Case Summary (BLD) | | | 6/23/2011 | | DONE |
|
|
|
|
BLD-Final | 9/30/2009 | 10/1/2009 | 10/1/2009 | A | PASS |
Tom Arcoraci
|
|
|
Brad Phone #: ###-####
|
Permanent Occupancy | | | 10/1/2009 | | DONE |
|
|
|
|
BLD-Final | 9/29/2009 | 9/30/2009 | 9/30/2009 | P | FAIL |
Dave Hannah
|
|
|
Brad Phone #: ###-#### needs door closure entry door
|
FIRE-Final Inspection | 9/29/2009 | 9/30/2009 | 9/30/2009 | A | PASS |
Forrest France
|
|
|
Fire life safety okay for final pending installation of the finished main door and closure with smoke seal -to be completed prior to structural final approval as discussed.
|
BLD-Framing/Rough-in | 7/13/2009 | 7/14/2009 | 7/15/2009 | P | PASS |
Dave Hannah
|
|
|
brad Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/12/2009 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 3/12/2009 | | DONE |
|
|
|
Called John, Permits ready
|
Permit Ready to Issue | | | 3/12/2009 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/2009 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/11/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plan assigned to (CJW) | 8/13/2008 | | 3/11/2009 | | PASS |
Carl Westfall
|
|
|
3/11/2009 07:42:55 CJW - activity updated through activity BLDA022 from case BLD08-01711.
|
Routing - PLAN CHECK | 2/27/2009 | | 3/10/2009 | | PASS |
Carl Westfall
|
|
|
(3-2-09) Sent E-mail to architect and engineer asking for a design for the attachment of the spas to the existing post tensioned concrete deck. The other items seem to be resolved. (3-10-09) Issues resolved.
|
Routing - PLANNING | 2/27/2009 | | 2/27/2009 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLAN CHECK | 12/10/2008 | | 2/27/2009 | | PASS |
Carl Westfall
|
|
|
(2-20-09) Completed the IBC resubmittal review. Drawings approved with "red lines". Working on resubmittal review for the 17th Story units.
|
Route to Impact Fee Review | 2/23/2009 | 2/26/2009 | 2/23/2009 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 12/3/2008 | 12/8/2008 | 2/23/2009 | | PASS |
Cindy M. Gould
|
|
|
|
CHANGE STATUS TO (REV) | | | 2/18/2009 | | DONE |
Rita DeYoung
|
|
|
|
Extend Permit 180 days | | 1/21/2009 | 1/21/2009 | | DONE |
|
|
|
At the request of Jenifer Gilliland, entered this activity to document that an 180 day extension was granted and that the new expiration date for this permit application is August 3, 2009. This permit application cannot be extended beyond that date. CJW
|
Routing - FIRE | 12/3/2008 | 12/3/2008 | 12/10/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 12/10/2008 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 8/13/2008 | | 12/3/2008 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on November 28, 2008 and was finished on December 3, 2008. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 8/13/2008 | | 8/13/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Sewer Rating | 8/13/2008 | | 8/13/2008 | | PASS |
Louise Waldorf
|
|
|
|
Pending Assignment by MYS | 8/8/2008 | | 8/13/2008 | | DONE |
Marlene Southard
|
|
|
8/13/2008 11:16:18 MYS - activity updated through activity BLDA172 from case BLD08-01711.
|
Plans ACCEPTED BY PLAN TECH | | | 8/8/2008 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/8/2008 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 8/8/2008 | | | |
Tisha Gallop
|
|
|
|