BLD-Other | 2/9/2010 | 2/9/2010 | 2/9/2010 | A | PASS |
Jim Sly
|
|
|
Inspection to determine that Duplex was built to Townhouse requirements. Two 1hr walls, Laydown parapet, No openings (4' ), Wall protection at property line (eaves) OK. OK to convert to Townhouse.
|
Telephone call | | | 12/29/2009 | | DONE |
Sam Zahorka
|
|
|
Spoke with Dennis about what is still needed to be completed prior to Townhouse conversion permit issuance. The remaining items are: Correct the Survey to show all utilities are within the required easments. Plumbing and Electrical inspectors will verify utilities are within the platted easements as sson as corrected survey is recorded and the city engineer has signed off.
As soon as these two items are completed Plan review will issue conversion permits. SRZ
|
Plan Reviewer's activity | | | 6/25/2009 | | DONE |
Sam Zahorka
|
|
|
Reviewed Preliminary Plat to identify if all utility lines are within easements. After reviewing I determined there is still an issue with the utility lines not within the easements. I shared this information with the Planning/Subdivisions department and they were going to call the Surveyor and have him correct. SRZ
|
BLD-Final | 5/29/2009 | 5/29/2009 | 5/29/2009 | P | PASS |
Jim Sly
|
|
|
Dennis Phone...........Duplex OK'd ONLY .......Need Permit, Zoning approval, and Record prior to Sale of individual units as townhouses.
|
DOC - Permit Finaled | 5/29/2009 | 5/29/2009 | 5/29/2009 | P | PASS |
Jim Sly
|
|
|
|
BLD-Conference | 5/28/2009 | 5/29/2009 | 5/29/2009 | A | DONE |
Jim Sly
|
|
|
Dennis ###-####
|
DOC - Permit Finaled | 5/29/2009 | 5/29/2009 | 5/29/2009 | P | PASS |
Jim Sly
|
|
|
|
BLD-Conference | 5/28/2009 | 5/28/2009 | 5/28/2009 | P | CANC |
Jim Sly
|
|
|
Dennis phone ###-####.....Re-Sched.......
|
BLD-Final | 5/27/2009 | 5/28/2009 | 5/28/2009 | A | CANC |
Jim Sly
|
|
|
Dennis Phone #: ###-####
|
Telephone call | | | 5/8/2009 | | DONE |
Sam Zahorka
|
|
|
Structural inspector notified of request for Duplex to Townhome conversion by plan review. Applicant has been instructed to call for evaluation inspection of property line construction, bring in approved plans and new plans showing compliance for townhouse construction. NOTE: conversion permits and either a recorded subdivision or a zoning certificate and recorded record of survey must be completed prior to selling as individual units. SRZ
|
Telephone call | | | 5/7/2009 | | DONE |
Sam Zahorka
|
|
|
Telephone call with Dave Crawford. Requested applicant to bring in plans showing Townhouse construction for approval. Applicant also needs to schedule an inspection through the front counter for verification of construction. A townhouse conversion permit is required.
|
Case Summary (BLD) | | | 2/13/2009 | | |
|
|
|
|
BLD-Framing/Rough-in | 1/12/2009 | 1/13/2009 | 1/13/2009 | A | PASS |
Jim Sly
|
|
|
dennis Phone #: ###-#### Energy OK
|
Meeting | | | 11/19/2008 | | DONE |
Sam Zahorka
|
|
|
Attended meeting with Dave Abo, Apllicant, and their designer about what needs to happen in order to convert Duplex's to Townhomes. Informed them the 1st step would be to call for an evaluation inspection to see what would need to be corrected for building code compliance. The Second step would be to bring approved plans and new plans showing compliance for townhome construction. The Third step would be to get with the subdivisions department for the record of survey. I also let them know a conversion permit would be required before they would be able to sell them as individual units. SRZ
|
Case Summary (BLD) | | | 11/17/2008 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 10/24/2008 | 10/24/2008 | 10/24/2008 | P | PART |
Jim Sly
|
|
|
dean - party wall Phone #: ###-#### Inside.... 2 1hr walls ok ok to stand...
|
BLD-Framing/Rough-in | 9/17/2008 | 9/17/2008 | 9/17/2008 | P | PART |
Jim Sly
|
|
|
paul - wall inspection Phone #: ###-#### Foundation Wall insp......OK
|
BLD-Footing | 9/10/2008 | 9/10/2008 | 9/10/2008 | P | PASS |
Jim Sly
|
|
|
Paul Phone #: ###-####
|
(F) Reprint permit | | | 9/4/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Issue PAID IN FULL permit | | | 9/4/2008 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/29/2008 | 8/29/2008 | 8/29/2008 | | PASS |
Cindy M. Gould
|
|
|
|
Inspection Record Card- Bld | | | 8/29/2008 | | DONE |
|
|
|
|
Telephone call | | | 8/29/2008 | | DONE |
|
|
|
t/c w dennis mccoy at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/29/2008 | | DONE |
|
|
|
|
Plan assigned to (BSP) | 8/21/2008 | 8/21/2008 | 8/26/2008 | | PASS |
Ben S. Pavelka
|
|
|
8/26/2008 11:32:52 BSP - activity updated through activity BLDA022 from case BLD08-01793.
|
Case Summary (BLD) | | | 8/26/2008 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/21/2008 | | 8/26/2008 | | PASS |
Ben S. Pavelka
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 8/21/2008 | | |
Ben S. Pavelka
|
|
|
|
Routing - PUBLIC WORKS | | | 8/21/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - Addressing | 8/19/2008 | | 8/20/2008 | | PASS |
Chris Pichardo
|
|
|
|
Application received | | 8/19/2008 | | | |
Marsha Smylie
|
|
|
|
Routing - PLANNING | 8/20/2008 | | | | PASS |
Joshua Johnson
|
|
|
Awaiting modfied plans for ornamental gabeled dormers. Plans will still be routed forward
|