Second Notice BLD | 3/4/2009 | 3/4/2009 | 3/5/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
First Notice has not been responded to.
|
First Notice | | 1/26/2009 | 3/4/2009 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 1/27/2009 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/27/2009 | | DONE |
Tisha Gallop
|
|
|
reprint perm. occ. card with new address approved by Chris P.
|
BLD-Final | 1/23/2009 | 1/26/2009 | 1/26/2009 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 1/22/2009 at 3:55:52 PM. ok for c of o,, tenant not moved into yet
|
Permanent Occupancy UNPAID FEE | | | 1/26/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
|
BLD-Final | 1/22/2009 | 1/23/2009 | 1/23/2009 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 1/22/2009 at 3:55:52 PM. temp ok,, need proper address, letter from struct ok on opening
|
FIRE-Final Inspection | 1/22/2009 | 1/23/2009 | 1/23/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 1/21/2009 | 1/22/2009 | 1/22/2009 | P | FAIL |
Troy Cobbley
|
|
|
The project related fire sprinkler permit needs to be finaled and the two missing exit signs installed and tested.
|
BLD-Framing/Rough-in | 12/18/2008 | 12/19/2008 | 12/19/2008 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/18/2008 at 9:29:36 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 12/11/2008 | 12/11/2008 | 12/11/2008 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/11/2008 at 8:11:17 AM. Contact: ###-####. interior walls ok to cover
|
BLD-Framing/Rough-in | 12/3/2008 | 12/4/2008 | 12/4/2008 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/3/2008 at 2:39:41 PM. Contact: ###-####. sky light framing ok per plan
|
BLD-Framing/Rough-in | 12/1/2008 | 12/2/2008 | 12/1/2008 | A | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/1/2008 at 12:46:31 PM. Contact: ###-####. Inspection cancelled from web by: Patricia Smith
|
Issue PAID IN FULL permit | | | 11/13/2008 | | |
|
|
|
|
Routing - PLAN CHECK | 11/10/2008 | | 11/12/2008 | | PASS |
Dan Stuart
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2008 | | PASS |
|
|
|
|
Print Occupancy Form | | | 11/12/2008 | | DONE |
|
|
|
|
Telephone call | | | 11/12/2008 | | DONE |
|
|
|
left vm for stephanie at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 11/12/2008 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 9/16/2008 | | 11/12/2008 | | PASS |
Dan Stuart
|
|
|
11/12/2008 09:23:58 DRS - activity updated through activity BLDA022 from case BLD08-01965.
|
Routing - FIRE | 11/6/2008 | | 11/10/2008 | | PASS |
Scott Arellano
|
|
|
See attached IFC fire review notes.
|
Plan resubmittals received | | | 11/10/2008 | | DONE |
|
|
|
received 1 transmittal. 1 legacy report, and 2 copies of sheets S1.0,A0.01,A3.01,P-1 taken to Dan S.
|
Routing - PLAN CHECK | 10/15/2008 | | 11/6/2008 | | FAIL |
Dan Stuart
|
|
|
Resubmittals are incomplete. Copy of remaining items needing to be addressed e-mailed to Stephanie. Plans to fire code analyst for re-review.
|
Plan resubmittals requested | | | 11/6/2008 | | DONE |
|
|
|
E-mailed report to Stephanie.
|
Plan resubmittals received | | | 11/4/2008 | | |
Dan Stuart
|
|
|
Received 1 cover transmittal, information for drinking fountain, responce from Kartchner Engineering, response from Treasure Valley Engineers, Project Start up for Special inspections, calcs for steel column, 2 copies of sheets A0.01, A0.02, A0.04, A2.01, A0.03, A5.01, A3.01, M-1, M-2, E-1, E-2, P-1, S1.0 and taken to Dan Stuart's desk///11-4-08 @ 8:35am BAS
|
Route to Impact Fee Review | 10/14/2008 | 10/17/2008 | 10/15/2008 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Routing - FIRE | 10/14/2008 | 10/14/2008 | 10/15/2008 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 10/15/2008 | | FAIL |
|
|
|
Failed Plan Check, Fire
|
Plan resubmittals requested | | | 10/14/2008 | | DONE |
|
|
|
PLAN REVIEW RESUBMITTAL REQUIREMENTS E-MAILED TO ARCHITECT.
|
Print Pending Permit.LaserJet4 | | | 10/14/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 10/14/2008 | | |
|
|
|
|
Routing - PLAN CHECK | 9/17/2008 | | 10/14/2008 | | FAIL |
Dan Stuart
|
|
|
COPY OF PLAN REVIEW E-MAILED TO ARCHITECT FOR RESUBMITTAL RESPONSE. PLAN ROUTED TO FIRE CODE ANALYST FOR REVIEW.
|
Routing - Design Review | 9/17/2008 | | 9/17/2008 | | PASS |
Andrea Tuning
|
|
|
Approved per CZC08-00142
|
Routing - PUBLIC WORKS | 9/16/2008 | | 9/17/2008 | | PASS |
Beverly Hall
|
|
|
|
Pending Assignment by JCB | 9/12/2008 | | 9/16/2008 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/12/2008 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/12/2008 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 9/11/2008 | | | |
Tisha Gallop
|
|
|
|