-####
|
BLD-Framing/Rough-in | 9/16/2008 | 9/16/2008 | 9/16/2008 | P | PASS |
Tony Young
|
|
|
vaughn Phone #: ###-####
|
BLD-Energy code compliance | 9/16/2008 | 9/16/2008 | 9/16/2008 | P | PASS |
Tony Young
|
|
|
vaughn Phone #: ###-####
|
BLD-Framing/Rough-in | 9/12/2008 | 9/15/2008 | 9/15/2008 | P | PASS |
Tony Young
|
|
|
tom or shane ###-#### Phone #: ###-####
|
BLD-Foundation | 8/20/2008 | 8/21/2008 | 8/21/2008 | A | PART |
Tony Young
|
|
|
een Phone #: ###-####
|
BLD-Footing | 8/19/2008 | 8/20/2008 | 8/20/2008 | A | PASS |
Tony Young
|
|
|
ian Phone #: ###-#### ftgs ok
|
BLD-Footing | 8/19/2008 | 8/19/2008 | 8/19/2008 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/19/2008 at 6:42:47 AM. Contact: ###-####.
|
BLD-Footing | 8/18/2008 | 8/18/2008 | 8/18/2008 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/18/2008 at 6:48:33 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 8/11/2008 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 8/8/2008 | 8/8/2008 | 8/8/2008 | P | DONE |
Perry Paine
|
|
|
8/8/2008 14:06:28 PEP - activity updated through activity BLDA022 from case BLD08-01663.
|
Routing Walk-In (BLD) | 8/1/2008 | 8/1/2008 | 8/8/2008 | P | DONE |
Marsha Smylie
|
|
|
8/8/2008 13:03:38 MLS - activity updated through activity BLDI252 from case BLD08-01663.
|
Case Summary (BLD) | | | 8/8/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 8/8/2008 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/8/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2008 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 8/1/2008 | 8/1/2008 | 8/1/2008 | P | PASS |
Lucinda Grames
|
|
|
|
Application received | | 8/1/2008 | | | |
|
|
|
|