Second Notice | | 7/22/2009 | 8/6/2009 | | DONE |
Barbara Stitt
|
|
|
|
First Notice | | 3/6/2009 | 7/22/2009 | | DONE |
|
|
|
|
BLD-Final | 3/5/2009 | 3/6/2009 | 3/6/2009 | A | PASS |
Tom Arcoraci
|
|
|
Daryl Phone #: ###-####
|
FIRE-Final Inspection | 3/5/2009 | 3/6/2009 | 3/6/2009 | A | PASS |
Troy Cobbley
|
|
|
life safety passed;
Note: sprinklers were installed and finaled under FIR08-00541. Fire alarm monitoring was installed and finaled under FIR08-00593. SLR 3-6-09
|
Print Occupancy Form | | | 3/6/2009 | | DONE |
|
|
|
|
Permanent Occupancy | | | 3/6/2009 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Final Inspection | 2/27/2009 | 3/2/2009 | 3/2/2009 | A | PART |
Troy Cobbley
|
|
|
LIfe safety will be ok to final when the shell permit is finaled.
|
FIRE-Final Inspection | 2/24/2009 | 2/25/2009 | 2/25/2009 | A | FAIL |
Troy Cobbley
|
|
|
See the correction notice left at the job site for items needing addressed.. Per a conversation with Scott the remote FDC and PIV arer not required. I measured the distance from the existing fire hydrant to the now wall mounted PIV and FDC and the distance is roughly 250'-0" which is ok with Scott.
|
BLD-Final | 1/22/2009 | 1/23/2009 | 1/23/2009 | A | PART |
Jim Storey
|
|
|
darrell Note: 9:00 am Phone #: ###-#### need fire life saftey sign off/ ada signage/ mirriors/ tp despencers/ all other bld insp. ok.
|
BLD-Energy code compliance | 12/16/2008 | 12/17/2008 | 12/18/2008 | P | PASS |
Jim Storey
|
|
|
Steve Phone #: ###-####
|
BLD-Energy code compliance | 10/29/2008 | 10/30/2008 | 10/30/2008 | A | PASS |
Jim Storey
|
|
|
steve Phone #: ###-#### frame and insulation ok for cover.
|
BLD-Energy code compliance | 10/17/2008 | 10/17/2008 | 10/17/2008 | P | NR |
Jim Storey
|
|
|
steve Phone #: ###-#### need plm permit.
|
BLD-Energy code compliance | 10/3/2008 | 10/7/2008 | 10/7/2008 | P | FAIL |
Jim Storey
|
|
|
steve Phone #: ###-#### need shell framing and trades as well as ti framing and trades/ stoped work bldg. insulated w/o aproval.
|
Issue PAID IN FULL permit | | | 10/3/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/2/2008 | | DONE |
|
|
|
|
Telephone call | | | 10/2/2008 | | DONE |
|
|
|
t/c w lynn brown at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/2/2008 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 9/5/2008 | | 10/1/2008 | | PASS |
Dan Stuart
|
|
|
10/1/2008 16:09:54 DRS - activity updated through activity BLDA022 from case BLD08-01759.
|
Routing - PLAN CHECK | 9/25/2008 | | 10/1/2008 | | PASS |
Dan Stuart
|
|
|
Resubmittals inserted into plans, plan review comments modified and attached to plans. Plans to permit desk to issue.
|
Plan resubmittals received | | | 10/1/2008 | | DONE |
Dan Stuart
|
|
|
Rec'd one response letter and two copies of pages- a-1, a-2, a-3, a-4, a-5, a-6, e-1, e-2, e-3; taken to Dan Stuart///10-1-08 ALR
|
Print Pending Permit.LaserJet4 | | | 10/1/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 10/1/2008 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2008 | | PASS |
|
|
|
|
Routing - FIRE | 9/25/2008 | 9/25/2008 | 9/25/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 9/25/2008 | | FAIL |
|
|
|
Failed Plan Check
|
Route to Impact Fee Review | 9/24/2008 | 9/29/2008 | 9/24/2008 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement
|
Plan resubmittals requested | | | 9/24/2008 | | DONE |
|
|
|
Copy of plan review items needing to be addressed by plan resubmittals e-mailed to architect, Lynn Brown and owner Steve Christensen.
|
Routing - PLAN CHECK | 9/16/2008 | | 9/24/2008 | | FAIL |
Dan Stuart
|
|
|
Plan correction resubmittals are required. Copy of plan review e-mailed to architect and owner. Plans to fire code analyst for review.
|
Routing - PLANNING | 9/8/2008 | | 9/16/2008 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer.
Tennant Improvements Only.
Routed to Plan Check (Dan).
|
Routing PW Sewer Rating | 9/8/2008 | | 9/8/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PUBLIC WORKS | 9/5/2008 | | 9/8/2008 | | PASS |
Beverly Hall
|
|
|
|
Plan resubmittals received | | | 9/5/2008 | | |
Jason Blais
|
|
|
Received 3 copies of sheets E-1, E-2, E-3 and taken to Jason Blais desk///9-5-08 BAS
|
Pending Assignment by JCB | 9/5/2008 | | 9/5/2008 | | DONE |
Jason Blais
|
|
|
|
Pending Assignment by MYS | 8/13/2008 | | 9/5/2008 | | BLDA |
Marlene Southard
|
|
|
9/5/2008 16:16:51 JCB - activity updated through activity BLDA168 from case BLD08-01759.
|
Telephone call | | | 8/19/2008 | | DONE |
Jason Blais
|
|
|
Talked with architect Lynn Brown. Need Building Permit Application and Registered Design Professional in Responsible Charge form signed. The plans are missing a Lighting Plan with switching, Lighting Fixture Schedule, and a Lighting Compliance COMcheck for the tenant. Lynn said he would also look into the structural engineering change and information for the cantilevered floor joists to support the new restrooms. He thought this was a change in the field on the shell. The plans will be on hold until this information is received.
|
Recd Pcfee & Taken To Pln CK | | | 8/13/2008 | | |
Marsha Smylie
|
|
|
|
Application received | | 8/13/2008 | | | |
Marsha Smylie
|
|
|
|