Third Notice | | 8/11/2009 | 8/21/2009 | | DONE |
|
|
|
|
Second Notice | | 7/24/2009 | 8/11/2009 | | DONE |
|
|
|
|
First Notice | | 7/8/2009 | 7/24/2009 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 7/8/2009 | | DONE |
Tisha Gallop
|
|
|
|
Zoning Approval | 7/6/2009 | 7/6/2009 | 7/7/2009 | | DONE |
Matthew A Halitsky
|
|
|
Lack of perimeter landscaping OK per S. Schafer.
|
BLD-Final | 7/1/2009 | 7/2/2009 | 7/2/2009 | P | PASS |
Tom Arcoraci
|
|
|
Mike Phone #: ###-####
|
FIRE-Final Inspection | 7/1/2009 | 7/2/2009 | 7/2/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. The racks will be limited to no more than 8'-0" in height.
|
PubWorks Occupancy Approval | 7/2/2009 | 7/2/2009 | 7/2/2009 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval Temp | 7/2/2009 | 7/2/2009 | 7/2/2009 | | FAIL |
Matthew A Halitsky
|
|
|
Bond needed for replacing gravel with bark, add awnings.
|
BLD-Other | 6/15/2009 | 6/15/2009 | 6/15/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 6/12/2009 | 6/15/2009 | 6/15/2009 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 6/12/2009 at 2:00:52 PM. Contact: ###-####.
|
BLD-Other | 5/7/2009 | 5/7/2009 | 5/7/2009 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 5/7/2009 at 10:19:27 AM. Contact: ###-####.
|
BLD-Energy code compliance | 4/30/2009 | 5/1/2009 | 5/1/2009 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/30/2009 at 5:08:40 PM. Contact: ###-####.
|
BLD-Conference | 4/22/2009 | 4/22/2009 | 4/22/2009 | P | PASS |
Tom Arcoraci
|
|
|
Mike Phone #: ###-####
|
BLD-Other | 3/20/2009 | 3/20/2009 | 3/20/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 3/18/2009 | 3/19/2009 | 3/19/2009 | A | PASS |
Tom Arcoraci
|
|
|
Mike- roof drain Phone #: ###-####
|
BLD-Concrete | 3/13/2009 | 3/16/2009 | 3/16/2009 | P | PASS |
Tom Arcoraci
|
|
|
mike - rebar Phone #: ###-####
|
BLD-Foundation | 1/14/2009 | 1/15/2009 | 1/15/2009 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/14/2009 at 4:58:42 PM. Contact: ###-####.
|
BLD-Footing | 1/9/2009 | 1/12/2009 | 1/12/2009 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/9/2009 at 4:53:01 PM. Contact: ###-####. wip ok
|
BLD-Footing | 1/5/2009 | 1/5/2009 | 1/5/2009 | P | PASS |
Tom Arcoraci
|
|
|
mike Note: rebar Phone #: ###-####
|
BLD-Footing | 12/22/2008 | 12/23/2008 | 12/22/2008 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/22/2008 at 4:55:01 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Dec 22 2008 5:04PM.
|
BLD-Footing | 12/19/2008 | 12/22/2008 | 12/22/2008 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/19/2008 at 4:58:16 PM. Contact: ###-####. wip footings ok
|
BLD-Footing | 12/16/2008 | 12/17/2008 | 12/17/2008 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/16/2008 at 4:45:25 PM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 11/21/2008 | | DONE |
|
|
|
|
OVERRIDE | | | 11/12/2008 | | |
|
|
|
|
Routing - PLAN CHECK | 11/3/2008 | | 11/12/2008 | | PASS |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 11/7/2008 | | 11/12/2008 | | PASS |
John Menard
|
|
|
called Action Couriers for pick up - Received letter from consulting structural engineer approval resubmitted, revised structural documents. JCM
|
Plan Reviewer's activity | | | 11/12/2008 | | PASS |
John Menard
|
|
|
Reviewed and approved resubmitted, revised plan sheets with red lined notes. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2008 | | DONE |
John Menard
|
|
|
|
Print Occupancy Form | | | 11/12/2008 | | DONE |
|
|
|
|
Telephone call | | | 11/12/2008 | | DONE |
|
|
|
t/c w dion zimmerman at ###-#### - permit ready and fees given - also need ACHD receipt and rp name
|
Override - People Holds | | | 11/12/2008 | | |
|
|
|
|
Permit Ready to Issue | | | 11/12/2008 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 9/2/2008 | | 11/12/2008 | | PASS |
John Menard
|
|
|
11/12/2008 14:28:02 JCM - activity updated through activity BLDA022 from case BLD08-01871.
|
Plan resubmittals received | | | 11/5/2008 | | |
John Menard
|
|
|
Rec'd two response letters, three copies of structral calcs, and three copies of sheets S1.0, S2.0 and A3.0; inserted by arch rep; taken back to John M
|
Plan resubmittals requested | | | 11/3/2008 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the second structural review requesting additional revisions. JCM
|
Routing - FIRE | 10/29/2008 | | 11/3/2008 | | PASS |
Scott Arellano
|
|
|
Attached updated IFC comments to plans
|
Routing Off Site - STRUCTURAL | 10/24/2008 | | 10/31/2008 | | FAIL |
John Menard
|
|
|
called Action Couriers for pick up - Received correction list from the consulting structural engineer requesting additional revisions. JCM
|
Plan resubmittals received | | | 10/30/2008 | | |
|
|
|
received "2" sheets each of C2.O1, C2.O2, A1.O, A3.O, A4.O, & S1.O--plans taken back to Scott Arrellano--inserter is Jo Larson
|
Routing - PLAN CHECK | 10/27/2008 | | 10/29/2008 | | FAIL |
John Menard
|
|
|
|
Plan resubmittals requested | | | 10/28/2008 | | DONE |
John Menard
|
|
|
E-mailed the architect a letter requesting additional revisions. JCM
|
Routing - PLUMBING | 10/22/2008 | | 10/27/2008 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Plan resubmittals received | | | 10/23/2008 | | |
John Menard
|
|
|
Rec'd a response letter, structural cals and 1 copy of page S1.0 and S2.0; taken to John M.
|
Routing PW Drainage | | | 10/22/2008 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 10/21/2008 | | 10/22/2008 | | PASS |
Beverly Hall
|
|
|
|
Plan resubmittals requested | | | 10/21/2008 | | DONE |
John Menard
|
|
|
E-mailed the architect requesting a third set of structural revisions. JCM
|
Routing PW Solid Waste | 10/21/2008 | | 10/21/2008 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Environmental | 10/21/2008 | | 10/21/2008 | | PASS |
Terry Alber
|
|
|
|
Routing - PLAN CHECK | 10/13/2008 | | 10/21/2008 | | |
John Menard
|
|
|
|
Plan resubmittals received | | | 10/20/2008 | | |
John Menard
|
|
|
Rec'd two copies of HAZMAT report and two copies of sheet G1.0; insterted by arch rep; taken to John M
|
Plan resubmittals received | | | 10/17/2008 | | |
Barbara Stitt
|
|
|
Received 2 copies of letter to Bill VanDeGrift, Scott Arellano with a copy of CCNR's attached, John Menard, Peter McCullough, structural calcs, ground water research letter, drainage report, O & M, sheets C1.0, C2.01, C2.02, A1.0, A3.0, A4.0, S1.0, S2.0, P1.1, P2.1, P3.1 and inserted into plans by Zimmerman's office then returned to John Menard's desk///10-17-08 @ 3:20pm BAS
|
Routing - FIRE | 10/7/2008 | 10/7/2008 | 10/13/2008 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 10/13/2008 | | FAIL |
|
|
|
Failed PW, Structural, Plumbing, Planning, Plan Check, Fire
|
Route to Impact Fee Review | 10/9/2008 | 10/14/2008 | 10/9/2008 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals requested | | | 10/7/2008 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Routing - PLAN CHECK | 9/18/2008 | | 10/7/2008 | | FAIL |
John Menard
|
|
|
John Menard
|
Routing - PLANNING | 9/12/2008 | | 9/18/2008 | | PASS |
Matthew A Halitsky
|
|
|
DRH08-00159 Matt Halitsky
Routed to Plan Check (John M.)
|
Routing - PLUMBING | 9/10/2008 | | 9/12/2008 | | FAIL |
Bill VanDegrift
|
|
|
provide approved interceptor detail, show venting. trap and vent area drain upstream of the interceptor. show water line and r.p. to wash bay. show required drinking fountain.
|
Routing - Erosion and Sediment | 9/9/2008 | | 9/10/2008 | | PASS |
Clint A Smith
|
|
|
ESC plan waiver approved with attched conditions. ESC08-00732
|
Routing - PUBLIC WORKS | 9/4/2008 | | 9/9/2008 | | FAIL |
Louise Waldorf
|
|
|
|
Routing PW Solid Waste | 9/8/2008 | | 9/9/2008 | | FAIL |
Peter J. McCullough
|
|
|
Details are required on the trash enclosure. See the Solid Waste Plan Submittal Checklist at www.cityofboise.org/Departments/Public_Works/NewDevelopmentPermitApps/page29449.aspx.
Also, confirmation is required that storage yard leading to trash enclosure will be paved.
|
Routing PW Environmental | | | 9/9/2008 | | FAIL |
Terry Alber
|
|
|
SHOW WASH PAD & INTERCEPTOR ON REVISED PLUMBING PLANS
|
Plan resubmittals requested | | | 9/8/2008 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 9/2/2008 | | 9/8/2008 | | FAIL |
John Menard
|
|
|
Received comment list from consulting structural engineer requesting revisions. JCM
|
Routing PW Drainage | | | 9/8/2008 | | FAIL |
Brian Murphy
|
|
|
NEED MORE INFO IN GEO TECH REPORT AND DESIGN FOR BYPASS OF SAND FILTER IN DESIGN.. BRIAN MURPHY ###-####
|
Routing PW Sewer Rating | 9/8/2008 | | 9/8/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing PW Street Lights | 9/4/2008 | | 9/5/2008 | | PASS |
Hank Alarcon
|
|
|
|
Routing PW Sewer Design | 9/4/2008 | | 9/4/2008 | | PASS |
Jon R. Gunnerson
|
|
|
Connect onto 4-inch service provided.
|
Routing - PLANNING Land Div | 9/3/2008 | | 9/4/2008 | | PASS |
Todd Tucker
|
|
|
Parcel is a platted lot in a subdivision.
|
Plan routing begun/NEW & ADDTN | | | 9/3/2008 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/2/2008 | | DONE |
Tisha Gallop
|
|
|
Called Action Couriers for pick up
|
Plans ACCEPTED BY PLAN TECH | | | 9/2/2008 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/2/2008 | | DONE |
Tisha Gallop
|
|
|
|
Pending Assignment by JCM | 9/2/2008 | | 9/2/2008 | | DONE |
John Menard
|
|
|
9/2/2008 11:13:35 JCM - activity updated through activity BLDA166 from case BLD08-01871.
|
Application received | | 8/29/2008 | | | |
Tisha Gallop
|
|
|
|