Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD08-01956
StatusFinaled
Name ST LUKES REG MED CNTR
Site Address 222 N 2ND ST Unit: 204
Project NameANDERSON PLAZA
Customer Number 
ePlanReviewNo
Description
(DR. DAVIS) Interior remodel to add 800 sq. ft. to an existing 1,215 sq. ft. office space. The new total tenant space area will be 2,016 sq. ft. This building is not sprinklered. There is a 1-hour rated exit corridor serving this space and connecting two exit enclosure's serving the second floor. Work to include: perform selective interior demolition within the current tenant area. To construct new interior walls to create new exam rooms, procedure room, waiting areas, reception, storage rooms, office, and support areas. Portions of the rated corridor will be modified to relocate or remove doors and install new rated door assemblies as required for rated corridors. Install new ceiling grid and tiles in specified locations; new accessible millwork and sinks; complete new interior finishes; upgrade electical, mechanical and plumbing. All work per the approved plans, and attached plan review report. **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 7/22/20099/8/2009 DONE
First Notice 4/3/20097/22/2009 DONE
Permanent Occupancy  4/3/2009 DONE
DetailsBarbara Stitt
BLD-Final1/13/20091/14/20091/14/2009APASS
DetailsDave Hannah
Daryl Phone #: ###-#### ok for perm occ
BLD-Final1/9/20091/12/20091/12/2009ANR
DetailsDave Hannah
DAREL Phone #: ###-#### needs an elec final first
FIRE-Final Inspection1/7/20091/8/20091/8/2009APASS
DetailsForrest France
Fire life safety passed, contractor to provide one additional fire extinguisher to be mounted as discussed-to be verified at structural final.
BLD-Framing/Rough-in12/8/200812/9/200812/9/2008APASS
DetailsDave Hannah
daryl Phone #: ###-####
BLD-Framing/Rough-in11/14/200811/17/200811/18/2008APART
DetailsDave Hannah
ceiling grid inspection please--darryl Phone #: ###-#### ok to cover ceiling
BLD-Framing/Rough-in10/28/200810/29/200810/29/2008APART
DetailsDave Hannah
daryl Phone #: ###-#### ok to cover walls
Issue & PRINT to be Invoiced  10/14/2008 DONE
Routing - PLAN CHECK10/9/2008 10/13/2008 PASS
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  10/13/2008 DONE
DetailsSam Zahorka
Print Occupancy Form  10/13/2008 DONE
Details
Telephone call  10/13/2008 DONE
Details
left vm for curtis at ###-#### - permit ready and fees given
Permit Ready to Issue  10/13/2008 DONE
Details
Plan assigned to (SRZ)9/12/2008 10/13/2008 PASS
DetailsSam Zahorka
10/13/2008 11:37:52 SRZ - activity updated through activity BLDA022 from case BLD08-01956.
Routing - FIRE10/7/200810/7/200810/9/2008 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  10/9/2008 PASS
Route to Impact Fee Review10/7/200810/10/200810/7/2008 PASS
DetailsCindy M. Gould
Tenant improvement no fees
Routing - PLAN CHECK  10/7/2008 PEND
DetailsSam Zahorka
Others to pass.
Case Summary (BLD)  10/7/2008 DONE
Routing - PUBLIC WORKS9/12/2008 9/15/2008 PASS
DetailsBeverly Hall
Pending Assignment by JCB9/11/2008 9/12/2008 DONE
DetailsJason Blais
Application received 9/10/20089/10/2008 DONE
DetailsAlexandra L. DeYoung
Case Summary (BLD)  9/10/2008 DONE
Plans ACCEPTED BY PLAN TECH  9/10/2008 DONE
DetailsAlexandra L. DeYoung
Recd Pcfee & Taken To Pln CK  9/10/2008 DONE
DetailsAlexandra L. DeYoung