Permanent Occupancy | | | 4/20/2010 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Conference | 4/2/2010 | 4/2/2010 | 4/7/2010 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 7/8/2009 | 7/9/2009 | 7/9/2009 | A | PASS |
Dave Hannah
|
|
|
Eric Phone #: ###-#### ok for perm occ
|
BLD-Final | 5/4/2009 | 5/5/2009 | 5/6/2009 | P | NR |
Dave Hannah
|
|
|
marva Phone #: ###-####
|
BLD-Final | 2/25/2009 | 2/26/2009 | 2/26/2009 | P | PART |
Dave Hannah
|
|
|
Recall for Final Inspection for pm on 2/26/09. Phone #: ###-#### Internet Inspection Request from: Ginger Knickerbocker ok for temp occ ok for perm occ after shell is finaled
|
FIRE-Final Inspection | 2/25/2009 | 2/26/2009 | 2/26/2009 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety passed
|
BLD-Final | 2/23/2009 | 2/24/2009 | 2/25/2009 | P | PART |
Dave Hannah
|
|
|
Requesting pm Final Building Inspection. Phone #: ###-#### Internet Inspection Request from: Ginger Knickerbocker needs fire fimal
|
BLD-Other | 1/28/2009 | 2/2/2009 | 2/2/2009 | A | PART |
Dave Hannah
|
|
|
Requesting an ABOVE CEILING T-BAR INSPECTION for the above date and time. Phone #: ###-#### Internet Inspection Request from: Ginger Knickerbocker ok to cover
|
BLD-Framing/Rough-in | 12/22/2008 | 12/24/2008 | 12/24/2008 | A | PASS |
Dave Hannah
|
|
|
###-#### - erick ok to cover
|
OVERRIDE | | | 12/22/2008 | | |
|
|
|
|
OVERRIDE | | | 12/22/2008 | | |
|
|
|
|
Plan assigned to (CJW) | 12/18/2008 | 12/18/2008 | 12/22/2008 | | PASS |
Carl Westfall
|
|
|
12/22/2008 10:40:26 CJW - activity updated through activity BLDA022 from case BLD08-01783.
|
Override - Parcel Holds | | | 12/22/2008 | | |
|
|
|
|
Routing - PLAN CHECK | 12/18/2008 | | 12/22/2008 | | PASS |
Carl Westfall
|
|
|
Plan modification approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/22/2008 | | DONE |
|
|
|
|
Telephone call | | | 12/22/2008 | | DONE |
|
|
|
left vm for doug cooper at ###-#### - plan mod ready to be picked up and fees given
|
Permit Ready to Issue | | | 12/22/2008 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 12/18/2008 | | |
Carl Westfall
|
|
|
Plan Mod accepted for-lighting layout, revisions to fixture typers for light, new lighting energy calculations. sheets E2.0L & E3.1 submitted for plan mod; no change in value///12-18-08 ALR
|
BLD-Conference | 12/15/2008 | 12/16/2008 | 12/16/2008 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: Ginger Knickerbocker
|
BLD-Conference | 11/30/2008 | 12/1/2008 | 12/1/2008 | A | PART |
Dave Hannah
|
|
|
Any time after 8:30am is good! Ask for Eric. Phone #: ###-#### Internet Inspection Request from: Ginger Knickerbocker talked with contractor about one hr walls
|
Plan assigned to (CJW) | 8/19/2008 | 8/19/2008 | 10/20/2008 | | PASS |
Carl Westfall
|
|
|
10/20/2008 10:33:24 CJW - activity updated through activity BLDA022 from case BLD08-01783.
|
Routing - PLAN CHECK | 9/5/2008 | | 10/20/2008 | | PASS |
Carl Westfall
|
|
|
(9-25-08) Completed the resubmittal review. Wating for the shell permit to be finished. Drawings otherwise approved. (10-20-08) Received an agreement letter signed 10-17-2008 committing that the shell permit will be finished by November 15, 2008. See the agreement letter.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/20/2008 | | DONE |
|
|
|
|
Telephone call | | | 10/20/2008 | | DONE |
|
|
|
t/c w doug cooper at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/20/2008 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/20/2008 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 10/20/2008 | | DONE |
Rita DeYoung
|
|
|
|
Plan resubmittals received | | | 9/22/2008 | | |
|
|
|
received transmittal letter from mckibben + cooper arch, response letter including "2" sheets each with 3 copies, & plan review report (3) pages. also "2" sets of plans with each sheet of code data sheet, AO.2, A2.O, A6.O, A7.O, P1.1, E2.OL, E3.O, & E3.1--plans taken to Carl Westfall.
|
Route to Impact Fee Review | 9/4/2008 | 9/9/2008 | 9/8/2008 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - FIRE | 9/4/2008 | 9/4/2008 | 9/5/2008 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 9/5/2008 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 8/19/2008 | | 9/4/2008 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on September 3, 2008 and was finished the next day. Revised drawings were required. See the plan review report.
|
Routing PW Sewer Rating | 8/19/2008 | | 8/19/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PUBLIC WORKS | 8/19/2008 | | 8/19/2008 | | PASS |
Beverly Hall
|
|
|
|
Pending Assignment by JCB | 8/15/2008 | | 8/19/2008 | | DONE |
Jason Blais
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/18/2008 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/18/2008 | | DONE |
Darla L Downs
|
|
|
|
Application received | | 8/15/2008 | 8/15/2008 | | DONE |
Darla L Downs
|
|
|
|