Second Notice BLD | 3/4/2009 | 3/4/2009 | 3/10/2009 | | DONE |
Patricia Smith
|
|
|
First Notice has not been responded to.
|
First Notice | | 2/12/2009 | 3/4/2009 | | DONE |
|
|
|
|
Permanent Occupancy | | | 2/12/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
BLD-Final | 2/7/2009 | 2/9/2009 | 2/9/2009 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/7/2009 at 1:56:12 PM. Contact: ###-####. OK for Perm Occ.
|
BLD-Final | 2/5/2009 | 2/6/2009 | 2/6/2009 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/5/2009 at 9:45:34 PM. Contact: ###-####. Talked to Loren......5'x5'landing at bottom of ramp cannot exceed 1/4" per ft slope.
|
BLD-Conference | 2/2/2009 | 2/4/2009 | 2/4/2009 | P | DONE |
Jim Sly
|
|
|
loren - late as possible please Phone #: ###-#### Met with Contr.....
|
BLD-Final | 1/28/2009 | 1/29/2009 | 1/29/2009 | A | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/28/2009 at 9:56:45 AM. Contact: ###-####. Needs to extend curb protection on ramp from were modular building ends. Refer to to aproved plans for handrail extensions. Installed handrail is not code compliant. c/n issued. Also contacted contractor.
|
FIRE-Final Inspection | 1/28/2009 | 1/28/2009 | 1/28/2009 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 1/22/2009 | 1/23/2009 | 1/23/2009 | A | FAIL |
Troy Cobbley
|
|
|
Provide a fire extinguisher as discussed and remove the non functioning fire alarm system.
|
Zoning Approval | 1/23/2009 | 1/23/2009 | 1/23/2009 | | PASS |
Cody Riddle
|
|
|
|
BLD-Final | 1/21/2009 | 1/22/2009 | 1/22/2009 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/21/2009 at 2:53:59 PM. Contact: ###-####. Need ACHD, Zoning, Electr, and Fire/Life prior to Struct insp......
|
BLD-Other | 11/5/2008 | 11/6/2008 | 11/6/2008 | A | PASS |
Jim Sly
|
|
|
larry Note: check support and tie for modular classroom Phone #: ###-#### plan inside door has the bld pemit taped
|
Issue PAID IN FULL permit | | | 10/8/2008 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/22/2008 | | DONE |
|
|
|
|
Telephone call | | | 9/22/2008 | | DONE |
|
|
|
t/c w larry roberts at ###-#### - permit ready and fees given - also need gc name, rce# and ACHD receipt
|
Permit Ready to Issue | | | 9/22/2008 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 9/8/2008 | 9/8/2008 | 9/19/2008 | | PASS |
Sam Zahorka
|
|
|
9/19/2008 16:04:04 SRZ - activity updated through activity BLDA022 from case BLD08-01846.
|
Routing PW Drainage | 9/19/2008 | | 9/19/2008 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 9/19/2008 | | 9/19/2008 | | PASS |
Beverly Hall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2008 | | DONE |
|
|
|
|
Routing - FIRE | 9/16/2008 | 9/16/2008 | 9/18/2008 | | PASS |
Scott Arellano
|
|
|
See IFC fire review notes attached.
|
1st review completed | | | 9/18/2008 | | FAIL |
|
|
|
P/W and sewer
|
Routing - PLAN CHECK | 9/18/2008 | | 9/18/2008 | | PASS |
Brian Murphy
|
|
|
Pending Public Works to pass. Routed back to Brian Murphy.
|
Route to Impact Fee Review | 9/16/2008 | 9/19/2008 | 9/17/2008 | | PASS |
Cindy M. Gould
|
|
|
|
Case Summary (BLD) | | | 9/16/2008 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/2/2008 | | 9/16/2008 | | PASS |
Sam Zahorka
|
|
|
Pending others to pass.
|
Plan resubmittals received | | | 9/15/2008 | | |
Tisha Gallop
|
|
|
received letter addressing drainage issues (existing roof funoff analysis); inserted into plans by LEG and taken back to Sam Z.
|
Route to Impact Fee Review | 9/9/2008 | 9/12/2008 | 9/9/2008 | | PASS |
Cindy M. Gould
|
|
|
|
Telephone call | | | 9/9/2008 | | DONE |
Sam Zahorka
|
|
|
Left message with the applicant to call me back at ###-####. The applicant needs to call Brian Murphy with Public Works at ###-####.
|
Plan assigned to (SRZ) | 8/28/2008 | 8/28/2008 | 9/5/2008 | | PASS |
Sam Zahorka
|
|
|
9/5/2008 15:02:45 PEP - activity updated through activity BLDA022 from case BLD08-01856.
|
Routing PW Drainage | 8/29/2008 | | 9/2/2008 | | FAIL |
Brian Murphy
|
|
|
NEEDS DRAINAGE PLAN. BRIAN MURPHY ###-####
|
Routing PW Sewer Rating | 9/2/2008 | | 9/2/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PUBLIC WORKS | 8/29/2008 | | 9/2/2008 | | FAIL |
Louise Waldorf
|
|
|
Contact Brian Murphy ###-####
|
Routing - PLANNING | 9/2/2008 | | 9/2/2008 | | PASS |
Cody Riddle
|
|
|
Cup08-00083 Cody
|
Routing - PLANNING Land Div | 8/28/2008 | | 8/29/2008 | | PASS |
Joan Johnson
|
|
|
Property is the same configuration now as it was when it was annexed.
|
Plans ACCEPTED BY PLAN TECH | | | 8/28/2008 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/28/2008 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 8/27/2008 | 8/27/2008 | | DONE |
Tisha Gallop
|
|
|
|