Third Notice BLD | 1/29/2009 | 1/29/2009 | 3/16/2009 | | DONE |
Patricia Smith
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 1/2/2009 | 1/2/2009 | 1/29/2009 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | | 11/19/2008 | 1/2/2009 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/19/2008 | 11/19/2008 | 11/19/2008 | A | PASS |
Forrest France
|
|
|
Fire life safety finaled, see activity completed 11/13.
|
Permanent Occupancy UNPAID FEE | | | 11/19/2008 | | |
|
|
|
|
BLD-Final | 11/13/2008 | 11/14/2008 | 11/14/2008 | A | PASS |
Jim Storey
|
|
|
don Phone #: ###-####
|
FIRE-Final Inspection | 11/12/2008 | 11/13/2008 | 11/13/2008 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
FIRE-Alarm Testing | 11/12/2008 | 11/13/2008 | 11/13/2008 | A | DONE |
Forrest France
|
|
|
don Phone #: ###-####
|
BLD-Final | 11/12/2008 | 11/12/2008 | 11/12/2008 | P | NR |
Tom Arcoraci
|
|
|
Don Phone #: ###-####
|
FIRE-Conference | 10/22/2008 | 10/22/2008 | 10/23/2008 | P | DONE |
Forrest France
|
|
|
Regarding sheetrock at full height wall for fire sprinkler separation at the 2nd floor.
|
BLD-Framing/Rough-in | 10/20/2008 | 10/20/2008 | 10/20/2008 | P | PASS |
Jim Storey
|
|
|
don Phone #: ###-####
|
Print Occupancy Form | | | 10/7/2008 | | DONE |
|
|
|
|
Telephone call | | | 10/7/2008 | | DONE |
|
|
|
t/c w walt at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/7/2008 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/7/2008 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (TLW) | 9/17/2008 | | 10/6/2008 | | PASS |
Tim L. Woodard
|
|
|
10/6/2008 15:52:57 TLW - activity updated through activity BLDA022 from case BLD08-01970.
|
1st review completed | | | 10/6/2008 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/6/2008 | | DONE |
|
|
|
|
Routing - FIRE | | | 10/6/2008 | | PASS |
Tim L. Woodard
|
|
|
Field Verify
|
Routing - PLAN CHECK | 9/16/2008 | | 10/6/2008 | | PASS |
Tim L. Woodard
|
|
|
|
Plan assigned to (DRS) | 9/15/2008 | | 9/17/2008 | | DONE |
Dan Stuart
|
|
|
Plans reassigned to Tim Woodard.
|
Routing - PUBLIC WORKS | 9/15/2008 | | 9/16/2008 | | PASS |
Beverly Hall
|
|
|
|
Pending Assignment by JCB | 9/11/2008 | | 9/15/2008 | | DONE |
Jason Blais
|
|
|
|
Routing PW Sewer Rating | 9/15/2008 | | 9/15/2008 | | PASS |
Louise Waldorf
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/11/2008 | | |
Marsha Smylie
|
|
|
|
Application received | | 9/11/2008 | | | |
Marsha Smylie
|
|
|
|