Third Notice | | 11/8/2010 | 11/30/2010 | | DONE |
|
|
|
mailed//all contact phone numbers disconnected, put company on hold.
|
Third Notice | | 8/30/2010 | 10/25/2010 | | DONE |
|
|
|
mailed
|
Third Notice | | 8/16/2010 | 8/16/2010 | | DONE |
|
|
|
processes with Bld08-02474 (foundation). faxed/didn't go thorough, mailed on 8/17
|
DOC - Permit Finaled | | | 8/13/2010 | | DONE |
Tisha Gallop
|
|
|
ok to Doc Final per Dave Hannah
|
FIRE-Final Inspection | 10/26/2009 | 10/26/2009 | 10/26/2009 | P | PASS |
Forrest France
|
|
|
Life safety final okayed.
|
BLD-Final | 10/23/2009 | 10/26/2009 | 10/26/2009 | P | PASS |
Dave Hannah
|
|
|
Eric ###-####//will meet Aaron out on sit
|
BLD-Framing/Rough-in | 3/24/2009 | 3/25/2009 | 3/25/2009 | A | PASS |
Dave Hannah
|
|
|
After 10 please Phone #: ###-####
|
BLD-Conference | 2/4/2009 | 2/6/2009 | 2/6/2009 | A | PASS |
Dave Hannah
|
|
|
PHIL KRICHBAUN - NOTE: PW AT CONF ASPEN RM 10:00 2 FL Phone #: ###-####
|
BLD-Footing | 2/4/2009 | 2/4/2009 | 2/4/2009 | P | CANC |
Dave Hannah
|
|
|
mike - before 2:30 if possible please Phone #: ###-####
|
BLD-Foundation | 2/4/2009 | 2/4/2009 | 2/4/2009 | P | PASS |
Dave Hannah
|
|
|
mike - before 2:30 if possible please Phone #: ###-####
|
BLD-Footing | 1/30/2009 | 1/30/2009 | 1/31/2009 | P | PASS |
Dave Hannah
|
|
|
mike Note: please footing at 3:00 pm - thanks Phone #: ###-####
|
Issue & PRINT to be Invoiced | | | 12/16/2008 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/12/2008 | | DONE |
Barbara Stitt
|
|
|
|
Inspection Record Card- Bld | | | 12/12/2008 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 12/12/2008 | | DONE |
Barbara Stitt
|
|
|
Sent an email to Mike with Sommer Construction and Jim pardy to let them know the fees due and that the permit is ready for pick up///12-12-08 @ 12:09pm BAS
|
Routing - PLAN CHECK | 12/4/2008 | | 12/8/2008 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLANNING | 12/8/2008 | | 12/8/2008 | | PASS |
Matthew A Halitsky
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/8/2008 | | DONE |
Sam Zahorka
|
|
|
|
Plan assigned to (SRZ) | 8/19/2008 | | 12/8/2008 | | PASS |
Sam Zahorka
|
|
|
12/8/2008 13:42:28 SRZ - activity updated through activity BLDA022 from case BLD08-01776.
|
Routing Off Site - STRUCTURAL | 10/17/2008 | | 12/8/2008 | | PASS |
Sam Zahorka
|
|
|
Routed structural re-submittals back to outsourced structural reviewer. Called Action Courier for pick up10-17-08 @ 2:50pm BAS
|
Routing - PLANNING | 11/26/2008 | | 12/4/2008 | | FAIL |
Matthew A Halitsky
|
|
|
Landscaping plan does not match DR approval.
|
Telephone call | | | 11/26/2008 | | DONE |
Sam Zahorka
|
|
|
Left message for Phil Krichbaum to contact Planning, Matt H.
|
Routing - PLAN CHECK | 10/23/2008 | | 11/26/2008 | | PEND |
Sam Zahorka
|
|
|
Pending others to pass. Routed to Planning.
|
Plan resubmittals received | | | 11/26/2008 | | |
Sam Zahorka
|
|
|
Received 2 cover transmittals and 2 copies of structural computations///11-26-08 BAS
|
Plan Reviewer's activity | | | 10/24/2008 | | DONE |
Sam Zahorka
|
|
|
Recieved structural reviewers comments and emailed to the applicant.
|
Routing - Erosion and Sediment | 10/23/2008 | | 10/23/2008 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC08-00924
|
Routing - Erosion and Sediment | 10/21/2008 | | 10/22/2008 | | FAIL |
Steven Webb
|
|
|
ESC plan does not meet the requirements per BMC 8-17. Plan checklist completed and faxed to applicant. Plan preparer not certified by Boise City. Applicant will need the PD certification and to make the necessary changes and re-submitt.
|
Routing - PLAN CHECK | 10/17/2008 | | 10/21/2008 | | PEND |
Sam Zahorka
|
|
|
Routed resubmittals to ESC.
|
Routing - PLAN CHECK | 10/10/2008 | | 10/17/2008 | | PEND |
Sam Zahorka
|
|
|
Plans have been corrected. Waiting for others to pass. (SRZ)
|
Routing - PUBLIC WORKS | 10/8/2008 | | 10/10/2008 | | PASS |
Beverly Hall
|
|
|
|
Routing PW Drainage | 10/8/2008 | | 10/10/2008 | | PASS |
Brian Murphy
|
|
|
|
Routing - Erosion and Sediment | 10/10/2008 | | 10/10/2008 | | FAIL |
Steven Webb
|
|
|
ESC plan and application is needed. Once this is submitted a review can be performed and when approved permit may be issued.
|
Plan resubmittals received | | | 10/9/2008 | | |
Barbara Stitt
|
|
|
Received 4 sets of sheets A1 of A9, A2 of A9, A5 of A9, A8 of A9, 1 package ofplan review comments for Sam Zahorka, 1 letter to George Slane, 1 letter to Matt Halitsky-insterted into plans and taken back to Brian Murphy's desk///10-9-08 @ 12:10pm BAS
|
Routing - PLAN CHECK | 10/6/2008 | | 10/8/2008 | | PEND |
Sam Zahorka
|
|
|
Routed to Public Works. Pending others to pass.
|
Routing - FIRE | 10/1/2008 | 10/1/2008 | 10/6/2008 | | PASS |
Scott Arellano
|
|
|
No fire review notes attached, see redline notes on plan sheet C-1.Hazmat is below MAQ.
|
1st review completed | | | 10/6/2008 | | FAIL |
|
|
|
Failed plan check.PW and errosion.
|
Route to Impact Fee Review | 10/1/2008 | 10/6/2008 | 10/2/2008 | | PASS |
Cindy M. Gould
|
|
|
|
Case Summary (BLD) | | | 10/1/2008 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/19/2008 | | 10/1/2008 | | FAIL |
Sam Zahorka
|
|
|
Recieved structural review comments. Emailed comments applicant.
|
Routing - PLAN CHECK | 9/18/2008 | | 10/1/2008 | | FAIL |
Sam Zahorka
|
|
|
Emailed plan review report with corrections to the Architect.
|
Plan resubmittals received | | | 9/30/2008 | | |
Sam Zahorka
|
|
|
Kevin Baker with JUB Engineers was in and red marked 5 sets of plans to reflect changes regarding drainage report & revision of O & M manual on sheet C2 and submitted 2 new O & M manuals then plans returned to Sam Zahorka's desk///9-30-08 @ 3:10pm BAS
|
Routing - PLANNING | 9/5/2008 | | 9/18/2008 | | FAIL |
Matthew A Halitsky
|
|
|
Landscaping Plan does not match that approved under DR.
Routed to Plan Check (Sam Z.)
|
Routing - PLUMBING | 8/28/2008 | | 9/5/2008 | | PASS |
Bill VanDegrift
|
|
|
no plumbing
|
Routing - Erosion and Sediment | 8/28/2008 | | 8/28/2008 | | FAIL |
Steven Webb
|
|
|
Need to have a ESC plan and application for review. SGW allowed J. Pardy to submit building package without ESC but the BLD cannot be issued until ESC has been approved.
|
Routing - PUBLIC WORKS | 8/18/2008 | | 8/28/2008 | | FAIL |
Louise Waldorf
|
|
|
|
Routing PW Flood Plain | | | 8/28/2008 | | PASS |
Jim Wyllie
|
|
|
|
Routing PW Street Lights | 8/25/2008 | | 8/28/2008 | | PASS |
Hank Alarcon
|
|
|
|
Routing PW Sewer Design | 8/21/2008 | | 8/25/2008 | | PASS |
Jon R. Gunnerson
|
|
|
Building gernerates no sewer, not required to connect.
|
Routing PW Sewer Rating | 8/25/2008 | | 8/25/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing PW Drainage | 8/19/2008 | | 8/21/2008 | | FAIL |
Brian Murphy
|
|
|
INFILTRATION SYSTEM MUST NOT TERMINATE IN FILL,WEEP HOLES IN FENCE MUST BE LABLED AND O AND M REVISED. BRIAN MURPHY ###-####
|
Routing - PLANNING Land Div | 8/19/2008 | | 8/19/2008 | | PASS |
Joan Johnson
|
|
|
Parcel larger than 5 acres
ok'd w/daa
|
Plan routing begun/NEW & ADDTN | | | 8/18/2008 | | DONE |
Darla L Downs
|
|
|
|
Application received | | 8/15/2008 | 8/15/2008 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/15/2008 | | DONE |
Barbara Stitt
|
|
|
Per Steve Webb ok to accept plans without ESC app and plans as those will be turned in by whomever is awarded the contract. A correct cert of value will be brought in with all of the project values when the contract is awarded. Public works will JV submittal payment///ESC app, plans and new cert of value must be submitted and approved before this permit can be issued///8-15-08 BAS
|