Second Notice BLD | 1/2/2009 | 1/2/2009 | 1/5/2009 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | 12/9/2008 | 12/9/2008 | 1/2/2009 | | DONE |
Jim Storey
|
|
|
|
PubWorks Occupancy Approval | 12/16/2008 | 12/16/2008 | 12/16/2008 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 12/8/2008 | 12/9/2008 | 12/9/2008 | A | PASS |
Forrest France
|
|
|
Site inspection passed.
|
BLD-Final | 12/8/2008 | 12/9/2008 | 12/9/2008 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/8/2008 at 3:06:36 PM. Contact: ###-####.
|
DOC - Permit Finaled | 12/9/2008 | 12/9/2008 | 12/9/2008 | P | PASS |
Jim Storey
|
|
|
|
Zoning Approval | 12/9/2008 | 12/9/2008 | 12/9/2008 | | PASS |
Josh Wilson
|
|
|
|
Letter of compliance | | | 12/9/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Case Summary (BLD) | | | 11/6/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 10/16/2008 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 10/16/2008 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 10/16/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Routing - PLANNING | 10/15/2008 | | 10/16/2008 | | PASS |
Josh Wilson
|
|
|
DRH08-00303 Josh Wilson- added two planter sites around building
|
Routing PW Drainage | 10/14/2008 | | 10/15/2008 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 10/14/2008 | | 10/15/2008 | | PASS |
Beverly Hall
|
|
|
|
Plan resubmittals received | | | 10/14/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
Rec'd 1 response letter, and 4 copies of pages C100, C110, C200, C300, and C310, and 3 copies of page L1.01; inserted into plans by permit tech; re-routed to public works
|
Plan resubmittals received | | | 10/10/2008 | | DONE |
Tisha Gallop
|
|
|
Received transmittal and two copies of sheet L1.01 and E1.0; routed to Josh W.
|
Routing - PLANNING | 10/10/2008 | | 10/10/2008 | | PASS |
Josh Wilson
|
|
|
OK per revised landscape plan
|
Plan resubmittals received | | | 10/9/2008 | | |
Barbara Stitt
|
|
|
Received 1 cover transmittal and 2 copies of L1.01 and E1.0 and inserted into plans///10-9-08 BAS
|
Telephone call | | | 10/7/2008 | | DONE |
Tisha Gallop
|
|
|
called Doug Watson and told him plans failed PW Drainage and need to turn in resubmittals to re-route plans//10/7/08 LEG
|
1st review completed | | | 10/7/2008 | | FAIL |
|
|
|
Failed PW
|
Routing - FIRE | 10/6/2008 | | 10/7/2008 | | PASS |
Scott Arellano
|
|
|
No comments attached.
|
Routing - Erosion and Sediment | 10/3/2008 | | 10/6/2008 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions. ESC08-00830
|
Routing - PLANNING | 10/6/2008 | | 10/6/2008 | | PASS |
Josh Wilson
|
|
|
DRH08-00303 Josh Wilson
|
Routing - PUBLIC WORKS | 10/1/2008 | | 10/3/2008 | | FAIL |
Louise Waldorf
|
|
|
Contact Brian Murphy ###-####
|
Routing PW Drainage | 10/1/2008 | | 10/3/2008 | | FAIL |
Brian Murphy
|
|
|
ALL STORMWATER MUST GO THRU SAND FILTER. BRIAN MURPHY ###-####
|
Routing PW Street Lights | | | 10/3/2008 | | PASS |
Hank Alarcon
|
|
|
|
Routing PW Sewer Rating | 10/3/2008 | | 10/3/2008 | | PASS |
Louise Waldorf
|
|
|
|
Routing - PLANNING Land Div | 9/29/2008 | | 10/1/2008 | | PASS |
Todd Tucker
|
|
|
Parcel was created with a property line adjustment and a parcel consolodation.
|
Plan routing begun/NEW & ADDTN | | | 9/29/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/29/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/29/2008 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Application received | | 9/26/2008 | | | |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 10/16/2008 | | | | |
|
|
|
|
Routing - PLAN CHECK | 10/7/2008 | | | | PEND |
Tisha Gallop
|
|
|
pending resubmittals to re-route to PW for grading/drainage
|
Routing - PLAN CHECK | | | | | |
Tisha Gallop
|
|
|
Tisha Gallop
|